Updates to Schedule 14 Measurement Transformers Commissioning Timescales

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 0 of 6
Approved - In Appeal Window
Summary
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.

Latest update and next planned activity

Date of latest update
Latest Update
12/08/2026 - the Metering Expert Panel approved the Change Report (Final Recommendation) V1.2. This Change Proposal will be implemented on 26 June 2027. If you wish to appeal this decision, this must be received by COB 28 August 2026.

Impacts Overview

Impacted Consumers
Others
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Distribution Network Operator (R) Energy Supplier (ES)
Impacted REC Documents
Schedule 14 - Metering Operations
Priority and rationale
Standard

Change Reports, Impact Assessments, Consultations and Documents

Solution development

Problem Statement
The current timetables in REC Schedule 14 Metering Operations sections 15.6 and 30.6, where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO, or in 15.7 and 30.7 where the Measurement Transformers are not owned by the DNO, may no longer be fit for purpose post the implementation of MHHS Milestone M16, where the Settlement timetable reduces the RF run to 4 months.
Solution documents
02 Nov 2026
02 Nov 2026
02 Nov 2026
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

03 Feb 2026

Presented at Change Issues Group

Completed

Start:

Due:

Completion:

05 Feb 2026

Change Report (For Consultation) approved by Metering Expert Panel

Completed

Start:

Due:

Completion:

08 Apr 2026

Original submission

Change details

Caroline Freimuller - REC Code Manager
1 Oct 2025

Change details

Updates to Schedule 14 Measurement Transformers Commissioning Timescales
The current timescales in Schedule 14 section 15.6 and section 30.6 where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 need to be reviewed before the settlement timetable changes from RF being 14 to 4 months to ensure they are still fit for purpose.
REC Schedule 14 Metering Operations sets out in section 15.6 and section 30.6 the process that shall be followed where an Electricity Metering Asset requires commissioning in accordance with BSC Metering CoP 4 and the Measurement Transformers are owned by the DNO. The timescales for this are currently:
• DNO commissions the Measurement Transformers within 16WDs of energisation (or receipt of D0139)
• DNO sends D0383 Notification of Commissioning Information with 21WDs of energisation
• MOA commissions Metering Asset within 32WDs of energisation
• Electricity Supplier resolves any defects/omissions preventing commissioning within 65WDs of energisation
• After resolution, MOA commissions Metering Asset within 80WDs of energisation
• MOA notifies Electricity Supplier commissioning has been completed within 5WDs of completion

In total, this process could take up to 85WDs. Under the new settlement timetable being introduced at MHHS milestone M16 (currently planned for July 2027), RF will be changing to 4 months which is very close to this 85WD window.
Review these timescales to ensure they are still fit for purpose or need to be shortened to be more in line with the new RF window being introduced by MHHS.
n/a

Impacts

Electricity
Billing accuracy
-
Schedule 14 - Metering Operations
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
Distribution Network Operators, Electricity Metering Operative, Energy Suppliers, Meter Operator Agent
-
Balancing and Settlement Code (BSC)
Potential to impact the BSC, to be confirmed at CCSG
No
No details provided

Priority & timing

No
-
Change should be implemented no later than the June 2027 release, to be ready for M16 (currently planned for July 2027)
n/a
No details provided
Billing accuracy

Activity

Change Category has been updated to Category 1.
Change Path has been updated to Self-Governance.
Status has been changed to Approved - In Appeal Window.
Implementation Date has been updated to 25 Jun 2027.
Change Report - Draft Change Report has been updated to Test (3).txt.
Change Report - Initial Assessment and Change Plan Report has been updated to Comments deadline for Test (4).txt - 2026-01-31.
Status has been changed to Issue Review.