The purpose of MHHS Qualification was to confirm that Parties were ready to operate under the required industry processes and standards for the new Market-wide Half Hourly Settlement (MHHS) arrangements. All REC Parties wanting to operate in the new market arrangements needed to qualify through MHHS Qualification.
MHHS Qualification has now completed and all future qualification is being managed under the enduring process that supports the MHHS arrangements.
Previous information on MHHS Qualification
All existing Distribution Network Operators (DNOs) are expected to be Qualified ahead of the migration period commencing. Qualification of Suppliers and Meter Operator Agents (MOAs) will be delivered through multiple Qualification Waves, by completing Qualification Testing (QT) starting before migration commences, and continuing through live operations.
Parties that volunteered for System Integration Testing (SIT) will not be expected to complete QT unless there is a gap between the testing they successfully completed in SIT, and the REC MHHS Qualification Assessment Criteria.
- Suppliers are not able to migrate Metering Points to the new MHHS arrangements until they are MHHS Qualified
- Meter Operator Agents cannot be appointed to MHHS Metering Points until they are MHHS Qualified
The MHHS arrangements allow for a period where ‘Reverse Migration’ is possible. This applies where a Supplier who is not yet MHHS Qualified registers a Metering Point that has already been through migration (and is being settled under MHHS arrangements). The MHHS Programme has specified a milestone (M14) part way through the MHHS migration period when all Suppliers must be MHHS Qualified. At this point Reverse Migration will cease and only Suppliers who are MHHS Qualified will be able to register Metering Points, via a Switch. This is true for all migrated or non-migrated Metering Points.
The Retail Energy Code (REC) and Balancing and Settlement Code (BSC) Code Bodies have been working together to develop a suite of documentation for REC Parties to understand and complete MHHS Qualification:
Qualification Approach & Plan
The REC and BSC Code Bodies and have developed an initial iteration of the MHHS Qualification Approach and Plan (QA&P). This document sets out the high-level approach to REC and BSC MHHS Qualification and is available via the MHHS Programme website.
The QA&P outlines the key requirements that Parties will have to follow to complete MHHS Qualification, an outline of the roles and responsibilities, and includes an appendix with the expected timeframe for the Qualification activities broken down by Wave. There are additionally 4 annexes to the QA&P:
- Annex 1: Non-SIT Licensed Distribution System Operator (LDSO - known as DNOs in the REC) MHHS Qualification Testing Approach
- Annex 2: Non-SIT Supplier & Agent MHHS Qualification Testing Approach
- Annex 3: New Entrant Non-SIT LDSO MHHS Qualification Testing Approach (first draft due to be published Autumn 2024)
- Annex 4: Non-Completion of Qualification
Qualification Assessment Document
To support the Qualification process, all participants wanting to operate in the new market arrangements will need to complete a Qualification Assessment Document (QAD), providing REC and BSC Code Bodies with information regarding their MHHS delivery (including evidence from relevant test phases). The Code Bodies will use the information in the QAD to assess whether Parties have provided sufficient evidence to demonstrate they have the appropriate systems, processes and controls in place to meet the MHHS requirements as outlined in the respective Codes. All Parties are required to submit the QAD, whether they are completing QT or SIT.
A reference copy of the QAD is available in the Qualification section on the MHHS website, however the QAD will be submitted via the QAD Portal (SOFY).
Further information on the QAD Portal can be found via the ‘Qualification Assessment Document (QAD) Portal Walkthrough: 18 June 2024’ MHHS Webinar.
Requirement to Test Traceability Matrix
The REC and BSC Code Bodies have provided Requirement to Test Traceability Matrix (RTTM) templates for each non-SIT Party type to support the assessment of testing activity. They clarify minimum requirements for test execution in Pre-Integration Testing (PIT) and will set out what is expected for QT as well as any evidence that must be provided – for example, to support the QAD submission. Parties are required to complete the template to show that all tests have been executed and to provide evidence of this. The RTTMs are available via the MHHS Programme website under the Qualification Overview section.
REC MHHS Assessment Criteria
The purpose of MHHS Qualification is for the REC Code Manager and BSC to assess whether their Parties have the appropriate systems, processes and controls in place to be able to operate in the Market in-line with their obligations under the respective codes.
Parties will be completing various activities, including PIT, SIT/QT, and the QAD to be able to demonstrate that they will be able to comply with their code obligations. The REC Assessment Criteria for MHHS Qualification captures and maps which of these activities the REC Code Manager requires Parties to complete for the various MHHS Requirements.
Pre-Qualification Submission
New Suppliers, MOAs, and DNOs who are currently going through the REC Market Entry process will also be required to complete MHHS Qualification; further information on the interaction between REC and MHHS Qualification requirements can be found in the REC Entry Assessment Information Pack under Category 3 Products in the REC Portal.
Parties that intend to complete MHHS Qualification with the MHHS Programme should notify PPC@mhhsprogramme.co.uk that they will be participating in the MHHS Programme and complete a Pre-Qualification Submission (PQS) to formalise this request. The purpose of the PQS is for Parties to outline when they intend to complete MHHS Qualification, and to provide further context on the Qualification activities they will be completing. Existing REC Parties should have already completed a PQS in April 2024.
How to keep up to date
The MHHS Programme has multiple Working Groups around MHHS Qualification to provide Programme Participants with updates to the MHHS Qualification Approach and Plan; further information on these Working Groups can be found under ‘Qualification Level 4 Working Groups and Subgroups’ under the Qualification Governance section of the MHHS Website. If you are interested in joining this Working Group, please contact PMO@mhhsprogramme.co.uk.