On-site Aggregation as a method to facilitate Third Party Access - BSC P455
Summary
Following a modification proposal to the Balancing and Settlement Code (BSC) to allow on-site aggregation as a method for third party access on private networks, the Code Manager is required to amend the REC to place a requirement on the Meter Equipment Managers (MEMs) appointed by the boundary points Electricity Supplier, to rectify any faults found with the submeters used in the on-site aggregation methodology.
Latest update and next planned activity
Date of latest update
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Impacts Overview
Impacted Consumers
Non-Domestic
Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Half Hourly Data Collector (C)
Non Half Hourly Data Collector (D)
Electricity Distribution Network Operator (R)
Energy Supplier (ES)
Others
Impacted REC Documents
Schedule 1 - Interpretations and Definitions
Schedule 25 - Central Switching Service
Priority and rationale
Standard
Solution development
Problem Statement
Under the proposed solution for BSC Modification P455, Consumers will require a Market Participant to oversee the maintenance of their sub-meter, including installations and rectification of metering faults. To ensure this, the REC will need to place a requirement on the MEMs appointed by the boundary point Electricity Supplier to rectify any faults found with the sub-meters used in the On-Site Aggregation.
Proposed solution summary
- The BSC Modification P455 Modification proposes to place a requirement on the SVA MOA (MEMs) appointed by the Boundary Point Supplier to rectify any faults found with the sub meters used in the On-Site Aggregation methodology; and to produce and submit the On-Site Aggregation Form to the HHDC. As MEMs (SVA MOAs) are governed under the Retail Energy Code (REC), R0150 is the REC's subsequent change to propose this.
Solution documents
05 Jun 2026
05 Jun 2026
05 Jun 2026
Documents Library
Change Plan
Preliminary Change Report and Consultation Issued
Completed
Start:
15 Jan 2024Due:
22 Mar 2024Completion:
22 Mar 2024Party Impact Assessment
Completed
Start:
30 Oct 2023Due:
15 Jan 2024Completion:
15 Jan 2024Final Change Report Issued
Completed
Start:
22 Mar 2024Due:
26 Apr 2024Completion:
25 Apr 2024Responsible Committee Decision
Completed
Start:
26 Apr 2024Due:
08 May 2024Completion:
08 May 2024Original submission
Change details
Colette Baldwin - Gemserv
30 Oct 2023
Change details
On-site Aggregation as a method to facilitate Third Party Access - BSC P455
Customers on private networks may be supplied electricity from the Boundary Point Supplier. The Boundary Point Supplier is usually appointed by the Private Network Operator (PNO).
Customers on private networks also have the right to switch to a Third Party Supplier (TPS) of their choice. Under the Electricity and Gas (Internal Markets) Regulations 2011 (Statutory Instrument (SI) 2011 No. 2704), PNOs are obligated to facilitate access to TPSs.
Where one or more customers on a PNO for a third party supply, corrective action is required to avoid the double counting of metered volumes in Settlement. This is because Third Party Meter readings submitted into Settlement by the TPS Agent also contribute to the aggregate Boundary Point Meter reading submitted into Settlement and allocated to the energy account of the Boundary Point Supplier.
The BSC Change indicates that they see inefficiencies aris in the differencing metering approach when there is more than one TPS supplying customers on a private network. For example, where a private network is connected to 100 domestic properties, 50 of which are supplied by a license exempt Supplier appointed by the PNO and 50 of which are supplied by 20 different TPSs, all 20 TPSs must establish the bespoke arrangements mentioned above to facilitate the scheme.
Customers on private networks also have the right to switch to a Third Party Supplier (TPS) of their choice. Under the Electricity and Gas (Internal Markets) Regulations 2011 (Statutory Instrument (SI) 2011 No. 2704), PNOs are obligated to facilitate access to TPSs.
Where one or more customers on a PNO for a third party supply, corrective action is required to avoid the double counting of metered volumes in Settlement. This is because Third Party Meter readings submitted into Settlement by the TPS Agent also contribute to the aggregate Boundary Point Meter reading submitted into Settlement and allocated to the energy account of the Boundary Point Supplier.
The BSC Change indicates that they see inefficiencies aris in the differencing metering approach when there is more than one TPS supplying customers on a private network. For example, where a private network is connected to 100 domestic properties, 50 of which are supplied by a license exempt Supplier appointed by the PNO and 50 of which are supplied by 20 different TPSs, all 20 TPSs must establish the bespoke arrangements mentioned above to facilitate the scheme.
When there is more than one TPS supplying customers on a private network. For example, where a private network is connected to 100 domestic properties, 50 of which are supplied by a license exempt Supplier appointed by the PNO and 50 of which are supplied by 20 different TPSs, all 20 TPSs must establish the bespoke arrangements.
The REC to consider how to treat metering issues related to the metering installations and rectification of metering faults.
Additional process will be required, similar to the Complex Sites validation processes to enable the HH Data Collector and HH MEM to establish the data integrity of the individual meters involved and the overall aggregation methodology that is being applied to these meters.
Additional process will be required, similar to the Complex Sites validation processes to enable the HH Data Collector and HH MEM to establish the data integrity of the individual meters involved and the overall aggregation methodology that is being applied to these meters.
This is a cross code change, required as a result of BSC Modification P455
Impacts
Electricity, Domestic Prepayment, Domestic Credit, Microbusiness, Small and Medium Enterprise (SME)
Trust and confidence, On site experience
-
Schedule 1 - Interpretations and Definitions, Schedule 14 - Metering Operations
CoMCoP - Consolidated Metering Code of Practice
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
Still to be determined.
Energy Suppliers, Distribution Network Operators, Data Collectors
-
Balancing and Settlement Code (BSC)
-
No
No details provided
Priority & timing
No
-
It will need to follow the timetable for the BSC Change - which will be the Lead Code for planning and progressing the Change Proposal
BSC P455
No details provided
-