A BSC CP has been raised to clarify Supplier obligations for IF-002 messages where a Switch is cancelled. This obligation is also in REC Schedule 14 Metering Operations, so a REC change is required or the obligation remains in place.
Latest update and next planned activity
Date of latest update
Latest Update
On 11 November 2026, the REC Metering Expert Panel voted, in line with the Code Manager’s recommendation, to approve this Change Proposal. The appeal window is now open until 25 November 2026. Subject to no appeal raised, R0339 will be implemented on 26 February 2027.
Impacts Overview
Impacted REC Parties and Market Participants
Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Other Industry Codes impacted
Balancing and Settlement Code (BSC)
Priority and rationale
Standard
Change Reports, Impact Assessments, Consultations and Documents
Change Reports
Solution development
Problem Statement
BSC CP1646 has been raised to address ambiguity around Supplier obligations following receipt of IF-002 messages for cancelled registration Switch Requests. The same obligation exists within the REC, so a REC change is needed to align with the clarifications introduced by BSC CP1646, ensuring consistent interpretation and behaviour across industry.
Solution documents
Workgroup
Has a Workgroup supported the development of the Change Proposal?
No
Documents Library
Change Plan
Proposal Plan approved by Change Panel
Completed
Start:
15 Sep 2026Due:
15 Sep 2026Completion:
15 Sep 2026Original submission
Change details
Caroline Freimuller - REC Code Manager / CCSG Representative
6 Aug 2026
Change details
REC Change to align with BSC CP Clarify Supplier obligations for IF-002 messages where a Switch is cancelled
A BSC CP has been raised to clarify Supplier obligations for IF-002 messages where a Switch is cancelled. This obligation is also in REC Schedule 14 Metering Operations, so a REC change is required or the obligation remains in place.
If the BSC CP progresses without the associated REC change, then Suppliers may not take the correct action as the obligations within the REC would remain unchanged.
The BSC CP specifies that where a IF-002 is received for a Switch request that has been cancelled, no actions are to be taken.
Similar clarifies are to be added to REC Schedule 14 Metering Operations 22.6.1 and 22.9.1
Similar clarifies are to be added to REC Schedule 14 Metering Operations 22.6.1 and 22.9.1
n/a
Impacts
Electricity
Other (please provide details in Additional information box below)
No Consumer impact identified
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Energy Suppliers
-
Balancing and Settlement Code (BSC)
BSC CP Clarify Supplier obligations for IF/PUB-002 messages where a registration switch is cancelled – BSC is the lead code
No
No details provided
Priority & timing
No
-
ASAP – BSC are aiming for November implementation, and would be ideal (but not required) for the changes to go live together.
n/a
No details provided
Other (please provide details in the Additional information box below)