MHHS Incremental Changes for go live
Summary
This Issue looks to assess and confirm the scope to be taken forward into the Change Proposal that will deliver critical updates to the REC MHHS Code Drafting. Any potential scope items that have material impacts over and above the approved MHHS design will be considered as having unacceptable risk to the intended Change Proposal and will not be included in the confirmed scope.
Latest update and next planned activity
Date of latest update
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Impacts Overview
Impacted Consumers
Non-Domestic
Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Half Hourly Data Collector (C)
Non Half Hourly Data Collector (D)
Electricity Distribution Network Operator (R)
Data and Communications Company (DCC)
Electricity Meter Asset Provider (8)
Gas Meter Asset Provider (MAP)
Shipper (SHP)
Energy Supplier (ES)
Half Hourly Data Aggregator (A)
Non Half Hourly Data Aggregator (B)
Gas Transporter (GT)
Others
Impacted REC Documents
Schedule 15 - Metering Accreditation
Schedule 1 - Interpretations and Definitions
Schedule 14 - Metering Operations
Schedule 19 - Market Exit and Supplier of Last Resort
Schedule 27 - RMP Lifecycle
Schedule 28 - Related Metering Points
Schedule 29 - Address Management
Schedule 9 - Qualification and Maintenance
Schedule 24 - Switching Data Management
Schedule 23 - Registration Services
Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
Standards Definition Document
Data Item Catalogue
Market Message Catalogue
Impacted REC Services
Electricity Retail Data Service (ERDS)
Electricity Enquiry Service (EES)
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Distribution Connection and Use of System Agreement (DCUSA)
Solution development
Problem Statement
It is critical to the implementation of MHHS that design changes approved by the MHHS Programme are reflected in the REC MHHS Code Drafting. The REC MHHS Code Drafting was approved by the Authority, to meet MHHS Programme Milestone M7, through R0209 and incremental changes that were not included under that Change Proposal, now need to be taken through REC change governance as captured under the R0209 RAID, Risk R001 and Assumptions A005 and A006.
Solution documents
Documents Library
Change Plan
Change Proposal Plan approved
Completed
Start:
30 Jan 2025Due:
04 Mar 2025Completion:
04 Mar 2025Issue scope developed and presented at Change Issues Group meetings (06 March, 03 April, 01 May)
Completed
Start:
04 Mar 2025Due:
01 May 2025Completion:
01 May 2025Solution and legal drafting presented to Code Drafting Working Group
Completed
Start:
01 May 2025Due:
13 May 2025Completion:
13 May 2025Solution and legal drafting endorsed by Cross Code Advisory Group
Completed
Start:
13 May 2025Due:
28 May 2025Completion:
28 May 2025Ofgem direction received
Completed
Start:
28 May 2025Due:
04 Jun 2025Completion:
04 Jun 2025Consultation published
Completed
Start:
04 Jun 2025Due:
17 Jun 2025Completion:
17 Jun 2025Change Report (Consultation) approved at Change Panel
Completed
Start:
17 Jun 2025Due:
17 Jun 2025Completion:
17 Jun 2025REC Change Panel vote on Code Manager's recommendation
Completed
Start:
17 Jun 2025Due:
15 Jul 2025Completion:
15 Jul 2025Authority referral sent
Completed
Start:
15 Jul 2025Due:
17 Jul 2025Completion:
16 Jul 2025Authority decision published
In Progress
Start:
17 Jul 2025Due:
05 Sep 2025Completion:
Original submission
Change details
Harriet Truss - -
30 Jan 2025
Change details
MHHS Incremental Changes for go live
Since the MHHS Code Drafting was baselined by the MHHS Programme in August 2024, a number of MHHS Design changes have been identified and approved by the programme to support the robustness of the design for implementation. Amendments to REC consequential change solutions have also been identified. Both of these types of incremental change were expected, due to further understanding being gained through preparations for implementation, including Systems Integration Testing (SIT). Further Code amendments could still be identified during SIT. The end of SIT Cycle 3, in March 2025, is when the majority of testing will be completed and it is assumed most of the Design defects will have been identified.
The REC MHHS Code Drafting was approved by the Authority, to meet MHHS Programme Milestone M7, through R0209 and incremental changes that were not included under that Change Proposal, now need to be taken through REC change governance as captured under the R0209 RAID, Risk R001 and Assumptions A005 and A006.
This issue looks to assess and confirm the scope to be taken forward into the Change Proposal that will deliver critical updates to the REC MHHS Code Drafting. Any potential scope items that have material impacts over and above the approved MHHS design will be considered to add unacceptable risk to the intended Change Proposal and will not be included in the confirmed scope.
Potential scope items to be considered under this Issue will include:
• Approved Programme Change Requests (Programme CRs) and/or Design Issue Notifications (DINs) not previously included – this will be anything with a REC impact that has been included since Design Interim Release (IR) 8.1
• Amendments identified to REC Consequential Changes identified since M6 and required for M8/M10 implementation – Consequential Change will be defined under the same principles previously adopted by the Programme’s Code workstream – Includes amendments to EES identified through participant testing
• Correction of issues identified with the code drafting to ensure alignment with the MHHS design
• Issues shared with the REC MHHS project team, that require further consideration with stakeholders to understand their criticality and impact
A potential scope list has not been included in this submission, as a full list cannot be defined at the time of submission and will be treated as a live document during the Definition stage of the issue.
The intention of the Definition stage of this issue will also be to confirm appropriate next steps for any potential scope items that are not taken forward. Impact assessments will be progressed where required to help with the final scope determination.
The REC MHHS Code Drafting was approved by the Authority, to meet MHHS Programme Milestone M7, through R0209 and incremental changes that were not included under that Change Proposal, now need to be taken through REC change governance as captured under the R0209 RAID, Risk R001 and Assumptions A005 and A006.
This issue looks to assess and confirm the scope to be taken forward into the Change Proposal that will deliver critical updates to the REC MHHS Code Drafting. Any potential scope items that have material impacts over and above the approved MHHS design will be considered to add unacceptable risk to the intended Change Proposal and will not be included in the confirmed scope.
Potential scope items to be considered under this Issue will include:
• Approved Programme Change Requests (Programme CRs) and/or Design Issue Notifications (DINs) not previously included – this will be anything with a REC impact that has been included since Design Interim Release (IR) 8.1
• Amendments identified to REC Consequential Changes identified since M6 and required for M8/M10 implementation – Consequential Change will be defined under the same principles previously adopted by the Programme’s Code workstream – Includes amendments to EES identified through participant testing
• Correction of issues identified with the code drafting to ensure alignment with the MHHS design
• Issues shared with the REC MHHS project team, that require further consideration with stakeholders to understand their criticality and impact
A potential scope list has not been included in this submission, as a full list cannot be defined at the time of submission and will be treated as a live document during the Definition stage of the issue.
The intention of the Definition stage of this issue will also be to confirm appropriate next steps for any potential scope items that are not taken forward. Impact assessments will be progressed where required to help with the final scope determination.
It is critical to the implementation of MHHS that design changes approved by the MHHS Programme are reflected in the REC MHHS Code Drafting.
In addition, some consequential changes may also be determined to be critical for implementation at go-live.
In addition, some consequential changes may also be determined to be critical for implementation at go-live.
Critical updates to the REC MHHS Code Drafting are implemented at M8, to ensure the MHHS design is implemented in full at go-live, de-risking transition, qualification and migration.
-
Impacts
Domestic Credit, Domestic Prepayment, Electricity, Industrial and Commercial (I&C), Microbusiness, Small and Medium Enterprise (SME)
Ability to pay, Billing accuracy, Security of supply, Trust and confidence
-
Schedule 1 - Interpretations and Definitions, Schedule 9 - Qualification and Maintenance, Schedule 14 - Metering Operations, Schedule 15 - Metering Accreditation, Schedule 19 - Market Exit and Supplier of Last Resort, Schedule 23 - Registration Services, Schedule 24 - Switching Data Management, Schedule 27 - RMP Lifecycle, Schedule 28 - Related Metering Points, Schedule 29 - Address Management, Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
To be determined, but could impact any documentation impacted within R0209
Consolidated Metering Code of Practice (CoMCoP)
To be determined, but could impact any documentation impacted within R0209
No details provided
To be determined, but could impact any documentation impacted within R0209
Data Item Catalogue, Market Message Catalogue, Standards Definition
To be determined, but could impact any documentation impacted within R0209. There are however known impacts to the Data Item Catalogue and Market Message Catalogue
EES API Technical Specification
-
Central Switching Service (CSS), Electricity Retail Data Service
To be determined, but could impact any services impacted by R0209.
Data Aggregators, Data Collectors, DCC, Distribution Network Operators, Electricity Metering Operative, Energy Suppliers, EES Users, Meter Asset Providers, Meter Operator Agent, Shippers, Third-Party Intermediary, Virtual Lead Party
-
Balancing and Settlement Code (BSC), Distribution Connection and Use of System Agreement (DCUSA)
Equivalent changes will be progressed under the BSC and DCUSA, with timetables that aligns to the Change Proposal timelines set out below.
The DIP Manager are also considering changes that need to be progress for MHHS go-live.
The DIP Manager are also considering changes that need to be progress for MHHS go-live.
Yes
No details provided
Priority & timing
No
No, this issue has been planned to allow progression under a standard timetable
Development: The Issue and the resulting go live Change Proposal will need to align with programme plan timescales and with equivalent modifications/change proposals under other industry codes. If possible, an estimated timetable is being targeted as follows:
Definition: Jan-April
Change Proposal: May
Consultation: June
Voting: July
Please note that these timescales may need to change, for example if other Code Body plans to make changes for M8 or if Ofgem decides to use its SCR powers and directs an alternative timetable.
Implementation: Implementation of the changes confirmed as in scope of the Change Proposal will need to be implemented at M8
Definition: Jan-April
Change Proposal: May
Consultation: June
Voting: July
Please note that these timescales may need to change, for example if other Code Body plans to make changes for M8 or if Ofgem decides to use its SCR powers and directs an alternative timetable.
Implementation: Implementation of the changes confirmed as in scope of the Change Proposal will need to be implemented at M8
MHHS Programme implementation plan
No details provided
Ability to pay, Billing accuracy, Security of supply, Trust and confidence