CSS Change to Allow Prevent of Registration by Market Segment

  • 1
    Issue Review
  • 2
    Issue Conclusion
  • 3
    Issue Closed
Step 3 of 3
Issue Closed
Summary
To prevent a Supplier with exemptions in place that were approved, in BSC and REC PAB for Smart and Unmetered, from registering meter points other than those that they are Qualified in.

Latest update and next planned activity

Date of latest update
Latest Update
06/05/2025 - Code Manager presented solution development outcomes to Technical Change Panel on 30/04/2025 and confirmed that the issue has been resolved and will not be progressed further. An operational process will be put in place for the monitoring of Registrations by Market Segment.

Impacts Overview

Impacted Consumers
Non-Domestic Domestic
Impacted REC Parties and Market Participants
Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Services
Electricity Retail Data Service (ERDS) Central Switching Service (CSS)
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
Standard

Solution development

Problem Statement
Suppliers who do not operate, or intend to operate, in the Smart or Unmetered Market Segments, will be seeking exemptions from the relevant MHHS Qualification requirements. At present, there is no mechanism in CSS to prevent Suppliers from registering Metering Points for which an exemption has been granted and for which they are therefore not qualified.
Solution documents
I0194 - Solution Report v1.0 23.04.2025 05 Jun 2026 PDF - 100.04 KB
05 Jun 2026
Change Plan

Change Proposal Plan approved

Completed

Start:

25 Jul 2024

Due:

03 Dec 2024

Completion:

03 Dec 2024

Definition

In Progress

Start:

03 Dec 2024

Due:

28 Feb 2025

Completion:

Original submission

Change details

Matt Cogram - Elexon
25 Jul 2024

Change details

CSS Change to Allow Prevent of Registration by Market Segment
To prevent a Supplier with exemptions in place that were approved, in BSC and REC PAB for Smart and Unmetered, from registering meter points other than those that they are Qualified in.
Currently this would allow Suppliers who are not Qualified to register meter points that are not Qualified in or have the systems, controls and processes in place.
We propose a solution similar to how green deal restrictions are managed currently within CSS where a list of qualified suppliers is maintained by market segment type and only those Suppliers can register meter points for the relevant segment. This would prevent Suppliers not qualified to supply to UMS or Smart Market Segment from breaching their qualification conditions
There has been a numerous of Code Bodies documentation that has gone to BSC and REC PAB Papers raising the exemptions for approval and the BSC Panel has raised P476 modification.

Impacts

Electricity
Switching experience
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Central Switching Service (CSS)
-
Energy Suppliers
-
Balancing and Settlement Code (BSC)
-
Yes
No details provided

Priority & timing

No
-
No
No
No details provided
-

Activity

Status has been changed to Issue Closed.
harriet.truss has been allocated as Lead Analyst.