Addition of the SOQ information for TPIs
Summary
As TPIs we are employed by our customers to check that the charges are being applied correctly. One of the big issues year after year is when the SOQ changes for a supply prior to the next supply contract renewal. As you are hopefully aware, the standing charges for Gas supplies are primarily built up around the Transportation charges. And one of the main component parts in the calculation of the standing charge is the SOQ. When we are asked to :- a) Validate the standing charge on any new offer, we are reliant on the supplier simply getting the SOQ correct. We need to see the SOQ so that we can work out what the standing charge should be. - then we challenge the supplier before they get the charges wrong. b) Our customers also want us to forecast the rates/costs for the coming year. This is impossible without access to the SOQ.
Latest update and next planned activity
Date of latest update
Latest Update
28/07/2026 - update to plan published for decision at the Change Panel on 4 August 2026.
Impacts Overview
Priority and rationale
Standard
Solution development
Documents Library
There is currently no Change Plan.
Original submission
Change details
Christopher Berry - Sustainable Energy First
5 Jun 2025
Change details
Addition of the SOQ information for TPIs
As TPIs we are employed by our customers to check that the charges are being applied correctly. One of the big issues year after year is when the SOQ changes for a supply prior to the next supply contract renewal. As you are hopefully aware, the standing charges for Gas supplies are primarily built up around the Transportation charges. And one of the main component parts in the calculation of the standing charge is the SOQ. When we are asked to :- a) Validate the standing charge on any new offer, we are reliant on the supplier simply getting the SOQ correct. We need to see the SOQ so that we can work out what the standing charge should be. - then we challenge the supplier before they get the charges wrong. b) Our customers also want us to forecast the rates/costs for the coming year. This is impossible without access to the SOQ.
Without access to the official SOQ we are blind when it comes to checking the suppliers are charging correctly. We often find that any large changes from one year to the next in the standing charge will need challenging and all we ever get back is that the SOQ has changed.
The V3 GES Data Access Matrix contains the following data items:- Formula Year SMP SOQ SMP SOQ SMP SOQ Effective Date Formula Year SMP SOQ Prospective Formula Year SMP SOQ Current Year Minimum SOQ SMP SOQ CSEP SOQ CSEP Connection Max SOQ But none of these are available to be viewed by TPIs. The simple solution is to allow all of these (or at least the ones that are relevant to commercial standing charges) to be available to TPIs.
We know how to calculate the Standing Charge and having access to the SOQ will allow us to predict and validate the standing charges without the need to challenge the supplier every year. It will also allow us to provide our customers with the forecast of costs that they desperately need every quarter.
Impacts
Gas, Industrial and Commercial (I&C)
Billing accuracy, Trust and confidence, Other (please provide details in Additional information box below)
It will allow the likes of Sustainable Energy First to calculate the expected standing charge. (The Gas Transporters already publish how to calculate the Standing charges each year in their LDZ Transportation Charging Statement) but this information is useless without the SOQ, hence why we are asking for it to be made available.
REC Main Body, Schedule 6 - Performance Assurance, Schedule 10 - Charging Methodology, Schedule 12 - Data Access
I wasn't sure which section of the REC Schedule needs to reflect giving TPIs a little bit more information - so I selected the items above that I thought might fit the request.
REC Change Panel - Terms of Reference
Again I wasn't sure which section of the Operational Docs needs to reflect giving TPIs a little bit more information - so I selected the item above that I thought might fit the request.
Central Data Service Provider Further Services Service Definition
Again I wasn't sure which section of the Service Specifications need to reflect giving TPIs a little bit more information - so I selected the items above that I thought might fit the request.
Data Access Matrix
To me the - question is more around - why wouldn't the SOQ be provided to TPI's? Seems strange to refuse access to this.
GES Meter Asset Enquiry API Technical Specification, GES Supply Point Enquiry API Technical Specification, GES Supply Point Switching API Technical Specification
I wasn't sure which section API Technical Specifications need to reflect giving TPIs a little bit more information - so I selected the items above that I thought might fit the request.
Gas Enquiry Service
We need it in the Gas Enquiry service. (Which I believe is only available through API at the moment for TPIs - but hopefully that will change soon to allow TPI's access to the web-based login search facility.)
Third-Party Intermediary
-
No details provided
I don't know if any other Codes require adjusting/amending to accommodate the access for TPI's
Not Sure
No details provided
Priority & timing
Yes
This has been gong on for years. We - at Sustainable Energy First - work hard on behalf of our customers to make sure that their prices are correctly calculated and the Gas Standing Charge is a major cost for a lot of our customers and without the SOQ we simply have to make big assumptions each year as to whether we challenge the supplier or not.
Development: I don't believe any development is required, I would imagine there is a "switch" of "Y" or "N" in the TPI column on the GES Data Access Matrix. The 9 relevant rows simply need changing to "Y".
Implementation: By April 25 would be good. Certainly we need it to happen before Sept 25 - which is when we start getting Gas prices for our customers
Implementation: By April 25 would be good. Certainly we need it to happen before Sept 25 - which is when we start getting Gas prices for our customers
No - I don't believe there are.
No details provided
Billing accuracy, Trust and confidence, Other (please provide details in the Additional information box below)