The Switch Meter Reading Problems processes do not appropriately describe the use of rejections. This inhibits Parties from operating the process as intended and may cause unnecessary delay to the production of an accurate and agreed Switching Meter Reading. Additionally, the Performance Assurance Reporting Catalogue (PARC) is missing key data items to allow Performance Assurance to more accurately assure Party performance against Risk Drivers 5.6 and 5.8. Rejection reasons do not appear to be being reviewed, nor are they understood to be end statuses for the process.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.

Impacts Overview

Impacted REC Parties and Market Participants
Energy Supplier (ES)
Impacted REC Documents
Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
Priority and rationale
Standard

Solution development

Problem Statement
Suppliers may interact with the Missing Switch Read process in a way that is operationally standard for them, but not reflected in the Code. This means that the D0300 or SAR may either be escalated unnecessarily (including Performance Assurance checks), or may not be responded to, whilst still resolving the overall issue.
Solution documents
I0215 Schedule 30 v0.1 05 Jun 2026 PDF - 93.01 KB
05 Jun 2026
05 Jun 2026
05 Jun 2026

There is currently no Change Plan.

Original submission

Change details

Carl Dennis - Code Manager
25 Sep 2024

Change details

Schedule 30 Switch Meter Reading Problems - Rejections and Timings
Incomplete Switch Meter Reading Problems process in Schedule 30, Section C. Also, missing/weak/unclear definitions of working days/hours for reporting purposes.
The Switch Meter Reading Problems processes do not appropriately describe the use of rejections. This inhibits Parties from operating the process as intended and may cause unnecessary delay to the production of an accurate and agreed Switching Meter Reading.

Additionally, the Performance Assurance Reporting Catalogue (PARC) is missing key data items to allow Performance Assurance to more accurately assure Party performance against Risk Drivers 5.6 and 5.8.

Rejection reasons do not appear to be being reviewed, nor are they understood to be end statuses for the process.
Schedule 30 needs to better describe the Switch Meter Reading Problems process for Parties to understand their obligations and for Performance Assurance to more accurately monitor the performance of Parties in line with their obligations.

Rejections should be viewed as end statuses, with no escalation required if the rejection reason code has been used correctly.

Below details areas already discussed at RIG. This is not an exhaustive list and should not limit the discussions of this Issue. For example, not discussed at RIG was the impact of MHHS on this process and the codes within the D0300. Additionally, the examples below are all electricity but the Issue should review gas as well. The RIG discusses are as follows:

Potential text to add to Schedule 30:

During the Missing Switch Meter Reading process, before or after sending the initial MM00231 - D0300 (SV00233), either Supplier may send or receive a MM00257 - D0010 (SV00385) or receive a MM00004 - D0086 (SV00006) Market Message from their NHHDC.

Receipt of this will stop the Missing Switch Meter Reading process. The recipient of the initial D0300 should therefore reject the latest D0300 Market Message using “Record Rejection Reason Indicator” (J1663) code 19 (Switch Meter Reading has already been issued).

If after receipt of the MM00257 - D0010 (SV00385) or MM00004 - D0086 (SV00006) either Supplier or Consumer does not agree that the reading is valid then the Disputed Switch Meter Reading process may be initiated as described in this Schedule.

Proposed housekeeping change to J1663 code 19

(J1663) code 19 (Switch Meter Reading has already been issued).

Additional data items to be included in PARC:

MM00004 - D0086 (SV00006)
MM00257 - D0010 (SV00385)

Rejections

Rejection reasons in the D0300 are primarily technical rejections, meaning that the initial request has been sent incorrectly/with missing data/to the wrong Party, or that a suitable Change of Supply Meter Read is already available. They should be reviewed and compared against the initial MM00231 - D0300 (SV00233) Market Message, as well as against messages MM00004 - D0086 (SV00006) and MM00257 - D0010 (SV00385) to establish their validity, and the validity of the original request.

Potential text to add to Schedule 30:

Suppliers must not use the Escalation of Delayed and Disputed Resolutions process if the rejection has been sent correctly, as it is a valid response and an end status to the process. The Switch Meter Reading Problems process may be restarted if there is still a requirement for the process and the rejection reason has been resolved.

Response reporting timing

It has been identified that there may be a small gap between RPA and Party reporting relating to the sending of responses to process initiations.

It appears that currently RPA measure responses from the timestamp on the process initiation Market Message, and Parties will measure responses working day to working day.

This needs to be discussed further to establish if a change to the PARC or Schedule 30 is required.

The examples above are all electricity focused, however the gas equivalent should also be reviewed and potentially amended.
Parties are failing against Risk Driver 5.8, leading to RPA and Party resources being utilised where they may not be needed. This was discussed at RIG on 08/03/2024 and 14/06/2024 which confirmed as an issue impacting multiple parties.

Impacts

Electricity, Gas, Domestic Prepayment, Domestic Credit, Microbusiness, Small and Medium Enterprise (SME), Industrial and Commercial (I&C)
Switching experience, Billing accuracy, Trust and confidence
-
Schedule 1 - Interpretations and Definitions, Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
Performance Assurance Report Catalogue
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Secure Data Exchange Service
-
Energy Suppliers
-
Balancing and Settlement Code (BSC), Uniform Network Code (UNC), Independent Gas Transporters (IGT) Uniform Network Code (UNC)
Due to the knock-on impact to settlements there is potential for impacts to BSC, UNC and iGT UNC
-
No details provided

Priority & timing

No
-
-
-
No details provided
-

Activity

Status has been changed to Implemented.
Implementation Date has been updated to 07 Nov 2025.