Altering the Trigger Points for CT Commissioning

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
-

Latest update and next planned activity

Date of latest update
Latest Update
-

Impacts Overview

Impacted Consumers
Non-Domestic Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations Data Item Catalogue Market Message Catalogue
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
Standard

Solution development

Problem Statement
The Balancing & Settlement Code Procedure (BSCP) 515 and the Retail Energy Code (REC) Metering Operations Schedule set out the obligations and timescales imposed on the DNO to send commissioning information to the MEM (using the D0383 (MM00370) data flow), where the DNO has installed metering equipment, with Measurement Transformers. When the DNO installs Low Voltage Current Transformer (LV CT) metering units, that have been pre-commissioned off-site, the commissioning of the units is done before installation and separately to the Energisation of the Supply. When the Energisation status change is the responsibility of the Registered Supplier and is requested of the MEM using the D0134 data flow, notification of the change in energisation status is then sent to the Registered Supplier and the DNO by the MEM, using the D0139 (MM00036) For an LV fused supply, the DNO may not be aware of who the MEM is to send the commissioning information to via a D0383 (MM00370) until a D0139 (MM00036) is received. This is often the point at which the DNO first becomes aware that a fused supply is now Energised. This may be several days/weeks/months after DNO commissioning, and it is proving difficult for the DNO to meet their BSC obligations.
Proposed solution summary
  1. As the DNO, I only want to send the commissioning information using the D0383 (MM00370) when I am made aware that the site has now been energised by the Registered Supplier’s MEM for a CT Pre-commissioned meter, so that I can meet my regulatory obligations under the BSC
  2. As a MEM I want to receive the information from the DNO in a timely manner to ensure my records are accurate and up to date, and that I can provide the Registered Supplier with information to ensure the metering point is accurately settled.
Solution documents
R0031 Proposed Draft Legal Text 05 Jun 2026 DOCX - 26.08 KB
05 Jun 2026
Change Plan

Preliminary Change Report Published

Completed

Start:

01 Feb 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Consultation Issued

Completed

Start:

08 Apr 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Consultation Period End

Completed

Start:

08 Apr 2022

Due:

04 May 2022

Completion:

04 May 2022

Final Change Report Published

Completed

Start:

04 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Responsible Committee Decision

Completed

Start:

27 May 2022

Due:

10 Aug 2022

Completion:

10 Aug 2022

Original submission

Change details

Colette Baldwin - -
1 Feb 2022

Change details

DNO LV CT Commissioning Trigger Points & Timescales
The Balancing & Settlement Code Procedure (BSCP) 515 and the REC Metering Operations Schedule sets out the obligations and timescales imposed on the Distribution Network Operator (DNO) to send commissioning Information to the Metering Equipment Manager (MEM) (using the D0383 data flow), where the DNO has installed metering equipment, with Measurement Transformers, which is to be energised by the Registered Supplier.

When the DNO installs Low Voltage Current Transformer (LV CT) metering units, that have been pre-commissioned off-site, the commissioning of the units is done before installation and separately to the Energisation of the Supply. The Energisation status change is then the responsibility of the Registered Supplier and is requested of the MEM using the D0134 data flow. Notification of the change in energisation status is then sent to the Supplier and DNO by the MEM, using the D0139

For an LV fused supply, the DNO may not be aware of who the MEM is to send the commissioning information to via a D0383 until a D0139 is received. This is often the point at which the DNO first becomes aware that a fused supply is now Energised. This may be several days/weeks/months after DNO commissioning, and it is proving difficult for the DNO to meet their BSC obligations.
As many DNOs are now using LV CT pre-installed, pre-commissioned metering units for fused supplies, these units are factory commissioned and the vast majority of the commissioning for the units will be completed prior to installation and, consequently, before Energisation too. The decoupling between installation and energisation means that the DNO may not know when the Supply is Energised, nor who is carrying this out until they receive the notification of change of Energisation Status. This makes it difficult for the DNO to comply with their BSCP and REC obligations to send the commissioning information in the timescales laid down, which can have a detrimental impact on DNO performance of its obligations and has also resulted in a number of BSC audit non-conformances.
The use of more appropriate trigger points for commissioning and subsequent sending of data flows within the Metering Operations Schedule for all types of LV CT operated metering systems, as well as changes to the BSCP 515 process for commissioning of Measurement Transformers for new metering Systems.
These current timescales and trigger points for this process were introduced and updated before the widespread use of “off-site” commissioned metering units for LV CT metering:
• BSC CP 1458 (implemented in Nov 2016) introduced the initial trigger points and timescales for Commissioning LV CT Metering Systems.
• BSCP 1496 (implemented Nov 2018) introduced the current industry data flows used in the process and revised the basic timescales.
• BSCP 1505 (also implemented Nov 2018) allowed the introduction of “off-site” commissioning of LV CT metering which many DNOs are now using.

Impacts

Electricity, Small and Medium Enterprise (SME), Industrial and Commercial (I&C)
On site experience
Changes will also be required to the BSCP515 Section 3.3.A New SVA Metering System - Commissioning of Measurement
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
Suggested Solution changes required: Amend section 6.7.1 to include the date of D0139 receipt from MEM (where the MEM energises) as the trigger point for commissioning timescales. It splits out the different trigger points for where the DNO or MEM energises. Amend section 6.7.2 to remove the reference to sending the commissioning information no later than 5WD after commissioning (action 6.7.1) and replace it with sending it no later than 21WD after Energisation (if DNO energises) or 21WD after receipt of D0139 (if MEM energises). This allows extra time for the DNO to send the D0383 but retain the existing overall timescale of within 21WD of Energisation (where the DNO energises) and uses the same timescale where notification of MEM Energisation is via the D0139. Amend section 6.7.3, 6.7.5 and 6.7.6 to include the variation trigger point of receipt of D0139 where the DNO energises. This prevents the MEM timescale for commissioning being reduced where DNO energises.
No details provided
-
No details provided
-
No details provided
-
Balancing and Settlement Code (BSC)
-
No
No details provided

Priority & timing

No
-
-
Changes will be required to BSCP515
No details provided
-

Activity

Proposed solution summary changed to As the DNO, I only want to send the commissioning information using the D0383 (MM00370) when I am made aware that the site has now been energised by the Registered Supplier’s MEM for a CT Pre-commissioned meter,…
Show more
Implementation Date has been updated to 04 Nov 2022.
colette.baldwin has been allocated as Lead Analyst.