Consequential Cross-Code Change for BSC P441 - Complex Site Classes Creation
Summary
A Balancing & Settlement Code (BSC) Modification P441 is looking to introduce additional Complex Site classes which would categorise the types of Complex Site, with each having clearly defined criteria within the BSC, whilst also facilitating a new "type" of Complex Site (referred to as a Class 6 Complex Site) to allow approval of "non-standard" complex sites. It will also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted.
Latest update and next planned activity
Date of latest update
Latest Update
22/03/2024 - Withdrawn.
Impacts Overview
Impacted Consumers
Others
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Data Item Catalogue
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Distribution Connection and Use of System Agreement (DCUSA)
Priority and rationale
High
Solution development
Problem Statement
The introduction of new Complex Site classes is needed into the REC to make the solutions under P441 and DCP 424 work. Meter Equipment Managers (MEMs) will need to understand what their new obligations are in respect of metering requirements, as well as impacts on any of the metering processes associated with a Complex Site.
Proposed solution summary
- As a consumer, I want more choice to take up low-carbon technology and more flexible energy solutions through local energy schemes, such as the Ofgem BEIS Smart System Flexibility Plan and any other future flexibility service provisions that may be developed.
- For MEMs, l want to remove ambiguity around the current Complex Site arrangements and will facilitate the advancement of community energy schemes.
- For Suppliers, I want to encourage more innovation that will lead to the better use of local energy schemes.
Documents Library
05 Jun 2026
Download R0133 Preliminary Change Report V1.0
Change Plan
Solution Development
Completed
Start:
04 Jul 2023Due:
14 Aug 2023Completion:
14 Aug 2023Party Impact Assessment
Completed
Start:
14 Aug 2023Due:
14 Aug 2023Completion:
04 Sep 2023Preliminary change report
Completed
Start:
14 Aug 2023Due:
22 Sep 2023Completion:
22 Sep 2023Original submission
Change details
Colette Baldwin - Code Manager
4 Jul 2023
Change details
Consequential Cross-Code Change for BSC P441 - Complex Site Classes Creation
The BSC Modification P441 is looking to introduce complex site classes which would categorise the types of Complex Site with each having clearly defined criteria within the BSC whilst also facilitating a new "type" of Complex Site (referred to as a Class 6 Complex Site) to allow approval of "non-standard" complex sites. It will also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted. The REC documentation and data specification will need to be updated to reflect the new classes being introduced.
The current processes do not cater for additional Complex Site Classes to be introduced.
The inclusion of new Complex Site Classes being incorporated into the REC Schedules and Data Specification.
This is a Cross-Code Change, which impacts both the Balancing & Settlement Code (Modification P441) and Distribution Connection and Use of System Agreement Code (DCUSA) (DCUSA Change Proposal 424). This CP will also need to be developed in a timeline that aligns with both the BSC and the DCUSA
Impacts
Electricity
Other (please provide details in Additional information box below)
They will be appropriately categorised for their metering systems, allowing other processes within the BSC and DCUSA to work effectively.
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Data Item Catalogue
-
No details provided
-
No details provided
-
Energy Suppliers, Distribution Network Operators
-
Balancing and Settlement Code (BSC), Distribution Connection and Use of System Agreement (DCUSA)
-
No
No details provided
Priority & timing
No
Cross-Code Change - not the Lead Code.
As above
Conclusion of P441, and DCP424
No details provided
-