Market-Wide Half Hourly Settlement
Market Half Hourly Settlement (MHHS) – Code Freeze Impact

The MHHS Programme was established to deliver the aims of the Electricity Settlement Reform Significant Code Review (SCR). When an SCR is in effect there are rules in place to prevent any Change Proposals which may impact the scope or delivery of the SCR. The MHHS programme implemented a Change Freeze to manage this requirement during MHHS transition.

There have been two freezes within the MHHS Programme.

  1. Change Freeze effective from 06 December 2023. This prevented any changes to MHHS Design or Code Drafting except in the case of fixing defects or supporting the implementation of urgent change
  2. Core Systems Code Freeze effective from November 2024. This technical freeze prevents any changes to MHHS Central systems and impacts:
  • Central Switching Service (CSS)
  • Electricity Retail Data Service (ERDS)
  • Electricity Enquiry Service (EES)
  • And consequential changes to the Secure Data Exchange Service (SDES)

How this impacts the REC?

RECCo assessed all changes that were already in flight and any raised since the freezes were in place to identify any impact on the MHHS Programme. The following principles applied:

  • If a REC Change Proposal (CP) required change to the MHHS design or code drafting, it may have had its implementation and/or progression postponed until MHHS Programme Milestone M10 was completed (September 2025).
  • If a CP impacts MHHS Qualification or Migration, it may have been delayed until MHHS Programme Migration Milestone M15 is completed (May 2027)
  • Any CP or Data Access requests requiring an amendment to an impacted technical system including changes to API or reporting, may have been delayed until MHHS Programme Milestone M10 was completed (September 2025).

Stakeholders were kept updated on the impacts to REC Change through REC Change Panel and the REC Change Issues Group. If you have any questions please contact us on the Service Desk.

 