Combined progression of Change Proposals R0058, R0104 and R0129
Summary
This change seeks to efficiently address the issues raised under the following Change Proposals. R0058 – REC Services Procurement Clarification R0104 – Clarifying Requirement for Continuous Billing Following an Erroneous Switch R0129 – Clarifying Event of Default Requirements These Change Proposals have been identified by the Code Manager as requiring non-contentious, clarificatory and non-material alterations to the REC Legal Text only.
Latest update and next planned activity
Date of latest update
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Impacts Overview
Priority and rationale
Standard
Solution development
Problem Statement
Three Change Proposals have been placed on hold due to having a low priority status. These proposals have been identified as having fully formed solutions, which are non-contentious and can be quickly implemented. This change seeks to address these Change Proposals so that they can be addressed, and their benefits realised.
Proposed solution summary
- As a Market Participant, I need the REC drafting to be accurate, so I can rely on it to ensure my processes and procedures correctly reflect my obligations. If there are mistakes or omissions, then it could cause issues with the effective operation and assurance of the retail energy market.
Solution documents
Documents Library
Change Plan
Preliminary Change Report published
Completed
Start:
04 Aug 2023Due:
01 Sep 2023Completion:
01 Sep 2023Consultation close
Completed
Start:
01 Sep 2023Due:
15 Sep 2023Completion:
15 Sep 2023Final Change Report published
Completed
Start:
15 Sep 2023Due:
22 Sep 2023Completion:
22 Sep 2023Responsible Committee decision
Not Started
Start:
22 Sep 2023Due:
03 Oct 2023Completion:
Original submission
Change details
Elise Handy - REC Code Manager
4 Aug 2023
Change details
Combined progression of Change Proposals R0058, R0104 and R0129
This change seeks to efficiently address the issues raised under the following Change Proposals.
R0058 – REC Services Procurement Clarification
R0104 – Clarifying Requirement for Continuous Billing Following an Erroneous Switch
R0129 – Clarifying Event of Default Requirements
These Change Proposals have been identified by the Code Manager as requiring non-contentious, clarificatory and non-material alterations to the REC Legal Text only.
R0058 – REC Services Procurement Clarification
R0104 – Clarifying Requirement for Continuous Billing Following an Erroneous Switch
R0129 – Clarifying Event of Default Requirements
These Change Proposals have been identified by the Code Manager as requiring non-contentious, clarificatory and non-material alterations to the REC Legal Text only.
R0058 – REC Services Procurement Clarification The Data Communications Company (DCC) highlighted that the current drafting within Clause 5.3 of the REC Main Body could impact both RECCo and the DCC’s ability to protect input VAT entitlements as a recipient of the Centralised Registration Service (CRS).
R0104 – Clarifying requirement for Continuous Billing following Erroneous Switch R0104 - One of the required outcomes of an Erroneous Switch is that the Consumer is only billed once for the period of Erroneous Switch. Currently this is unclear in Schedule 30.
R0129 – Clarifying Event of Default Requirements Following several recent events of non-payment for services and REC defaults, it has been identified that the Event of Default provisions in the Code are unclear.
R0104 – Clarifying requirement for Continuous Billing following Erroneous Switch R0104 - One of the required outcomes of an Erroneous Switch is that the Consumer is only billed once for the period of Erroneous Switch. Currently this is unclear in Schedule 30.
R0129 – Clarifying Event of Default Requirements Following several recent events of non-payment for services and REC defaults, it has been identified that the Event of Default provisions in the Code are unclear.
All three changes require the REC Schedules to be updated and their intent to be made explicitly clear.
Three Change Proposals have been placed on hold due to having a low priority status. These proposals have been identified as having fully formed solutions, which are non-contentious and can be quickly implemented. This change seeks to address these Change Proposals so that they can be removed from hold and their benefits realised.
Impacts
Electricity, Gas
Switching experience, Billing accuracy, Trust and confidence
-
REC Main Body, Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Energy Suppliers
R0129 - Impacts the Code Manager and RECCo.
No details provided
-
No
No details provided
Priority & timing
No
-
No
No
No details provided
-