Creation of a Tool to Manually Correct ERDS / CSS Discrepancies

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
There is currently a tool utilised by DNOs to manually correct registration data to align the Registered Supplier in ERDS with the data held in CSS. The Market-Wide Half Hourly Settlement (MHHS) Design does not allow for retrospective amendment of Supplier Registration i.e. there is no equivalent tool for manual correction post MHHS go live (M10). Therefore, post MHHS implementation, any issues which prevent CSS data being reflected in ERDS cannot be corrected. This will prevent the Supplier from appointing agents and will lead to errors in settlement data under the BSC. A change is required to address this.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal was implemented on 27 March 2026.

Impacts Overview

Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Distribution Network Operator (R) Data and Communications Company (DCC) Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Impacted REC Services
Electricity Retail Data Service (ERDS)
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
High

Change Reports, Impact Assessments, Consultations and Documents

Change Reports

Solution development

Problem Statement
There are instances where ERDS (and SMRS under BSC governance) can be misaligned with the CSS and under the MHHS arrangements there is no mechanism for manual correction which there is in place today. From MHHS go live the Supplier will not be able to appoint their preferred agents. This issue only applies to MHHS Migrated Metering Points as the existing mechanism for manually correcting data would be used if the issue related to a non-migrated Metering Point. In the event that the Supplier cannot appoint its agents, this may prevent the Supplier from accurately billing the Consumer. The potential impact will increase as MHHS Migration continues, with more MHHS Metering Points potentially impacted by any CSS / ERDS discrepancy.
Solution documents
Indicative PARC extract for R0201 05 Jun 2026 XLSX - 21.94 KB
05 Jun 2026
05 Jun 2026
05 Jun 2026
Documents Library
Change Plan

Change Issue Group

Completed

Start:

01 Aug 2024

Due:

01 Aug 2024

Completion:

01 Aug 2024

Proposal Plan Approval

Completed

Start:

01 Aug 2024

Due:

03 Sep 2024

Completion:

03 Sep 2024

Original submission

Change details

Andrew Wallace - RECCo
2 Aug 2024

Change details

Creation of a Tool to Manually Correct ERDS / CSS Discrepancies
There is currently a tool utilised by DNOs to manually correct registration data to align the Registered Supplier in ERDS with the data held in CSS.

The Market-Wide Half Hourly Settlement (MHHS) Design does not allow for retrospective amendment of Supplier Registration i.e. there is no equivalent tool for manual correction post MHHS go live (M10).

Therefore, post MHHS implementation, any issues which prevent CSS data being reflected in ERDS cannot be corrected. This will prevent the Supplier from appointing agents and will lead to errors in settlement data under the BSC.

This is a known exception which occurs regularly today, with DNOs reportedly being required to correct a hundred of these exceptions each month. Any delay in implementing a mechanism to correct these exceptions for MHHS Migrated Metering Points will therefore result in an increasing backlog of erroneous registration data in the DNO’s SMRS.
From MHHS go live, where an issue arises which leads to the ERDS (and SMRS under BSC governance) from reflecting the correct Registered Supplier, the Supplier will not be able to appoint agents. This issue only applies to MHHS Migrated Metering Points as the existing mechanism for manually correcting data would be used if the issue related to a non-migrated Metering Point.

In the event the Supplier cannot appoint its agents this will impact both Settlements and create a safety risk for the consumer, as there will be no Meter Operator Agent (MOA) appointed to attend site in the event of an emergency. Furthermore, the absence of Meter Technical Details and validated meter readings may prevent the Supplier from accurately billing the Consumer.

The potential impact will increase as MHHS Migration continues, with more MHHS Metering Points potentially impacted by any CSS / ERDS discrepancy.
A tool to enable manual correction of registration data is required that can be utilised alongside the wider MHHS design processes (equivalent to the existing tool).

Where discrepancies are identified, DNOs could then manually correct the data. Once the correct Supplier is registered to the Metering Point, the Supplier will be able to appoint agents.
This issue was initially discussed by the MHHS Programme with CR045 raised and impact assessed. CR045 was rejected by the MHHS Programme as it could not be delivered ahead of MHHS go live (M10). It was noted that parties were supportive of the change and agreed that it should be passed to code bodies to deliver through the BAU change processes at the earliest feasible implementation date.

Impacts

Electricity
Switching experience, Billing accuracy, Trust and confidence
Under the MHHS Design, the registration service (SMRS) is central to the agent appointment process. If the SMRS does not hold the correct Registered Supplier then an MOA cannot be appointed which may prevent meter works being progressed.
Schedule 14 - Metering Operations
Clarification to be added to the Metering Operations Schedule to confirm that the MOA appointment should be progressed once registration data is corrected.

Specifically the following to be added against the MHHS drafting in paragraph 22.6.18, 22.9.23 and 22.11.23:

‘An MOA Appointment request may be lapsed where a valid Registration is not reflected within SMRS. Once this discrepancy is resolved, the Electricity Supplier shall issue a new MOA Appointment request’.
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Electricity Retail Data Service
Paragraph 11.5 of the ERDS Service Definition currently states that: Upon receipt of a Market Message that indicates / infers a data inconsistency with the CSS, the ERDA will initiate the required steps to determine the necessary resolution.
REC CP to add addition statement that:
‘The ERDA shall develop and maintain a tool to enable Registration data to be manually corrected within ERDS where this is inconsistent with the data held in the CSS’.
Energy Suppliers, Distribution Network Operators
-
Balancing and Settlement Code (BSC)
Whilst the REC change can place an obligation on the ERDA to correct data, a parallel BSC change is also required to introduce the new business process elements, with DIP market messages issued to participants once the registration data is corrected.
No
No details provided

Priority & timing

No
-
The change should be implemented as soon as possible (subject to formal impact assessment). Should any issues arise post MHHS go live (M10) which impact MHHS Migrated Metering Points, then there is no way to manually resolve the issue and correct the registration data.
Market Participants have previously raised concerns with implementation of this change before M10 due to MHHS design, build and test priorities.

In addition, the interaction with the parallel BSC change should be considered. Whilst it may be feasible to implement the REC CP independently, delivery efficiencies may be gained with parallel implementation.
No details provided
-

Activity

Status has been changed to Implemented.
holly.law has been allocated as Lead Analyst.
Change report - Final Change Report has been updated to Comments deadline for R0201 Change Report (Final) v1.0 Post Vote.pdf - 2025-10-07.
Implementation Date has been updated to 27 Mar 2026.
holly.law has been allocated as Lead Analyst.
Orphaned SME: Lead Technical Analyst, vaishnsharma have been allocated as SME.