Uplift to CSS Maximum Demand Volumes during MHHS Migration Period

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This Change Proposal seeks to make the necessary updates to the REC, primarily to the Central Switching Service (CSS) Service Definition, to ensure that the Switching Operator is appropriately prepared for the increase in message volumes that will be created during the Market Wide Half-Hourly Settlement (MHHS) programme migration period.

Latest update and next planned activity

Date of latest update
Latest Update
This change was implemented as part of the the Extraordinary release on 28 March 2024. * This Change Proposal supports the transition to Market-wide Half Hourly Settlement.

Impacts Overview

Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Half Hourly Data Collector (C) Non Half Hourly Data Collector (D) Data and Communications Company (DCC) Energy Supplier (ES)
Impacted REC Documents
Schedule 1 - Interpretations and Definitions
Impacted REC Services
Central Switching Service (CSS)
Priority and rationale
High

Solution development

Problem Statement
As part of the MHHS programme, it is necessary to migrate approximately 31 million MPANs from the existing settlement arrangements to those under the MHHS Target Operating Model. This will create a significantly increased volume of messages, whether for Switches or changes to Supplier Agents, for the CSS during the MHHS Migration Period. The CSS Service Definition does not currently require the Switching Operator to be capable of processing these additional volumes.
Proposed solution summary
  1. As an Electricity Consumer, I want the migration of my MPAN to the new HH Settlement arrangements to be as smooth as possible, so that the service I receive from my Electricity Supplier or it’s appointed agents is not interrupted As an Electricity Consumer, I want my ability to switch to be impacted as little as possible by MHHS migration activities
  2. As the Switching Operator, I want to be prepared for the increased volumes expected during the MHHS Migration Period. As the ERDS Provider, I want the CSS to be able to manage the volume of messages being sent so that I can provide the service I am required to during the MHHS Migration Period
  3. As an Electricity Supplier, I want the MPANs I select to the new HH Settlement arrangements to complete their migration without undue delay, so that the service I provide to Consumers is impacted as little as possible and so that I can meet my migration obligations As a MEM, as part of migration I want my new appointment and my legacy de-appointment to occur within the planned timescales so that the services I provide are impacted as little as possible As a Data Service, as part of migration, I want my new appointment to occur within the planned timescales so that the services I provide can commence in a timely manner As a Data Collector, I want my legacy de-appointment to occur within the planned timescales so that I have a clear understanding and smooth ending to the service I provide
Solution documents
05 Jun 2026
05 Jun 2026
R0093 - Legal text for PCR 17.11.2023 05 Jun 2026 ZIP - 426.77 KB
05 Jun 2026
Change Plan

Solution Analysis and Development completed

Completed

Start:

08 Feb 2023

Due:

06 Apr 2023

Completion:

04 Apr 2023

Service Provider Preliminary Impact Assessment period started

Completed

Start:

06 Apr 2023

Due:

06 Apr 2023

Completion:

04 Apr 2023

Service Provider impact assessment period completed

Completed

Start:

06 Apr 2023

Due:

23 Oct 2023

Completion:

23 Oct 2023

Preliminary Change Report issued

Completed

Start:

23 Oct 2023

Due:

17 Nov 2023

Completion:

17 Nov 2023

Responsible Committee review

Completed

Start:

17 Nov 2023

Due:

29 Nov 2023

Completion:

29 Nov 2023

Consultation issued

Completed

Start:

29 Nov 2023

Due:

01 Dec 2023

Completion:

01 Dec 2023

Consultation closed

Completed

Start:

01 Dec 2023

Due:

15 Dec 2023

Completion:

15 Dec 2023

Final Change Report issued

Completed

Start:

15 Dec 2023

Due:

12 Jan 2024

Completion:

12 Jan 2024

Responsible Committee decision

Completed

Start:

12 Jan 2024

Due:

24 Jan 2024

Completion:

24 Jan 2024

Appeal Window closure

Completed

Start:

24 Jan 2024

Due:

08 Feb 2024

Completion:

08 Feb 2024

Original submission

Change details

Jon Hawkins - RECCo
8 Feb 2023

Change details

Uplift to CSS Maximum Demand Volumes during MHHS Migration Period
The MHHS Programme is responsible for the detailed design and implementation of the MHHS Target Operating Model. The detailed design has now completed and the programme is programme participants have begun to design, build and test the changes required to their systems and processes in order to implement MHHS. Once this is complete, and MHHS goes live, Electricity Suppliers will be required to migrate all electricity Metering Points to MHHS over a 12-18 month timescale (in accordance with the MHHS Programme Plan). The migration design process is in the final stages of definition, but in any case will involve the appointment of MHHS supplier agents (MEM, Data Service and MDR) and the de-appointment of legacy supplier agents (existing MEM, Data Collector and Data Aggregator). This may occur as part of a switch, or as a separate planned migration activity by the Supplier.

The MHHS Programme have also made a determined that the migration design will allow for "reverse migration" to occur on Change of Supplier, where an MPAN will be able to revert to legacy settlement arrangements if switching to a non-MHHS Qualified Supplier.

All central systems, including the CSS, will need to be able to manage an increased volume of messages during this period to accommodate the migration of c. 31m MPANs (in addition to BAU requirements).
The CSS is currently required to be capable of processing, as a minimum, the following volume of Switch Requests and changes to Supplier Agents:

(a) average daily volume of 42,300;
(b) peak daily volume of 281,600;
(c) average hourly volume of 3,500;
(d) peak hourly volume of 25,300; and
(e) annual volume of 15,450,000.

The expected volume of messages during the MHHS Migration Period is expected to exceed these volumes significantly. It is important that the CSS Provider prepares accordingly to manage any additional volumes required during this period, to ensure there is no detrimental impact on the MHHS migration process or BAU switching arrangements.
This change proposal will seek to add a requirement to the CSS Service Definition, to require the CSS Provider to be capable of processing additional volumes of changes to electricity Supplier Agents during the MHHS Migration Period. We propose that rather than attempting to estimate the numbers at this stage, and these being defined in the code, that there is a new requirement for the CSS Provider to plan for the required additional volumes in accordance with the MHHS Migration Implementation Plan, which will be drafted and approved by the MHHS Programme. We would expect the CSS Provider to proactively engage in the MHHS Programme to ensure it is familiar with the MHHS design, and the impacts to its service.

For the purposes of supporting the impact assessment, the following estimated volumes should be considered:

1. 31m MPANs to be migrated over 12-18 months
2. Minimum of two notifications to the CSS to appoint the new MEM and MDR (neither the CSS or DSP will need to know that a Data Service has appointed, as the MDR appointment notification is a separate event).
3. Up to three additional notifications to the CSS to de-appoint the legacy Data Collector, Data Aggregator and MEM (if not derived from new MEM appointment). The detailed design will need to be clarified with the ERDS Provider.
4. All MHHS appointment messages are sent between 8pm - 9pm, following Secured Active processing (as described in the MHHS Operational Choregraphy). Therefore, the bulk of daily MHHS appointments should be assumed to be received in this time period. This would make the average/peak hourly volume the same as the average/peak daily volume.
5. i.e. if 4 additional change of supplier agent messages were sent in total for an MHHS migration, this would result in an additional 122,000,000 change of supplier agent messages (CSS00200), with an average daily/hourly volume of 500,000. The expected peak volume would need to be confirmed with the MHHS Programme.
6. For the avoidance of doubt, these volumes are estimates based on information known to date. These will need to be validated with the MHHS Programme and ERDS Provider.
-

Impacts

Electricity
Switching experience
-
Schedule 1 - Interpretations and Definitions
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Central Switching Service (CSS), Electricity Retail Data Service
-
Energy Suppliers, Distribution Network Operators, DCC
-
Balancing and Settlement Code (BSC)
-
Yes
No details provided

Priority & timing

No
-
The Change Proposal needs to be implemented in line with the MHHS M8 milestone, as the CSS will not need to manage the new volumes until MHHS go-live. However, the CSS may be required to provide these volumes can be managed in an integrated test environment as part of MHHS SIT Non-Functional Testing. This is currently due to commence on 02 September 2024, so any Impact Assessment will need to include the requirement to complete internal performance testing ahead of this date, and performance testing in the MHHS SIT B environment from this date.
As above
No details provided
-

Activity

Proposed solution summary changed to As an Electricity Consumer, I want the migration of my MPAN to the new HH Settlement arrangements to be as smooth as possible, so that the service I receive from my Electricity Supplier or it’s appointed agents i…
Show more
Implementation Date has been updated to 28 Mar 2024.
harriet.truss has been allocated as Lead Analyst.
Orphaned SME: Lead Technical Analyst has been allocated as SME.