New Meter Types for Auxiliary Proportional Controllers (APCs)
Summary
This change seeks to introduce a method for industry parties to identify new SMETS2 variant meter types with Auxiliary Proportional Controllers (APCs).
Latest update and next planned activity
Date of latest update
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Impacts Overview
Impacted Consumers
Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Half Hourly Data Collector (C)
Non Half Hourly Data Collector (D)
Electricity Distribution Network Operator (R)
Data and Communications Company (DCC)
Energy Supplier (ES)
Others
Other (Other)
Impacted REC Documents
Data Item Catalogue
Market Message Catalogue
Impacted REC Services
Electricity Enquiry Service (EES)
Other Industry Codes impacted
Smart Energy Code (SEC)
Priority and rationale
Standard
Solution development
Problem Statement
Currently there is no way to identify new meter types that incorporate Auxiliary Proportional Controllers (APCs) outside of the DCC Smart Metering Inventory. Failure to correctly identify these could result in an incorrect meter type being assigned to a supply point. Failure to accurately record where meter types that incorporate Auxiliary Proportional Controllers (APCs) are at a property could result in the meter not being configured correctly by the Supplier. This may impact switching, timely and accurately billing, and industry settlements. Options need to be considered to accurately record what meter types that incorporate Auxiliary Proportional Controllers (APCs) are installed at a property.
Proposed solution summary
- As an Energy Consumer, I want to be quoted the correct rates as part of my contract conversation when switching supplier. I want my meter set-up correctly to be able to utilise secondary electricity loads at specific times for specific purposes. (e.g., overnight Electric Vehicle (EV) charging, Heat/Hot Water, Boost, etc.). I want to be assured that I will have access to electricity when I need it. I want to switch to my chosen Supplier without any delays or issues.
- As an Energy Supplier, I need to identify meter types with Auxiliary Proportional Controllers (APCs) at a property, so that I can offer my customer the correct tariff and configure their meter correctly.
- As a Meter Equipment Manager (MEM), I need to identify meter types that incorporate Auxiliary Proportional Controllers (APCs) are present at a property, so that any necessary maintenance/repair work can be carried out appropriately.
Solution documents
Documents Library
Change Plan
Change Panel review
Completed
Start:
08 Sep 2021Due:
19 Oct 2021Completion:
19 Oct 2021Analysis and Solution development activity
Completed
Start:
19 Oct 2021Due:
30 Dec 2021Completion:
30 Dec 2021Alternative Change Proposal decision point
Completed
Start:
30 Dec 2021Due:
31 Dec 2021Completion:
31 Dec 2021Service Provider Impact Assessment completion
Completed
Start:
31 Dec 2021Due:
21 Apr 2022Completion:
21 Apr 2022REC Party Impact Assessment completion
Completed
Start:
21 Apr 2022Due:
23 May 2022Completion:
28 Mar 2022Preliminary Change Report issued
Completed
Start:
23 May 2022Due:
27 Jun 2022Completion:
27 Jun 2022Technical Expert Panel review
Completed
Start:
27 Jun 2022Due:
05 Jul 2022Completion:
30 Jun 2022Consultation starts
Completed
Start:
05 Jul 2022Due:
12 Jul 2022Completion:
01 Jul 2022Consultation ends
Completed
Start:
12 Jul 2022Due:
26 Jul 2022Completion:
22 Jul 2022Final Change Report issued
Completed
Start:
26 Jul 2022Due:
22 Aug 2022Completion:
19 Aug 2022Technical Expert Panel decision
Completed
Start:
22 Aug 2022Due:
31 Aug 2022Completion:
31 Aug 2022Original submission
Change details
Jonathan Holland - -
8 Sep 2021
Change details
New Meter Types for Auxiliary Proportional Controllers (ACP)
November 2020 SEC changes introduced a series of new Electricity Smart Metering Equipment (ESME) variants that parties are obliged to provide to Data Communications Company (DCC) as part of any meter installation. This data needs to be passed between parties using industry data flows to have consistency between ESME variants that are on DCC and the meter types.
Currently these new Meter Types are not set in the the Market Message MM00051 (DTC Legacy Reference D0150 data flow).. Therefore, identification and correct configuration of the new Meter Types is not possible.
If the industry is following an unagreed mapping of the new variants to the existing Meter Types, this could lead to misinterpretation by parties.
Currently these new Meter Types are not set in the the Market Message MM00051 (DTC Legacy Reference D0150 data flow).. Therefore, identification and correct configuration of the new Meter Types is not possible.
If the industry is following an unagreed mapping of the new variants to the existing Meter Types, this could lead to misinterpretation by parties.
Gaining meters cannot be configured correctly, which will prevent suppliers being able to meet their Licence obligations, regarding ensuring the customers meter(s) are configured correctly and display accurate tariff information. This obligation is specifically detailed in Condition 49 - Smart Metering Systems and In-Home Displays Operational Requirements.
This could have a significant impact on consumers if devices are configured incorrectly; especially if auxiliary loads like heating and hot water rely on that configuration and might not switch on if Suppliers get it wrong. Incorrect configuration could also impact on settlements as reads could be entered that only cover part of full consumption, leading to larger errors in allocation of energy that would be spread over Suppliers who would then be potentially unfairly penalised in terms of settlement costs. Knowing this up front will help any Supplier manage that process and ensure they can take over such meters.
This could have a significant impact on consumers if devices are configured incorrectly; especially if auxiliary loads like heating and hot water rely on that configuration and might not switch on if Suppliers get it wrong. Incorrect configuration could also impact on settlements as reads could be entered that only cover part of full consumption, leading to larger errors in allocation of energy that would be spread over Suppliers who would then be potentially unfairly penalised in terms of settlement costs. Knowing this up front will help any Supplier manage that process and ensure they can take over such meters.
To update Data Item Enumeration for data item DI50230 (DTC Legacy Reference J0483) (Meter Type) and to ensure all parties use relevant correct data as provided to DCC on data flows related to metering installed to ensure accurate and consistent data is seen in market. This will improve efficiency in contracting with any potential new customer by having access to data related to a MPAN in a single repository, namely Electricity Enquiry Service (EES), that is most likely to require charges applied to for any contract. This allows any Supplier to use a single source of data for all discussions with customer as to suitability of tariff offerings and to minimise time taken to access that data as it will only require calls to EES and not also to DCC inventory data initially. It also allows Suppliers to minimise possibly problems in that DCC and data flow data cannot be matched at all at present but matching ESME variant to Meter Type reduces risk of mismatches.
New Meter Types need to be included for those meters where APC is integrated within a meter.. This change will give a Supplier an opportunity to identify these types of meters from a single source as part of any contract sign up process, namely ECOES, thus simplifying this process for parties
New Meter Types need to be included for those meters where APC is integrated within a meter.. This change will give a Supplier an opportunity to identify these types of meters from a single source as part of any contract sign up process, namely ECOES, thus simplifying this process for parties
-
Impacts
Electricity, Domestic Credit
Switching experience, Billing accuracy, Trust and confidence
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
-
No details provided
-
No details provided
-
Energy Suppliers, Distribution Network Operators, DCC, Data Collectors, Data Aggregators, Meter Asset Providers
-
No details provided
-
No
No details provided
Priority & timing
No
N/A
No
No
No details provided
-