Addition of Export flag in D0303 flows

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
The Market Message (D0303 / MM00240) responsible for informing Metering Asset Providers (MAPs) of Metering Equipment installation is generating a lot of queries and exceptions due to Export MPAN creation. This is requiring MAPs to manually investigate whether a D0303 showing a Metering Asset being installed against a second Metering Point is a correction or the creation of an Export MPAN that can be ignored. Due to the growing uptake of microgeneration this is a problem that is growing in volume.

Latest update and next planned activity

Date of latest update
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.

Impacts Overview

Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Meter Asset Provider (8) Gas Meter Asset Provider (MAP)
Impacted REC Services
Electricity Enquiry Service (EES)
Priority and rationale
Standard

Solution development

Problem Statement
MAPs must manually check D0303 Market Messages received with duplicated Metering Equipment (e.g. duplicated Meter Serial Number) to ensure they hold the correct Metering Equipment against the correct Metering Point. For Export Metering Points using the same Metering Equipment as the Import Metering Point, this manual check results in no action needing to be taken.
Solution documents
I0261 solution V0.1 02 Nov 2026 DOCX - 42.95 KB
02 Nov 2026
I0261 solution post IA V0.2 02 Nov 2026 DOCX - 40.04 KB
02 Nov 2026
Documents Library
Change Plan

Change Report (Proposal Plan) approved at Change Panel

Completed

Start:

Due:

Completion:

04 Nov 2025

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

05 Feb 2026

Change Report (For Consultation) approved at TEP

Completed

Start:

Due:

Completion:

25 Mar 2026

Change Report (Final Recommendation) approved at TEP

Completed

Start:

Due:

Completion:

27 May 2026

Original submission

Change details

Stuart Blair - Centrica Smart Meter Assets
5 Jun 2025

Change details

Addition of Export flag in D0303 flows
flows responsible for informing MAPs of installation are being polluted by Export MPAN creation.
The impact to MAPs is currently a requirement to manually investigate whether or not an installation flow showing an asset being stalled in a second location is a corrective flow on an asset or a flow that can be ignored. Due to the growing affordability of microgeneration this is a problem that is growing in volume.
a flag indicating whether or not an MPAN is an export MPAN to be included in the meter point details.
-

Impacts

Electricity
Other (please provide details in Additional information box below)
Whilst this change has minor impact to consumers, it will allow MAPs to more accurately bill the correct supplier, and reduce the likelihood of inaccurate bills created by export MPANs being treated as import.
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
Other (please provide details in the Additional information box below)

Activity

Change Category has been updated to Category 2.
Status has been changed to Awaiting Implementation.
Implementation Date has been updated to 06 Nov 2026.
Orphaned SME: Lead Technical Analyst has been allocated as SME.