Clarify obligations on gas meter exchanges that occur close to CoS
Summary
This change has been raised to address an issue with the 'Switch with a Concurrent Change of MEM process.'. MEMs are obliged to issue ONJOBs to the CDSP as part of a meter exchange. However, this would not be issued if the MEM has received a de-Appointment flow as part of the Switch. This change proposes to obligate MEMs to issue ONJOBs for any completed meter exchanges, even after receiving a de-Appointment flow. This will ensure accurate Meter Technical Details are available to the gaining Supplier and MEM.
Latest update and next planned activity
Date of latest update
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Impacts Overview
Impacted Consumers
Others
Domestic
Impacted REC Parties and Market Participants
Gas Meter Asset Manager (MAM)
Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Market Message Catalogue
Impacted REC Services
Gas Retail Data Service (GRDS)
Priority and rationale
Standard
Solution development
Problem Statement
When Metering Asset work is carried out concurrently with a Switch, details of the work undertaken may not be sent to industry by the MEM, resulting in inaccurate and out of date Metering Asset data being passed to the gaining Registered Gas Supplier.
Proposed solution summary
- As a Consumer, I want my Supplier to have accurate information about my meter, so that I do not experience billing problems following a Switch.
- As a MEM, I want to clearly understand my obligations relating to data transfer during a Switch, so that records of work I carry out are accurately recorded. 2 - As a Registered Supplier, I want metering data on my portfolio of Registrable Measurement Points to be accurate, so that Consumers do not experience billing problems or have a negative switch experience. 3 - As the CDSP, I want Change of Metering Asset data communicated with me to be timely and accurate, so that I am better able to fulfil my role and support REC Parties.
Solution documents
Documents Library
Change Plan
Solution Development & Analysis
Completed
Start:
17 Feb 2023Due:
29 Mar 2024Completion:
27 Mar 2024Party Impact Assessment Due
Completed
Start:
29 Mar 2024Due:
19 Apr 2024Completion:
19 Apr 2024Preliminary Change Report Issued
Completed
Start:
19 Apr 2024Due:
26 Apr 2024Completion:
26 Apr 2024Responsible Committee Review
Completed
Start:
26 Apr 2024Due:
08 May 2024Completion:
08 May 2024Consultation Closes
Completed
Start:
08 May 2024Due:
31 May 2024Completion:
31 May 2024Final Change Report Issued
Completed
Start:
31 May 2024Due:
05 Jun 2024Completion:
05 Jun 2024Responsible Committee Decision
Completed
Start:
05 Jun 2024Due:
12 Jun 2024Completion:
12 Jun 2024Appeal Window Closure
Not Started
Start:
12 Jun 2024Due:
26 Jun 2024Completion:
Original submission
Change details
David Morley - OVO Energy
17 Feb 2023
Change details
Clarify obligations on meter exchanges that occur close to CoS - gas only
Gas only change. Change of Supplier and Change or Metering processes overlap. This causes metering flows to not be issued. This happens from time to time and is exasperated by Faster Switching. In the REC Metering Operations Schedule, 8.5.10 is the step under which MAMs (as MEMs) are obliged to issue ONJOBs to the CDSP as part of a meter exchange. However, this would not be issued if the MAM is deappointed under step 9.5.10 in the Switch with Concurrent Change of MEM process.
This means that the incoming MAM has incorrect meter details, GES is incorrect, the customer's bill is incorrect, settlement will be incorrect, MAP data will be wrong.
A change is needed here to place an obligation on the MAM to issue ONJOBs for meter exchanges they have been instructed to complete regardless of whether they have been in receipt of a deappointment flow. Following on from that, I think the CDR and UNR set up needs to be surfaced, or at the very least referenced, in the Metering Operations Schedule. The incoming MAM/Shipper/Supplier can then use the CDR and UNR to ensure that meter details are correct on CoS. 8.5.10 could be updated to include the text: "This step must be completed regardless of whether the supplier is no longer the current supplier. Following this the gaining MEM, must pick up the corresponding CDR or UNR". 9.5.10 could be updated to include the text: "if a meter exchange occurred during the Losing MEM's appointmenet period, meter exchange flows must be issued to CDSP and the gaining MEM, must pick up the corresponding CDR or UNR ".
-
Impacts
Gas
Switching experience, Billing accuracy, Trust and confidence, Safety, Security of supply, Ability to pay, On site experience
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Market Message Catalogue
-
No details provided
-
Gas Retail Data Service
-
Energy Suppliers, Shippers
-
No details provided
-
No
No details provided
Priority & timing
No
-
Prior to next day switching
No
No details provided
-