Implementation of IF-051 Data Refresh in EES for BSC CP1607
Summary
The IF-051 provides a refresh of data from Supplier Meter Registration Service (SMRS) to the Electricity Enquiry Service (EES) (REC) and Market Data Service (BSC). Currently the REC does not hold any detail regarding the DIP Market Messages that the EES is required to receive and process. Due to the nature of the IF-051, the EES Provider obligations need to be clear to ensure the interface can be received and processed appropriately.
Latest update and next planned activity
Date of latest update
Latest Update
28/10/2026 On 28 October 2026, the Technical Expert Panel voted, in line with the Code Manager’s recommendation, to approve the extension to plan for R0294. The Code Manager is working with the BSC on stakeholder workshops on a complete end-to-end solution, including the required market message specification, governance arrangements and operational processes. Stakeholder workshops will be held to run through the new ‘Data Refresh’ message, discuss the proposed change and gather stakeholder views on the full solution. The Code Manager will be attending these workshops to provide input on the new BSC CP, as well as impacts on the REC and REC services (primarily the Electricity Enquiry Services).
Impacts Overview
Impacted Consumers
Non-Domestic
Domestic
Impacted REC Parties and Market Participants
Electricity Distribution Network Operator (R)
Others
Impacted REC Services
Electricity Enquiry Service (EES)
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Data Integration Platform (DIP) Rules
Priority and rationale
Standard
Solution development
Problem Statement
BSC CP 1607 will implement a new DIP Market Message, the IF-051 ‘Data Refresh’ on 26 March 2026. EES will be a recipient of that change. If EES is not able to receive and process instances of the IF-051, data in EES will be misaligned with other industry systems (SMRS, DIP and MDS) meaning that it will not maintain its role as the accurate reference point for industry participants. This could lead to potential disruption of industry processes.
Solution documents
Documents Library
Change Plan
Proposal Plan approved at REC Change Panel
Completed
Start:
Due:
16 Dec 2025Completion:
16 Dec 2025Consultation published
Completed
Start:
Due:
12 Feb 2026Completion:
12 Feb 2026Consultation closed
Completed
Start:
Due:
27 Feb 2026Completion:
27 Feb 2026Proposal Plan update approved by Technical Expert Panel
Completed
Start:
Due:
25 Mar 2026Completion:
25 Mar 2026Proposal Plan update approved by Technical Expert Panel
Completed
Start:
Due:
Completion:
28 Oct 2026Original submission
Change details
Harriet Truss - REC Code Manager
27 Nov 2025
Change details
Implementation of IF-051 Data Refresh in EES for BSC CP1607
The Balancing and Settlement Code Change Proposal (BSC CP) 1607 will introduce a new Data Integration Platform (DIP) Market Message, the IF-051 Data Refresh.
The IF-051 provides a refresh of data from Supplier Meter Registration Service (SMRS) to the Electricity Enquiry Service (EES) (REC) and Market Data Service (BSC).
Currently the REC does not hold any detail regarding the DIP Market Messages that the EES is required to receive and process. Due to the nature of the IF-051, the EES Provider obligations need to be clear to ensure the interface can be received and processed appropriately.
The IF-051 provides a refresh of data from Supplier Meter Registration Service (SMRS) to the Electricity Enquiry Service (EES) (REC) and Market Data Service (BSC).
Currently the REC does not hold any detail regarding the DIP Market Messages that the EES is required to receive and process. Due to the nature of the IF-051, the EES Provider obligations need to be clear to ensure the interface can be received and processed appropriately.
By adding obligations and processing requirements into the REC, it will ensure the right data is updated and the appropriate data history is maintained in EES, as required when it has been agreed that the IF-051 should be triggered.
This change seeks to implement the IF-051 Data Refresh Market Message in EES, approved for implementation via BSC CP 1607.
The overall EES requirements relating to processing DIP messages were implemented as part of R0209 and R0241.
BSC CP 1607 was raised to progress the MHHS Programme’s On Hold Request OHCR003, originally Programme Change Request, CR-044 which the programme was not able to add to the MHHS design prior to MHHS Go-Live.
BSC CP 1607 was raised to progress the MHHS Programme’s On Hold Request OHCR003, originally Programme Change Request, CR-044 which the programme was not able to add to the MHHS design prior to MHHS Go-Live.
Impacts
Domestic Credit, Domestic Prepayment, Electricity, Industrial and Commercial (I&C), Microbusiness, Small and Medium Enterprise (SME)
Achieving Net Zero, Billing accuracy, On site experience, Switching experience
The IF-051 as a potential full registration refresh could impact a number of REC processes.
Through it’s support of data exchange under the MHHS market arrangements, this change is an enabler to new zero.
Through it’s support of data exchange under the MHHS market arrangements, this change is an enabler to new zero.
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
EES Users
EES Users - for awareness of the data refresh and how it will be used
Balancing and Settlement Code (BSC), Data Integration Platform (DIP) Rules
This REC change is a consequential change for BSC CP 1607 to ensure appropriate implementation of the BSC-owned IF-051 in EES.
A consequential DIP change is expected to be raised by the BSC to deliver the IF-051 for March 2026.
A consequential DIP change is expected to be raised by the BSC to deliver the IF-051 for March 2026.
Yes
No details provided
Priority & timing
No
This change needs to progress immediately to meet the approved implementation date of BSC CP 1607 on 26 March 2026, which is a MHHS Programme agreed addition to the MHHS design.
This will need to include a service provider impact assessment by the EES Provider
This will need to include a service provider impact assessment by the EES Provider
Development: As soon as possible, needs to align to additional BSC CP
Implementation: BSCP 1607 has been approved for implementation on 26 March 2026. The REC change should target the same date.
Implementation: BSCP 1607 has been approved for implementation on 26 March 2026. The REC change should target the same date.
Appropriate testing will be required, this may have a dependency on the testing arrangements, including with the DIP, for BSC CP 1607 which are targeting January 2026.
No details provided
Achieving Net Zero, Billing accuracy, On site experience, Switching experience