Clarification on TDIS portfolio transfers on sale

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
The current wording of the Energy Theft Reduction Schedule has wording on the transfer of theft targets on portfolio sale, however which sales would qualify is ambiguous.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.

Impacts Overview

Impacted REC Documents
Schedule 7 - Energy Theft Reduction
Priority and rationale
Standard

Solution development

Solution documents
R0225 - Legal Drafting 05 Jun 2026 DOCX - 39.58 KB
05 Jun 2026
Change Plan

Change Plan at Change Panel

Clarification on TDIS portfolio transfers on sale > Change Plan

Start:

27 Nov 2024

Due:

21 Jan 2025

Completion:

21 Jan 2025

Change Report (Consultation) to Change Panel

In Progress

Start:

21 Jan 2025

Due:

04 Feb 2025

Completion:

Original submission

Change details

Anton Moden - REC Code Manager
27 Nov 2024

Change details

Clarification on TDIS portfolio transfers on sale
The current wording of the Energy Theft Reduction Schedule has wording on the transfer of theft targets on portfolio sale, however which sales would qualify is ambiguous.
We have multiple instances of Parties requesting this transfer in cases the legal advice is that this would not apply.
It should be unambiguous if this transfer is possible, by clarifying the term 'substantially all'.
I have mark up.

Impacts

All
Other (please provide details in Additional information box below)
This does not benefit consumers, but clarity does benefit Suppliers.
Schedule 7 - Energy Theft Reduction
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
Development: I don't think so.

Implementation: It seems this should be updated reasonably quickly. We should consider if this is a housekeeping change. My view is it is not, but this is clarifying a term.
No
No details provided
Other (please provide details in the Additional information box below)

Activity

Implementation Date has been updated to 27 Jun 2025.
florentina.monea has been allocated as Lead Analyst.
rosalind.timperley, amoden have been allocated as SME.