Cross code change to align with BSC CP1598

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
This Change Proposal has been raised to align with BSC CP1598, which states that six Scenario Variants of Market Messages specified within the early drafting of P375 were not progressed to the final solution of P375 and REC CP R0008.

Latest update and next planned activity

Date of latest update
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.

Impacts Overview

Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Energy Supplier (ES)
Impacted REC Documents
Market Message Catalogue
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
Standard

Solution development

Problem Statement
As these Scenario Variants are not captured in the Data Specification, the relevant Market Participants won’t be able to use the Data Transfer Network (DTN) to exchange the relevant data, which would result in them having to use a less secure mechanism to send and receive data. This means the original intent of Elexon Modification P375 has yet to be achieved as not all Market Message changes have been implemented.
Solution documents
R0206 Solution Document v1.0 05 Jun 2026 PDF - 165.95 KB
05 Jun 2026

There is currently no Change Plan.

Original submission

Change details

Lorna Mallon - REC Code Manager
22 Aug 2024

Change details

Cross code change to align with BSC CP1598
CP1598 states that six Scenario Variants of Market Messages specified within the early drafting of P375 were not progressed to the final solution of P375 and REC CP R0008.
The original intent of P375 has yet to be achieved as not all Market Message changes have been implemented.
See BSC CP1598 which sets out the scenario variant updates.
CP1598 has already been through the BSC industry consultation process with a finalised solution and is due to be presented at SVG for approval on 3rd September.

Impacts

Electricity, Industrial and Commercial (I&C)
Other (please provide details in Additional information box below)
See P375 for original impacts.
No details provided
-
No details provided
-
No details provided
-
Market Message Catalogue
Update with the following new scenario variants:
D0008 ‘Meter Advance Reconciliation Report’ from Half Hourly Data Collector (HHDC) to SVA Meter Operator Agent (MOA)
D0011 ‘Agreement of Contractual Terms’ from MOA to AMVLP
D0268 ‘Half Hourly Meter Technical Details’ from AMVLP to MOA
D0268 ‘Half Hourly Meter Technical Details’ from Supplier to MOA
D0390 ‘Asset Metering System Half Hourly Metered Data’ from HHDC to AMVLP
D0390 ‘Asset Metering System Half Hourly Metered Data’ from HHDC to Supplier
No details provided
-
No details provided
-
No details provided
-
Balancing and Settlement Code (BSC)
CP1598 has already been raised and BSC is the lead code
No
No details provided

Priority & timing

Yes
BSC CP1598 (pending approval) is tabled for the November 2024 release
None flagged within BSC CP1598
SVG approval on 3rd September 2024.
No details provided
-

Activity

Implementation Date has been updated to 08 Nov 2024.
Orphaned SME: Lead Technical Analyst, Orphaned SME: Lead Assurance Analyst have been allocated as SME.