REC Changes to tie in with DCP419

  • 1
    Rejected
Step 1 of 1
Rejected
Summary
DCP419 is looking to place obligations on any Party or agent to update the DNO before any planned de-energisation or comms interruptions on sites with a smart meter. This is to allow DNOs to be able to manage any off supply notifications (via AD1 alerts).

Latest update and next planned activity

Date of latest update
Latest Update
19/01/2026 - on 19 January 2026, the Authority published their decision to reject R0216, in line with the recommendation from both the Metering Expert Panel and the Code Manager.

Impacts Overview

Impacted Consumers
Domestic Non-Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations Market Message Catalogue
Other Industry Codes impacted
Distribution Connection and Use of System Agreement (DCUSA)
Priority and rationale
Standard

Solution development

Problem Statement
DNOs may be unnecessarily contacting Consumers where an AD1 notification is generated but the Consumer is having planned works involving their Electricity Smart Meter or Communications Hub replacements for their Electricity Smart Meter. This may create a poor Consumer experience.
Solution documents
Documents Library
Change Plan

Discussed at Change Issues Group

Completed

Start:

Due:

Completion:

07 Nov 2024

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

18 Feb 2025

Change Report (For Consultation) approved by MEP

Completed

Start:

Due:

Completion:

09 Jul 2025

Change Report (Final Recommendation) presented at Metering Expert Panel

Completed

Start:

Due:

Completion:

10 Sep 2025

Original submission

Change details

Lorna Mallon - -
16 Oct 2024

Change details

REC Changes to tie in with DCP419
DCP419 is looking to place obligations on any Party or agent to update the DNO before any planned de-energisation or comms interruptions on sites with a smart meter. This is to allow DNOs to be able to manage any off supply notifications (via AD1 alters)
DNOs have an obligation to respond to all off supply notifications (AD1 alerts) they receive from smart meters. Currently they do not have sight of planned work so are contacting Consumers unnecessarily.
Introduce a new Market Message to allow Suppliers, MOAs, SIPs, Revenue Protection Agents and any others that might work on the comms up to provide advance notice of planned work.
Update REC Schedule 14 to set out the requirements.
Review CoMCoP to understand if updates are required
A draft Market Message was drawn up by the DCP419 working group. However, need to make sure it covers as many scenarios as possible.

Pre-Notifications of Planned Supply De-Energisations - DCUSA

Impacts

Electricity, Domestic Prepayment, Domestic Credit, Microbusiness, Small and Medium Enterprise (SME)
Safety, Security of supply, On site experience
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
See Attached
No details provided
-
No details provided
-
Energy Suppliers, Distribution Network Operators, Data Collectors
SIPs, Crowed Meter Room Coordinators and possibly Data Retrievers (suppliers to confirm who will be doing the comms replacement programme).
Distribution Connection and Use of System Agreement (DCUSA), Smart Energy Code (SEC)
DCUSA - DCP419 – decision required on lead code.

SEC – potential solution via DCC still being investigated.
-
No details provided

Priority & timing

No
-
Needs to tie in with DCP419
No
No details provided
-

Activity

Status has been changed to Rejected.
Status has been changed to Decision.
Orphaned SME: Lead Technical Analyst, vaishnsharma have been allocated as SME.