Changes to SDEP Messages and Schedule numbering for REC V3.0

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
-

Latest update and next planned activity

Date of latest update
Latest Update
-

Impacts Overview

Impacted Consumers
Non-Domestic Domestic
Impacted REC Parties and Market Participants
Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Market Message Catalogue
Priority and rationale
High

Solution development

Problem Statement
The Secure Data Exchange Portal (SDEP) will be updated at CSS Go-Live Date to reflect the new processes being introduced as part of REC V3.0. The SDEP messages and Data Items in the Energy Market Architecture Repository (EMAR) do not currently reflect these new processes. SDEP users require the Data Specification to accurately reflect the messages and Data Items to enable them to meet their obligations.
Proposed solution summary
  1. As a Consumer, I want my Energy Supplier to resolve any Switching or billing issues in a timely manner without unnecessary delays, so that I can receive accurate and timely bills from my chosen Energy Supplier.
  2. As an SDEP User, I want to understand any changes to SDEP messages I need to send and receive that may impact my business, so I can engage in the process and plan any required changes to my processes.
Solution documents
R0045 - Draft Legal Text 05 Jun 2026 DOCX - 698.75 KB
05 Jun 2026
Change Plan

Preliminary Change Report issued

Completed

Start:

05 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Consultation Issued

Completed

Start:

27 May 2022

Due:

27 May 2022

Completion:

27 May 2022

Consultation closure

Completed

Start:

27 May 2022

Due:

14 Jun 2022

Completion:

14 Jun 2022

Final Change Report issued

Completed

Start:

14 Jun 2022

Due:

22 Jun 2022

Completion:

22 Jun 2022

Responsible Committee Decision

Completed

Start:

22 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022

Original submission

Change details

Jon Hawkins - RECCo
5 May 2022

Change details

Changes to SDEP Messages for REC V3
REC V3 will be implemented on 18th July 2022 and, among other things, will introduce a new Resolution of Consumer Facing Switching and Billing Issues (CFSB) Schedule to supersede the existing processes in the MRA Transition Schedule and SPAA Transition Schedule for REC Parties to resolve switching and billing exceptions between each other.

Part of the changes in the CFSB Schedule is to introduce a standardised and shortened escalation process between Suppliers that will apply to all processes set out in the Schedule. This will change the way that Suppliers need to interact with each other, and the individual points of contact used in the current processes, to reflect the new resolution and escalation processes being introduced.

The majority of these interactions between Suppliers and, in some cases, Distribution Network Operators, is managed through the Secure Data Exchange Portal (SDEP), where users can send unstructured messages to each other to investigate and resolve issues through a secure system, rather than the use of email. The changes being introduced with REC V3 will impact the existing SDEP messages and require these to be updated.
SDEP users will require the SDEP messages being used to reflect the new process being introduced with REC V3 in order to meet their obligations in the REC.
The required changes to the SDEP have been agreed with the SDEP Service Provider, and are due to be implemented at CSS Go-Live with REC V3. As the SDEP messages are set out in the Data Specification, a Change Proposal is required to reflect the changes to these messages in the Energy Market Architecture Repository (EMAR).

The existing SDEP messages in the EMAR are also not populated correctly, and do not accurately reflect the data items relevant to each message or the conditionality of these. This change will also update these so that all SDEP messages will be represented accurately in the EMAR from REC V3.

Changes being made to the SDEP are:

Housekeeping Updates – existing SDEP messages in the EMAR need to be updated to correctly reference the relevant data items and the associated conditionality of these data items. There are also some existing SDEP messages that aren’t reflected in the EMAR, which will need to be added.

Removal of the “second escalation” from escalation messages – the CFSB Schedule has removed the “second escalation” from the existing escalation processes, and there will now only be a first escalation to an operational contact, followed by a final escalation to the REC Contract Manager. The following messages will be amended to reflect this from CSS Go-Live:
- Disputed Meter Readings (Gas.) – Escalation
- Missing and Disputed Meter Readings (Elec.) - Escalation
- Erroneous Transfers (Elec.) – Escalation
- Erroneous Transfers (Gas.) - Escalation
- Erroneous Transfer Re-registration (Elec.) – Escalation
- Erroneous Transfer Re-registration (Gas.) – Escalation
- Debt Assignment Protocol (Elec.) – Escalation
- Debt Assignment Protocol (Gas.) – Escalation
- Misdirected Payments (Elec.) – Escalation
- Misdirected Payments (Gas.) – Escalation
- Crossed Meters (Gas.) – Escalation
- Duplicate Meter Points (Gas.) – Escalation

Where there are existing messages at a “second escalation” stage, the following will be applied:

- All existing active and archived Communications, belonging to the above Process Types at Second Escalation, at the time of the change will be downgraded to First Escalation.
- A record will be added to the Audit History for each affected Communication stating that the Communication Escalation was changed by the System.
- The ‘Last Escalated Date’ will be updated by this change, meaning, the sender of an affected Communication will have to wait the given number of days (5 Working Days) before escalating the Communication again.
- Any users, assigned to Second Escalation for the above Process Types, will be reassigned to First Escalation. If the user is already assigned to First Escalation, they will only be removed from Second Escalation.

New messages – four new messages will be introduced to the SDEP as part of REC V3. These are:
- Replacement Readings (Gas.) – Escalation
- Crossed Meters (Elec.) – Escalation
- Duplicate Meter Points (Elec.) – General Query
- Duplicate Meter Points (Elec.) – Escalation

These messages will only impact Energy Suppliers, who will need to assign relevant team members to the new process types to ensure they are able to send and receive these messages.

Removed messages – the following messages will be removed from REC V3, as the processes they relate to will no longer be in operation:
- Customer Requested Objections (Elec.) – General Query
- Customer Requested Objections (Gas.) – General Query.
Once these are removed, users will no longer be able to create new communications or assign users to these process types. It will still be possible to perform the following actions belonging to these process types:
- Download attachments
- Delete attachments
- Archive communication
- Export communication
- Assign/unassign owner
- Read existing comments
- View Audit History
It will not be possible to perform the following actions:
- Add a new comment
- Add a new attachment
- Update search tags
- Update data items

Update process type name – the existing process type “CSS Data Cleanse (Elec.) – General Query” will be updated to “Supplier Data Error Resolution (Elec.) General Query”. This reflects the fact that this will no longer be required for CSS Data Cleansing, but will still be required by Suppliers and Distributors to resolve ongoing data quality issues. Therefore, the message has been retained (as requested by the Switching Programme Data Working Group) but the name has been updated to reflect the enduring use.
-

Impacts

Electricity, Gas, Domestic Prepayment, Domestic Credit, Microbusiness, Small and Medium Enterprise (SME), Industrial and Commercial (I&C)
Switching experience, Billing accuracy
-
No details provided
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
Updates are required to the SDEP messages in the Market Message Catalogue, and associated Data Items in the Data Item Catalogue.
No details provided
-
Secure Data Exchange Service
Changes have already been impact assessed, costed and approved to the SDEP. Therefore, there is no need for further impact assessment with the Service Provider.
Energy Suppliers, Distribution Network Operators
-
Balancing and Settlement Code (BSC), Distribution Connection and Use of System Agreement (DCUSA)
There is no consequential change required to the BSC or DCUSA, but it should be noted that some of the housekeeping updates required relate to processes that will be governed under these codes from REC V3.
Yes
No details provided

Priority & timing

Yes
This will need to be progressed under an urgent timetable in order to be implemented in time for REC V3. There was confusion regarding the home of the SDEP messages following the introduction of REC V2, which is why these amendments weren’t picked up as part of the wider REC V3 data specification changes. The changes are being implemented to the SDEP already, and associated guidance is being delivered to REC Parties through updates to the SDES User Guide (Category 3 document), but the EMAR should be updated to reflect this as well.
This should be implemented on 18 July 2022 as part of REC V3.

We propose that this CP follow the following timetable:
- Presentation to Change Panel – 17/05/2022
- Industry Consultation – 27/05/2022 – 14/06/2022 (10 Working Days)
- Final Change Report issued to Technical Expert Panel – 22/06/2022
- Technical Expert Panel Decision – 29/06/2022
This should be implemented on 18 July 2022 as part of REC V3.
No details provided
-

Activity

Proposed solution summary changed to As a Consumer, I want my Energy Supplier to resolve any Switching or billing issues in a timely manner without unnecessary delays, so that I can receive accurate and timely bills from my chosen Energy Supplier.As…
Show more
Implementation Date has been updated to 18 Jul 2022.
beth.brown has been allocated as SME.