Complex Sites process improvements
Summary
-
Latest update and next planned activity
Date of latest update
Latest Update
-
Impacts Overview
Impacted Consumers
Non-Domestic
Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Electricity Distribution Network Operator (R)
Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
Standard
Solution development
Problem Statement
There is not a consistent understanding around the Complex Site process which can lead to the Complex Site Supplementary Information Form (CSSIF) being populated or interpreted differently by different parties. This may lead to incorrect data being used for consumer billing and Settlement, which can result in BSC Trading Disputes.
Proposed solution summary
- As an electricity Consumer, I want my metering data to be accurate, to ensure my account is set up correctly and I receive accurate and timely invoices.
- As a Metering Equipment Manager, I want to have clarity on my obligations to provide data - specifically what data I need to send, who the recipients are and when I need to send it to ensure I provide accurate data to other Market Participants. As an Electricity Supplier and as an Electricity Distribution Network Operator (DNO), I want to receive accurate and complete Meter Technical Details (MTD) to enable me to take appropriate action following a change of metering equipment, a switch, a change of HHDC, a new connection a meter configuration or MEM.
- As a Half Hourly Data Collector, I want to receive accurate and complete Meter Technical Details to enable me to take appropriate action following a change of metering equipment, change of supplier, change of HHDC, new connections, meter configuration or MEM.
Solution documents
Documents Library
05 Jun 2026
Download R0018 - Final Change Report v1.0
Change Plan
Party Impact Assessment Issued
Completed
Start:
25 Nov 2021Due:
20 Jan 2022Completion:
10 Feb 2022Preliminary Change Report Issued
Completed
Start:
20 Jan 2022Due:
21 Feb 2022Completion:
18 Feb 2022Responsible Committee Decision – Ex-Committee
Completed
Start:
21 Feb 2022Due:
03 Mar 2022Completion:
03 Mar 2022Consultation Started
Completed
Start:
03 Mar 2022Due:
07 Mar 2022Completion:
07 Mar 2022Consultation End
Completed
Start:
07 Mar 2022Due:
01 Apr 2022Completion:
01 Apr 2022Final Change Report Issued
Completed
Start:
01 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Responsible Committee Decision
Completed
Start:
29 Apr 2022Due:
11 May 2022Completion:
11 May 2022Appeal Window Open
Completed
Start:
11 May 2022Due:
13 May 2022Completion:
13 May 2022Appeal Window Closed
Completed
Start:
13 May 2022Due:
27 May 2022Completion:
27 May 2022Original submission
Change details
Ann Perry - -
25 Nov 2021
Change details
Complex Sites process improvements
‘Complex sites’ are defined as sites at which the Metering Technical Details are too complex to be captured in the standard D0268 ‘Half Hourly Metering Technical Details’ Market Message. BSC Procedure BSCP502 (‘Half Hourly Data Collection for SVA Metering Systems Registered in SMRS’) and REC Schedule 14 (‘Metering Operations’) include provisions for ‘Complex sites’, providing guidance and clarification on the appropriate Settlement arrangements for various types of complex site. In recent years Elexon have received questions (from Suppliers and other interested parties) on the scope of these arrangements. Confusion over the current complex site procedures was also identified as a key factor in the lessons learned session related to a high materiality BSC Trading Dispute. BSC Issue 88 was raised by Elexon to clarify the ambiguities and to identify process weaknesses/improvements.
The current lack of clarity around aspects of the Complex Site process can lead to the Complex Site Supplementary Information Form (CSSIF) being interpreted differently by different parties. As such, the Complex Site rule is sometimes being applied incorrectly or not being updated when there is change of status of the Metering Equipment associated with the Complex Site. This leads to incorrect data being submitted to Settlement. Metering Systems comprised within a Complex Site are often submitting large quantities of energy into Settlement. This lack of clarity increases the chance of errors associated with these Metering System Identifiers (MSIDs), which have resulted in Trading Disputes.
Updates are required to REC Schedule 14 (‘Metering Operations’) to introduce the following changes:
• Mandating the use of the Complex Site Supplementary Information Form (CSSIF)
• Implementing changes to the standardised CSSIF:
o Addition of an Effective from/to date
o Addition of all associated Metering System Identifiers (MSIDs) to highlight the relationship between Boundary connected and embedded MSIDs.
o Removal of duplicate fields between the ‘D0268 – Half Hourly Meter Technical Details’ market message and the CSSIF
o Addition of a Smart Meter indicator o Addition of a ‘comments box’.
o Addition of ‘method of calculation’ where compensation has been applied (i.e dynamically in the Meter or as a fixed constant in the Complex Site Rule)
o A field for the user to sign when the CSSIF has been signed
o Addition of a version number; and
o Changed format from Microsoft Word to Microsoft Excel.
• Clarifying that a Single Line Diagram of the site should be included and transferred along with the CSSIF.
• Clarifying that a change in Feeder status requires a new and updated CSSIF to be sent
• Clarify that as part of the Complex Site Validation Test both the raw metered data and aggregate of the Complex Site Rule should be sent from the Half Hourly Data Collector (HHDC) to the Half Hourly Meter Operator (HHMOA) and both sets of this data checked and confirmed before the validation test is considered ‘passed’.
• Mandating the use of the Complex Site Supplementary Information Form (CSSIF)
• Implementing changes to the standardised CSSIF:
o Addition of an Effective from/to date
o Addition of all associated Metering System Identifiers (MSIDs) to highlight the relationship between Boundary connected and embedded MSIDs.
o Removal of duplicate fields between the ‘D0268 – Half Hourly Meter Technical Details’ market message and the CSSIF
o Addition of a Smart Meter indicator o Addition of a ‘comments box’.
o Addition of ‘method of calculation’ where compensation has been applied (i.e dynamically in the Meter or as a fixed constant in the Complex Site Rule)
o A field for the user to sign when the CSSIF has been signed
o Addition of a version number; and
o Changed format from Microsoft Word to Microsoft Excel.
• Clarifying that a Single Line Diagram of the site should be included and transferred along with the CSSIF.
• Clarifying that a change in Feeder status requires a new and updated CSSIF to be sent
• Clarify that as part of the Complex Site Validation Test both the raw metered data and aggregate of the Complex Site Rule should be sent from the Half Hourly Data Collector (HHDC) to the Half Hourly Meter Operator (HHMOA) and both sets of this data checked and confirmed before the validation test is considered ‘passed’.
Further information can be found in the BSC Issue 88 Report https://www.elexon.co.uk/documents/change/issues/51-100/issue-88-issue-report/
Impacts
Electricity
Billing accuracy, Other (please provide details in Additional information box below)
This change impacts Half Hourly settled electricity sites only, where the Meter Technical details are too complex to be captured in the standard D0268 ‘Half Hourly Metering Technical Details’ data flow. Clarity on the Complex Site process will help ensure accurate billing and Settlement, and reduce the likelihood of large scale Trading Disputes.
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Balancing and Settlement Code (BSC)
This Change Proposal is a consequential change following the conclusion of BSC Issue 88. A BSC Change Proposal will be raised to deliver corresponding changes to BSC Procedure BSCP502 (‘Half Hourly Data Collection for SVA Metering Systems Registered in SMRS’). The interdependency across the REC and the BSC means that the changes should be progressed in parallel in the interests of understanding and clarity for market participants. The REC Code Manager and Elexon will work together to ensure alignment of the implementation of the REC and BSC Change Proposals.
No
No details provided
Priority & timing
No
-
No specific timelines
No – only the interdependency with BSC
No details provided
-