SFIC to CMRM - missing Scenario Variant in D0126 / MM00016

  • 1
    Initial Assessment
  • 2
    Solution Development
  • 3
    Consultation
  • 4
    Decision
  • 5
    Awaiting Implementation
  • 6
    Implemented
Step 6 of 6
Implemented
Summary
It has been raised to the Code Manager by a Party that the Scenario Variant of Supply Fault Information Centre (SFIC) to Crowded Meter Room MEM (CMRM) is missing from the D0126 / MM00016 (Asset Condition Report Response / Clearance) Market Message. This should have been introduced as part of REC Change R0043 which introduced the role of the CMRM.

Latest update and next planned activity

Date of latest update
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.

Impacts Overview

Impacted Consumers
Non-Domestic Domestic
Impacted REC Parties and Market Participants
Advanced Meter Equipment Manager (T) Electricity Meter Operator (M) Smart Meter Equipment Manager (S) Electricity Distribution Network Operator (R) Other (Other)
Impacted REC Documents
Market Message Catalogue
Priority and rationale
Standard

Solution development

Problem Statement
CMRMs can send the D0135 / MM00023 Asset Condition Report Market Message to the SFIC, but the SFIC cannot send a response on the D0126 / MM00016 Asset Condition Report Response / Clearance Market Message to confirm the outcome of their investigation.
Solution documents
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

16 Sep 2025

Original submission

Change details

Caroline Freimuller - REC Code Manager
19 Aug 2025

Change details

SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
It has been raised to the Code Manager by a Party that the Scenario Variant of Supply Fault Information Centre to Crowded Meter Room MEM is missing from the D0126 / MM00016 (Asset Condition Report Response / Clearance) Market Message. This should be been introduced as part of REC Change R0043 which introduced the role of the CMRM.
The CMRM is required to send the D0135 (Asset Condition Report) to the SFIC, but cannot receive the D0126 back to inform them of actions taken.
Add the SFIC to CMRM Scenario Variant to the D0126.
REC Change R0043

Impacts

Electricity
Safety
-
No details provided
-
No details provided
-
No details provided
-
Market Message Catalogue
-
No details provided
-
No details provided
-
No details provided
-
No details provided
-
No
No details provided

Priority & timing

No
-
-
-
No details provided
Safety

Activity

Status has been changed to Implemented.
Implementation Date has been updated to 26 Jun 2026.