Consequential REC changes for BSC CP1532
Summary
-
Latest update and next planned activity
Date of latest update
Latest Update
-
Impacts Overview
Impacted Consumers
Non-Domestic
Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
High
Solution development
Problem Statement
BSC CP1532 proposed updates to the Change of Supply (CoS) timescales within BSC Procedures BSCP502, BSCP504 and BSCP514, to align the Half-Hourly and Non-Half Hourly Supplier Agent Appointment and de-Appointment timescales and to facilitate the achievement of the Faster Switching programme objectives. BSC CP1532 was approved on 01 September 2021 by the Supplier Volume Allocation Group (SVG). Following the SVG’s decision to approve, BSCP514 moved to the Retail Energy Code (REC) following the implementation of P420 ‘Retail Code Consolidation Significant Code Review’. A REC Change Proposal is therefore required to deliver the full solution.
Proposed solution summary
- As an electricity Consumer I want my new Energy Supplier to set up my account and appoint their agents appropriately, so I receive timely and accurate bills.
- As a Market Participant, I need to understand any changes to Market Messages I send and receive that may impact my business, so I can engage in the change process and plan any required changes to my systems and processes.
- As an Energy Supplier, I want to be able to Appoint and De-appoint Agents more quickly, to minimise risks to my settlement performance and ability to produce accurate and timely consumer bills when the new switching arrangements go-live.
Solution documents
Documents Library
Change Plan
Initial Assessment Report and Change Proposal Plan approved
Completed
Start:
26 Nov 2021Due:
21 Dec 2021Completion:
21 Dec 2021Preliminary Change Report issued
Completed
Start:
21 Dec 2021Due:
28 Jan 2022Completion:
28 Jan 2022Preliminary Change Report approval
Completed
Start:
28 Jan 2022Due:
09 Feb 2022Completion:
09 Feb 2022Consultation starts
Completed
Start:
09 Feb 2022Due:
14 Feb 2022Completion:
11 Feb 2022Consultation ends
Completed
Start:
14 Feb 2022Due:
04 Mar 2022Completion:
04 Mar 2022Final Change Report Issued
Completed
Start:
04 Mar 2022Due:
11 Mar 2022Completion:
11 Mar 2022Responsible Committee decision (ex-Committee)
Completed
Start:
11 Mar 2022Due:
23 Mar 2022Completion:
22 Mar 2022Original submission
Change details
Ann Perry - -
26 Nov 2021
Change details
Consequential REC changes for BSC CP1532
Balancing and Settlement Code (BSC) CP1532 was approved on 01 September 2021 by the Supplier Volume Allocation Group (SVG).
CP1532 proposed updates to the Change of Supply (CoS) timescales within BSC Procedures BSCP502, BSCP504 and BSCP514, to ensure that all activities can be completed by the Initial Settlement Run (SF). This would align the appointment and de-appointment timescales (in both the NHH and HH processes) with the expected changes introduced to facilitate the Switching programme.
Following the SVG’s decision to approve CP1532, BSCP514 has moved to the Retail Energy Code (REC) following the implementation of P420 ‘Retail Code Consolidation Significant Code Review’.
This Change Proposal seeks to deliver the corresponding changes to REC Schedule 14 - Metering Operations, following the transition of BSCP514 to the REC.
An implementation date of February 2022 had initially been approved, however a revised date of 30 June 2022 will be recommended to the SVG in December, to enable the alignment of the BSC and REC Change Proposal implementation.
CP1532 proposed updates to the Change of Supply (CoS) timescales within BSC Procedures BSCP502, BSCP504 and BSCP514, to ensure that all activities can be completed by the Initial Settlement Run (SF). This would align the appointment and de-appointment timescales (in both the NHH and HH processes) with the expected changes introduced to facilitate the Switching programme.
Following the SVG’s decision to approve CP1532, BSCP514 has moved to the Retail Energy Code (REC) following the implementation of P420 ‘Retail Code Consolidation Significant Code Review’.
This Change Proposal seeks to deliver the corresponding changes to REC Schedule 14 - Metering Operations, following the transition of BSCP514 to the REC.
An implementation date of February 2022 had initially been approved, however a revised date of 30 June 2022 will be recommended to the SVG in December, to enable the alignment of the BSC and REC Change Proposal implementation.
If Parties use the maximum lead times available within the relevant BSCPs/REC Schedule, it is not currently possible for Half Hourly Supplier Agents to complete Change of Supply activities by the first Settlement Run.
The current arrangements are therefore not aligned with Ofgem’s Switching Programme objectives.
The current arrangements are therefore not aligned with Ofgem’s Switching Programme objectives.
Updates to the Change of Supply timelines within Schedule 14 – Metering Operations
Switch with Concurrent Change of MEM (Half Hourly)
• 9.6.2 - 5 Working Days (WD) to 2WD (sending D0261)
• 9.6.3 - 5WD to 2WD (sending D0011)
• 9.6.4 ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
• 9.6.6 - 5WD to 1WD (sending D0148/D0302)
• 9.6.7 - 2WD to 1WD (sending D0170)
• 9.6.8 - 5WD to 2WD (sending D0268/ Complex Site Supplementary Information Form)
Switch with Concurrent Change of MEM (Non Half Hourly)
• 9.7.4 - ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
Switch with No Concurrent Change of MEM (Half Hourly)
• 10.6.2 - 5WD to 2WD (sending D0261)
• 10.6.3 - 5WD to 2WD (sending D0011)
• 10.6.4 - ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
• 10.6.5 – ‘Between 5WD and 10WD of 10.6.3.’ to ‘Within 1 WD of receiving all applicable D0011s.’ (sending D0148/D0302)
Switch with No Concurrent Change of MEM (Non Half Hourly)
• 10.7.4 – ‘Within 5WDs of notification from MPAS or by last date of Supplier Appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
Footnote 55 – 5WD to 1WD
Footnote 59 – Typographical error - ‘exits’ to ‘exists’
Note: Full Legal text changes will be drafted as part of the REC Change Proposal, text changes to the REC Schedule have been proposed based on previously drafted changes to BSCP514.
Switch with Concurrent Change of MEM (Half Hourly)
• 9.6.2 - 5 Working Days (WD) to 2WD (sending D0261)
• 9.6.3 - 5WD to 2WD (sending D0011)
• 9.6.4 ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
• 9.6.6 - 5WD to 1WD (sending D0148/D0302)
• 9.6.7 - 2WD to 1WD (sending D0170)
• 9.6.8 - 5WD to 2WD (sending D0268/ Complex Site Supplementary Information Form)
Switch with Concurrent Change of MEM (Non Half Hourly)
• 9.7.4 - ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
Switch with No Concurrent Change of MEM (Half Hourly)
• 10.6.2 - 5WD to 2WD (sending D0261)
• 10.6.3 - 5WD to 2WD (sending D0011)
• 10.6.4 - ‘Within 5WDs of notification from MPAS or by last date of Electricity Supplier appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
• 10.6.5 – ‘Between 5WD and 10WD of 10.6.3.’ to ‘Within 1 WD of receiving all applicable D0011s.’ (sending D0148/D0302)
Switch with No Concurrent Change of MEM (Non Half Hourly)
• 10.7.4 – ‘Within 5WDs of notification from MPAS or by last date of Supplier Appointment.’ to “By Gaining Supplier Effective From Date” (sending D0151)
Footnote 55 – 5WD to 1WD
Footnote 59 – Typographical error - ‘exits’ to ‘exists’
Note: Full Legal text changes will be drafted as part of the REC Change Proposal, text changes to the REC Schedule have been proposed based on previously drafted changes to BSCP514.
-
Impacts
Electricity
Other (please provide details in Additional information box below)
Without changes, delays to Settlement could be seen when the new switching arrangements are introduced, which may also result in delays to consumer billing.
Schedule 14 - Metering Operations
Although the timelines for the sending of Market Messages are impacted by this Change, there is no direct impact to Market Messages or Data Items
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Energy Suppliers, Distribution Network Operators, Data Collectors
-
Balancing and Settlement Code (BSC)
This is a consequential REC change following the approval of BSC CP1532. The implementation of the REC and BSC Change Proposals are aligned.
No
No details provided
Priority & timing
No
-
The BSC SVG will be asked to consider the recommendation to move the implementation date for BSC CP1532 to 30 June 2022. The REC Change Proposal implementation date should be aligned with the BSC Implementation date.
-
No details provided
-