Amendments to the PARC relating to Address Management
Summary
While undertaking the CRS Improvements Project, RECCo, the Code Manager and DCC completed a review of current reporting that is generated as part of REC Obligations. As part of this review, Address Management-related reports were identified that are not fit for purpose. These reports are produced only for DCC internal consumption. The identified reports are captured in the Performance Assurance Report Catalogue (PARC). As such, DCC proposed raising a REC change to have these removed from the PARC (they will still be available on an ad-hoc on request basis).
Latest update and next planned activity
Date of latest update
Latest Update
The Final Recommendation has been published for determination by the REC Performance Assurance Board on 24 November 2026.
Impacts Overview
Impacted REC Services
Central Switching Service (CSS)
Priority and rationale
Standard
Change Reports, Impact Assessments, Consultations and Documents
Change Reports
Solution development
Problem Statement
As part of the Centralised Registration Service (CRS) Improvements Plan some Address Management-related reports included in the Performance Assurance Reporting Catalogue (PARC) were identified as not fit for purpose. These reports are produced only for DCC's internal consumption and are operationally burdensome to produce and store, but the PARC obligates their generation even where the data included in reports is available elsewhere.
Solution documents
Workgroup
Has a Workgroup supported the development of the Change Proposal?
No
There is currently no Change Plan.
Original submission
Change details
Bradley Baker - Smart DCC
13 Aug 2026
Change details
Amendments to the PARC relating to Address Management
While undertaking the CRS Improvements Project, RECCo, the Code Manager and DCC completed a review of current reporting that is generated as part of REC Obligations.
As part of this review, Address Management-related reports were identified that are not fit for purpose.
These reports are produced only for DCC internal consumption.
The identified reports are captured in the Performance Assurance Report Catalogue (PARC).
As such, DCC proposed raising a REC change to have these removed from the PARC (they will still be available on an ad-hoc on request basis).
The reports in question are:
Address Quality Summary
Unmatched REL Extract
Unmatched ME Extract
Matched Extract
Address Quality Report
Address Quality Postcode Report
Unchanged Postcodes Report
REL Updates Report - multiple reports
RELChange
RELSourceInitialRegistration
RELChangeRMP
As part of this review, Address Management-related reports were identified that are not fit for purpose.
These reports are produced only for DCC internal consumption.
The identified reports are captured in the Performance Assurance Report Catalogue (PARC).
As such, DCC proposed raising a REC change to have these removed from the PARC (they will still be available on an ad-hoc on request basis).
The reports in question are:
Address Quality Summary
Unmatched REL Extract
Unmatched ME Extract
Matched Extract
Address Quality Report
Address Quality Postcode Report
Unchanged Postcodes Report
REL Updates Report - multiple reports
RELChange
RELSourceInitialRegistration
RELChangeRMP
The reports have little to no value, yet the PARC obligates their generation.
Amend the PARC to remove these reports.
None.
Impacts
Other (please specify in the Additional information box below)
Other (please provide details in Additional information box below)
This change will have no impact on consumers.
No details provided
-
Performance Assurance Report Catalogue
This document lists the reports in question.
No details provided
-
No details provided
-
No details provided
-
Central Switching Service (CSS)
-
No details provided
-
No details provided
-
No
No details provided
Priority & timing
No
-
Development: No.
Implementation: Although not meeting the urgency criteria, DCC would like to see what should be a relatively simple change be implemented as soon as reasonably possible.
Implementation: Although not meeting the urgency criteria, DCC would like to see what should be a relatively simple change be implemented as soon as reasonably possible.
No.
No details provided
Other (please provide details in the Additional information box below)
Change Report - Open for Comments