Schedule 5 – Change Management: Clarity and Typographical Review

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
Following the implementation of R0167 and the introduction of the REC Issues process, the Code Manager has identified several opportunities to improve clarity, and correct typographical issues, in Schedule 5 – Change Management relating to the Issue and Change Proposal processes. This Change Proposal has been raised to enhance clarity for REC Parties Additionally, key terms—such as the updated titles of Change Reports (e.g., Change Report (Proposal Plan))—should be included in Schedule 5 and defined in Schedule 1 – Interpretations and Definitions.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.

Impacts Overview

Impacted REC Documents
Schedule 1 - Interpretations and Definitions Schedule 5 - Change Management
Priority and rationale
Standard

Solution development

Problem Statement
The Code Manager has identified several inaccuracies and areas of ambiguity within Schedule 5 – Change Management. These issues have led to confusion for both the Code Manager and REC Parties, and in some cases, have resulted in procedural inefficiencies and unnecessary burdens on Sub-Committees.

There is currently no Change Plan.

Original submission

Change details

James Hardy - REC Code Manager
30 Jul 2025

Change details

Schedule 5 – Change Management: Clarity and Typographical Review
Following the implementation of R0167 and the introduction of the REC Issues process, the Code Manager has identified several inaccuracies in Schedule 5 – Change Management relating to the Issue and Change Proposal processes. This Change Proposal has been raised to correct those inaccuracies, enhance clarity for REC Parties, and simplify the associated processes. Additionally, key terms—such as the updated titles of Change Reports (e.g., Change Report (Proposal Plan))—should be included in Schedule 5 and defined in Schedule 1 – Interpretations and Definitions.
The current Change Management process outlined in Schedule 5 lacks clarity and, in some cases, provides incorrect guidance to both the Code Manager and REC Parties, creating an ambiguity risk. Additionally, certain procedural steps unnecessarily prolong the Change Process and may place a burden on specific Sub-Committees, reducing overall efficiency and effectiveness of the change process.
An effective solution would be to amend Schedule 5 following this review to address the following:

• Further distinction between Issue and Change Proposal (and Alternatives)
• Resolved Issues procedure
• Clarity on how a submission will only be accepted as a Change Proposal if it includes a developed solution
• The steps for the Code Manager to notify Change Panel if a submission is not accepted.
• Clear distinction on meaning of each Change Report between Proposal Plan, Impact Assessment, For Consultation and Final Recommendation.
• Responsible Sub Committee-s to have the ability to ratify Updates to Proposal Plans (Paragraph 10.4 – new)
• Clarity on Service Provider Impact Assessment timetables
• Clarity on how the Code Manager may decide to re-issue a Change Proposal for consultation, and how any changes post consultation will be documented in the Change Report (Final Recommendation)/
• Typographical and terminology corrections

An effective solution would also introduce, or update, the following definitions in Schedule 1:

• Alternative Issue (new)
• Change Report
• Change Report (Proposal Plan) (new)
• Change Report (Impact Assessment) (new)
• Change Report (For Consultation) (new)
• Change Report (Final Recommendation) (new)
• Category 3 Change Proposal

These have all been addressed and included in the draft legal text provided with this Change Proposal submission.

This solution does not seek to introduce or remove any existing Change Management processes, but rather ensure the Schedule is an accurate reflection of the current processes in place and provides enough clarity and guidance for all REC Parties and Sub-Committees.
N/A

Impacts

All
Trust and confidence
-
Schedule 1 - Interpretations and Definitions, Schedule 5 - Change Management
-
REC Change Panel - Terms of Reference
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
AMR Service Providers, Approved Meter Installer, Data Aggregators, Data Collectors, Data Services, DCC, Distribution Network Operators, Electricity Metering Operative, Energy Suppliers, EES Users, Gas Transporters, GDCC Users, GES Users, Green Deal Finance Party, Green Deal Providers, Meter Asset Manager, Meter Asset Providers, Meter Operator Agent, Safe Isolation Provider, Shippers, Smart Meter Data Retrievers, Third-Party Intermediary, Virtual Lead Party
-
No details provided
Sub-Committees
No
No details provided

Priority & timing

No
-
Development: N/A – Fully formed solution provided.

Implementation: Next available REC Release, where possible, due to impacts on REC Change Process and Responsible Sub-Committees. Targeted implementation of November 2025.
No
No details provided
Trust and confidence

Activity

Implementation Date has been updated to 07 Nov 2025.
james.hardy has been allocated as Lead Analyst.