Withdrawal of Service Termination Issue Reporting Guidance (STIRG) from REC Governance.
Summary
REC MEP have decided that the current governance for the STIRG is unsuitable for this type of document, and that it should be removed from the REC into ENA governance.
Latest update and next planned activity
Date of latest update
Latest Update
15/11/2024 - The Authority have published their decision, to reject this change proposal in line with the Code Manager and REC Change Panel recommendations. This decision can be found here: https://www.ofgem.gov.uk/decision/retail-energy-code-modification-r0170-rejected
Impacts Overview
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T)
Electricity Meter Operator (M)
Smart Meter Equipment Manager (S)
Gas Meter Asset Manager (MAM)
Electricity Distribution Network Operator (R)
Energy Supplier (ES)
Priority and rationale
Standard
Solution development
Problem Statement
The issues surrounding the status of the STIR Guidance document is impacting on the ability of involved parties to review and update the guidance.
Proposed solution summary
- As a Consumer, I want to be confident that any person working on the metering at my property has the adequate guidance under the appropriate governance to allow works to be conducted safely.
- As an electricity MEM or DNO, I need the STIR Guidance Document to sit under appropriate governance so I can be confident it is kept up to date for industry needs.
Solution documents
Documents Library
Change Plan
Party Impact Assessment opens
Completed
Start:
09 May 2024Due:
21 Jun 2024Completion:
20 Jun 2024Party Impact Assessment closes
Completed
Start:
21 Jun 2024Due:
12 Jul 2024Completion:
12 Jul 2024Preliminary Change Report published
Completed
Start:
12 Jul 2024Due:
26 Jul 2024Completion:
25 Jul 2024Change Panel review
Completed
Start:
26 Jul 2024Due:
06 Aug 2024Completion:
06 Aug 2024Consultation opens
Completed
Start:
06 Aug 2024Due:
09 Aug 2024Completion:
08 Aug 2024Consultation closes
Completed
Start:
09 Aug 2024Due:
02 Sep 2024Completion:
02 Sep 2024Final Change Report published
Completed
Start:
02 Sep 2024Due:
20 Sep 2024Completion:
05 Sep 2024Change Panel review
Completed
Start:
20 Sep 2024Due:
01 Oct 2024Completion:
17 Sep 2024Original submission
Change details
Paul Abreu - Energy Networks Association
9 May 2024
Change details
Withdrawal of Service Termination Issue Reporting Guidance (STIRG) from REC Governance.
REC MEP have decided that the current governance for the STIRG is unsuitable for this type of document.
The issues surrounding the status of the STIRG is impacting on the ability of involved parties to review and update the guidance as previously happened under MOCOPA.
REC MEP have determined that alternative governance arrangements outside of REC should be considered and that transferring the document to ENA should provide an acceptable solution for all affected REC Parties.
The REC Code Manager has previously produced R0145 as their proposal to change the STIRG document from a REC Category 3 document to a REC Category 2 document. This was consulted on and subsequently presented at REC MEP on 14 Feb 2024, where it was rejected on the basis that the proposal was not addressing the fundamental underlying issue, as raised by Network Parties during the consultation stage. REC MEP Members explored options for resolving the underlying issues and agreed that the option of withdrawing the document from REC governance to more suitable governance under ENA should be pursued via the development of an alternative new REC change proposal (this CP).
Impacts
Electricity, Domestic Prepayment, Domestic Credit, Microbusiness, Small and Medium Enterprise (SME), Industrial and Commercial (I&C)
Safety, Security of supply, On site experience
The development of this change proposal should include suitable additional REC legal text wording that requires Electricity Network Operators to consult with MEMs during any proposed updates of the STIRG document. The proposal should also explore possibilities for providing a route of appeal for MEM parties to follow should they be dissatisfied with any outcome of a proposal for review of the document.
The proposal should also include changes that make it clear that MEMs are also able to propose changes to the guidance and that any proposed changes are discussed at the E-OMF to seek views and suggested improvements.
The proposal should also include changes that make it clear that MEMs are also able to propose changes to the guidance and that any proposed changes are discussed at the E-OMF to seek views and suggested improvements.
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Energy Suppliers, Distribution Network Operators
-
Distribution Connection and Use of System Agreement (DCUSA)
-
No
No details provided
Priority & timing
No
-
Only that it should be progressed as soon as possible.
No
No details provided
-