Consequential Cross-Code Change for BSC P441 - Complex Site Classes Creation

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 4 of 6
Decision
Summary
The Balancing and Settlement Code (BSC) modification P441 is looking to introduce Complex Site classes which would categorise the types of Complex Site with each having clearly defined criteria within the BSC whilst also facilitating a new "type" of Complex Site (referred to as a Class 6 Complex Site) to allow approval of "non-standard" Complex Sites. It will also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted.

Latest update and next planned activity

Date of latest update
Latest Update
15/10/2026 On 14 October 2026, REC Metering Expert Panel voted to recommend that the Authority approve this Change Proposal, in line with the Code Manager recommendation. The Change Report (Final Recommendation) V2.0 has been issued to the Authority.

Impacts Overview

Impacted Consumers
Others
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Half Hourly Data Collector (C) Non Half Hourly Data Collector (D) Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Other Industry Codes impacted
Balancing and Settlement Code (BSC) Distribution Connection and Use of System Agreement (DCUSA)
Priority and rationale
High

Solution development

Problem Statement
The introduction of new Complex Site classes is needed into the REC to facilitate the solutions under BSC P441 and DCP 424.
Solution documents
R0268 Metering Operations v0.1 draft 05 Jun 2026 ZIP - 1.08 MB
05 Jun 2026
Documents Library
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

21 Oct 2025

Extension to Plan approved by MEP

Completed

Start:

Due:

Completion:

14 Jan 2026

Final Recommendation approved at MEP

Completed

Start:

Due:

Completion:

11 Mar 2026

Final Recommendation V2.0 approved at MEP

Completed

Start:

Due:

Completion:

14 Oct 2026

Original submission

Change details

Caroline Freimuller - REC Code Manager
28 Jul 2025

Change details

Consequential Cross-Code Change for BSC P441 - Complex Site Classes Creation
The BSC Modification P441 is looking to introduce complex site classes which would categorise the types of Complex Site with each having clearly defined criteria within the BSC whilst also facilitating a new "type" of Complex Site (referred to as a Class 6 Complex Site) to allow approval of "non-standard" complex sites. It will also clarify when the netting of Imports from Exports for multiple Metering Systems registered in Supplier Volume Allocation (SVA) is permitted. The REC documentation and data specification will need to be updated to reflect the new classes being introduced.
The current processes do not cater for additional Complex Site Classes to be introduced.
The inclusion of new Complex Site Classes being incorporated into the REC Schedules and Data Specification.
This is a Cross-Code Change, which impacts both the Balancing & Settlement Code (Modification P441) and Distribution Connection and Use of System Agreement Code (DCUSA) (DCUSA Change Proposal 424). This CP will also need to be developed in a timeline that aligns with both the BSC and the DCUSA.

Impacts

Electricity
Other (please provide details in Additional information box below)
They will be appropriately categorised for their metering systems, allowing other processes within the BSC and DCUSA to work effectively.
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
Data Item Catalogue, Market Message Catalogue
-
No details provided
-
No details provided
-
Distribution Network Operators, Energy Suppliers, Meter Operator Agent
-
Balancing and Settlement Code (BSC), Distribution Connection and Use of System Agreement (DCUSA)
-
No
No details provided

Priority & timing

No
-
We are not the Lead code for this change, and will have to align our change plans with those of the BSC (the Lead Code).
-
No details provided
Other (please provide details in the Additional information box below)

Activity

Implementation Date has been updated to 06 Nov 2026.
Implementation Date has been updated to 26 Jun 2026.