DNOs Create Export MPANs after approving G98/99 commissioning documents

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 5 of 6
Awaiting Implementation
Summary
The creation of Import Metering Points for new Premises sits with the Distribution Network Operator (DNO), while the Export Metering Points generally sit with the Electricity Supplier. When the DNO approves the G98 Engineering Recommendation Installation Document (Form B) or G99 Engineering Recommendation Installation Document (Form A3-1 or A3-2) under the Distribution Code, they could create Export Metering Points at this time (with the logical Disconnection process being available for any Export Metering Points that are then not required).

Latest update and next planned activity

Date of latest update
Latest Update
04/11/2026 On 20 October 2026, the REC Change Panel voted, in line with the Code Manager's recommendation, to approve this Change Proposal. The appeal window is now closed. R0321 will be implemented on 25 June 2027.

Impacts Overview

Impacted Consumers
Non-Domestic Domestic
Impacted REC Parties and Market Participants
Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Schedule 27 - RMP Lifecycle
Priority and rationale
Standard

Solution development

Problem Statement
The information required by the DNO to create an Export Metering Point sits with the Consumer rather than the Electricity Supplier, and leads to the Electricity Supplier acting as an unnecessary third party in the process. This is leading to unnecessary time being added to the process, negatively impacting Consumers and the journey to Net Zero. This is particularly apparent for large new housing developments, which may have several tens of thousands of Export Metering Points to create with the same DNO and require the use of the Bulk Request process. This process is cumbersome and has no two DNOs operating the process in the same way.
Solution documents
Schedule 27 RMP lifecycle draft V0.1 02 Nov 2026 DOCX - 378.68 KB
02 Nov 2026
Schedule 27 RMP lifecycle draft V0.2 02 Nov 2026 DOCX - 378.87 KB
02 Nov 2026
Change Plan

Change Report (Proposal Plan) approved at Change Panel

Completed

Start:

Due:

Completion:

05 May 2026

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

07 May 2026

Change Report (For Consultation) and Update to Plan approved at Change Panel

Completed

Start:

Due:

Completion:

17 Aug 2026

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

03 Sep 2026

Final Recommendation approved at Change Panel

Completed

Start:

Due:

Completion:

20 Oct 2026

Original submission

Change details

Ben Atkinson - British Gas
26 Mar 2026

Change details

DNOs Create Export MPANs after approving G98/99 commissioning documents
The creation of Import MPANs for new housing developments sits with the DNO, while the Export MPANs sit with the Energy Supplier.
This can lead to a very large manual workload for the Energy Supplier as they may have several tens of thousands of MPANs to create and have to use the bulk Export MPAN creation request process as set out in section 7.5 of the RMP Lifecycle Schedule. This is subject to bi-lateral agreement between the Energy Supplier and the DNO, with no two DNOs operating the exact same process.
When the developer informs the DNOs of how many Import MPANs they require, they could also inform them how many of the properties require Export MPANs for creation at the same time (with the logical disconnection process being available for any Export MPANs that are then not required).
Large manual workloads for Energy Suppliers, with lack of standardised processes between DNOs, is leading to unnecessary costs and timescales when setting up large numbers of Export MPANs for new housing developments.
Where they are informed of properties requiring Export MPANs by the developer, DNOs create the Export MPAN as well as the Import MPAN.
-

Impacts

Electricity
Achieving Net Zero, Billing accuracy, On site experience
The increased uptake of microgeneration (particularly at domestic properties) is a direct link to achieving net zero. The market needs to make the bulk creation of Export MPANs as easy and resource-light as possible.
Schedule 27 - RMP Lifecycle
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Distribution Network Operators, Energy Suppliers
-
No details provided
-
-
No details provided

Priority & timing

No
-
-
-
No details provided
Achieving Net Zero, Billing accuracy, On site experience

Activity