REC Schedule 27 – RMP Lifecycle

Contents

See also: REC Schedules

The RMP Lifecycle is a mandatory schedule for all Suppliers, Gas Transporters, Distribution Network Operators and DCC. It details the processes for:

  • establishing an RMP Record within the Electricity Retail Data Service and Central Switching Service following the establishment of a new electricity Metering Point
  • establishing an RMP Record within the Central Switching Service following the establishment of a new gas Supply Meter Point in accordance with the UNC
  • terminating an RMP Record within the Central Switching Service following disconnection of a Metering Point in accordance with the DCUSA or a Supply Meter Point in accordance with the UNC or IGT UNC
  • amending the data recorded against an RMP Record within the Central Switching Service, following an update to the Electricity Retail Data Service or Gas Retail Data Service
  • establishing additional Metering Points within the Electricity Retail Data Service, following a request from an Electricity Supplier

The Schedule also outlines RMP statuses.

You can access this schedule with a Portal account on the Digital REC.

RMP Statuses

An RMP will have one of the following statuses

  • Created – indicates that a Metering Point has a status of ‘New’ or ‘Registered’ as defined within the Data Specification. This RMP Status only applies to electricity RMPs
  • Operational – indicates that a gas RMP is capable of offtaking gas (and is not Isolated or no longer capable of flowing gas); or for electricity RMPs, that the RMP has a status of ‘Traded’ as defined within the Data Specification
  • Dormant – indicates that the Supply Meter Point has been Isolated. This RMP Status only applies to gas RMPs
  • Terminated – indicates that a gas RMP has been no longer capable of offtaking gas; or in the case of electricity RMPs have been disconnected