CoMCoP 2-year Audit Cycles

Date of latest update
Type
Change
ID
R0311
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
Renewal audits under the Consolidated Metering Code of Practice (CoMCoP) are consistently delivered on a 2 year cycle and include both a desktop audit and a site audit. However, Schedule 15 currently does not explicitly define this.
Proposer
David Haddock
Change Report - Initial Assessment and Change Plan Report
Change report - Final Change Report
Impacted REC Documents
Status
Implementation Date
Status Superseded
EMAR Version 4.3.0
Included changes Affected REC Items
R0267 Smart Meter Installation Surveys - Microbusiness requirements
  • Smart Meter Installation Schedule (since removed)
R0276 SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
  • Market Message Catalogue
R0286 Clarification on Detailed Impact Assessment Activities
  • Schedule 5 - Change Management
R0291 Review of Schedule 1 Interpretations and Definitions
  • Schedule 1 - Interpretations and Definitions
R0299 Data Latency Targets for the GES Service Definition
R0300 Amendments to D0312 to align with BSC CP1622
  • Data Item Catalogue
R0307 Release and Licensing of the CoMCoP Logo for Accredited Parties
R0308 Update CCSG ToRs to include cross-code prioritisation as per Code Reform
R0310 Addition of value 11 to data item J0418
  • Data Item Catalogue
R0311 CoMCoP 2-year Audit Cycles
  • Schedule 15 - Metering Accreditation
R0316 Clarification of Data Items within the Payment Method Levelisation Supplier Data Reporting Specification
R0319 Clarification of in-year amendments to the CRS budget
R0320 Housekeeping June 2026
  • Schedule 1 - Interpretations and Definitions
  • Schedule 11 - Prepayment Arrangements
  • Schedule 7 - Energy Theft Reduction
  • Schedule 17 - Secure Data Exchange
  • Schedule 12 - Data Access
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. An update to the REC Schedule 15 - Metering Accreditation
Proposed Solution Document
Document title
R0311_Draft legal text (For Final Recommendation)
Upload document
R0311_Draft legal text (4).docx
Archive
Off
Problem Statement
The current lack of explicit wording in the Metering Accreditation Schedule of both a desktop and site audits that need to be completed one year after the initial accreditation, and then every two years for renewals introduces ambiguity for future audit delivery undertaken under CoMCoP as it creates a gap between operational practice and the codified baseline. This could potentially lead to inconsistent approaches by Parties, which in turn could reduce the consistency, predictability, and effectiveness of the industry’s audit and assurance framework.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0311 submission form
Draft legal text (On submission)
R0311 Draft legal text (For Consultation)
R0311_Change Report (Final Recommendation)_v1.1 (13 May 2026)
Company Name
Wilcock Consultants Ltd (WCL)
Review status
Review required

Implementation of Ofgem-led code modification prioritisation within the REC

Date of latest update
Type
Change
ID
R0304
Change Category
Change Path
Urgent
No
Latest Update
This Change Proposal was implemented on 29 May 2026.
Summary
Ofgem has consulted on, and is progressing towards a decision on, the introduction of a harmonised code modification prioritisation framework across all industry codes, under its transitional powers in Schedule 12 to the Energy Act 2023. This Issue is being raised to provide the formal REC change vehicle through which Ofgem’s prioritisation reforms can be tracked, developed and implemented in the REC, once the Authority has published its decision and statutory modification notice.
Proposer
Ann Perry
Change report - Final Change Report

Comments deadline
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Problem Statement
In the absence of REC changes, the REC would not align with Ofgem’s harmonised approach to code modification prioritisation, creating inconsistency with other industry codes and undermining the objectives of Energy code reform.
I0304 submission form
I0304 Change Report (Proposal Plan) V1.0
New Priority Status
Company Name
RECCo
Review status
Review required

Updates to Enquiry Service API endpoints to support migration to RECCo’s API Gateway

Date of latest update
Type
Issue
ID
I0301
Change Path
Urgent
No
Latest Update
06/11/2026 - Following further analysis, it was determined that I0301 is no longer required. While the Issue was originally raised to support a dual-fuel approach to RECCo’s Enquiry Service evolution, the initial focus on GES means that no changes to the REC are currently required to update the relevant API endpoints.
Summary
As part of RECCo’s plan to procure a dual-fuel Enquiry Service, there will be a single point of entry to API services. A migration plan has been developed with two independent stages. For stage one, all current Enquiry Service API users will need to connect through RECCo’s API Gateway rather than connecting directly to the existing EES and GES APIs. This will require users to amend the URLs they call when accessing the services.
Proposer
Elise Handy
Status
Implementation Status
Date Raised
Fuel
Solution Development
I0301 submission form
Company Name
REC Code Manager
Review status
Review required

Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations (Alternate)

Date of latest update
Type
Change
ID
R0287A
Change Category
Priority
Urgent
No
Latest Update
20/02/2026 The Authority has published their decision to reject R0287A and approve the R0287, in line with the Code Manager and the Change Panel's recommendation. The Authority's decision has been published below.
Summary
Inconsistent interpretations of the Annulment definition in Schedule 23 are leading to disputes between suppliers. We are, therefore, seeking to further clarify the use of annulments to ensure that the customer is placed firmly at the heart of this process.
Proposer
Komal Brown
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

02 Dec 2025
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0287A Draft Legal Changes - For Consultation
Upload document
I0287A (Alternate) Proposed Solution For Consultation.docx
Archive
Off
Problem Statement
The current wording of the Annulment definition in the REC Schedule 23 – Registration Services is insufficiently aligned with the obligations set out in Ofgem’s Electricity Supply Standard Licence Conditions (SLC). This has led to inconsistent interpretations of the usage of the Annulment process.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0287A submission form
R0287 and R0287A Change Report (Proposal Plan and Consultation) v1.0 approved 02.12.25
R0287 and R0287A Consolidated Consultation Responses PUBLIC
R0287 and R0287A Change Report (Final Recommendation) Post Vote 20.01.2026 v1.0
Ofgem decision to reject R0287A
Company Name
ScottishPower
Review status
Review required

Housekeeping February 2026

Date of latest update
Type
Change
ID
R0293
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The Code Manager has identified a number of non-material clarifications, typographical errors and changes needed to REC products.
Proposer
Caroline Freimuller
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
This Housekeeping Change Proposal seeks to make typographical and formatting corrections that have been identified and improve consistency across the REC.
February 2026 Housekeeping Summary spreadsheet V1.0
February 2026 Housekeeping legal text (zip file) V1.0
R0293 Housekeeping Change Report v1.0 approved 16.12.25
Company Name
REC Code Manager
Review status
Review required

Obligate Energy Suppliers to provide photo evidence of Theft in Conveyance to Network Parties

Date of latest update
Type
Change
ID
R0292
Change Category
Change Path
Priority
Urgent
No
Latest Update
17/11/2026 - the Change Panel voted to approve this Change Proposal for implementation on 26 February 2027. If you wish to raise an appeal against this decision, it must be received by COB 01 December 2026.
Summary
This Issue seeks to introduce an additional clause for Suppliers that have attended Sites with suspected or actual Energy Theft in Conveyance to share and store evidence of the tampering to be made available to Network Parties upon request.
Proposer
Danielle Gibson
Change report - Final Change Report
Change Plan

Presented at Change Issues Group

Completed

Start:

06 Aug 2026

Due:

06 Aug 2026

Completion:

06 Aug 2026

Update to Plan approved by Change Panel

Completed

Start:

21 Jul 2026

Due:

21 Jul 2026

Completion:

21 Jul 2026

Change Report (For Consultation) approved by Change Panel

Completed

Start:

18 Aug 2026

Due:

18 Aug 2026

Completion:

18 Aug 2026
Status
Implementation Date
Status Scheduled
EMAR Version 4.5.0_Scheduled
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0292 Schedule 8 draft V0.1
Upload document
I0292 Scheudle 8 draft V0.1 - R0253 baseline.docx
Archive
Off
Document title
I0292 Schedule 8 draft V0.2
Upload document
I0292 Scheudle 8 draft V0.2 - R0253 baseline - for consultation.docx
Archive
Off
Problem Statement
There are cases where Energy Suppliers (or its Revenue Protection Agent) have provided the Network Parties with minimal information and no photos following Site visits for Theft in Conveyance, which results in additional time for Energy Theft Desktop Investigations and additional costs where jobs are raised for attendance that aren’t always needed.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0292 submission form
I0292 Change Report (Proposal Plan) V1.0
I0292 Consolidated Information Request Responses V1.0
I0292 Update to Plan V1.0 approved 21.07.26
I0292 Consolidated Impact Assessment Responses PUBLIC v1.0
R0292 Change Report (For Consultation) V1.0 approved 18.08.26
R0292 Consolidated Consultation Responses v1.0
Company Name
SSEN
Review status
Review required

Review of Schedule 1 Interpretations and Definitions

Date of latest update
Type
Change
ID
R0291
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
During the quality checks of REC Schedules for MHHS, several capitalised terms throughout schedules were identified with no entry in Schedule 1. It has also been identified that there are definitions that link to Schedules (such as 2, 20 and 21) which are no longer live REC Schedules. The Code Manager has reviewed these and determined some changes are required to Schedule 1.
Proposer
Caroline Freimuller
Change Plan

Change Report (Proposal Plan) approved by Change Panel

Completed

Start:

Due:

Completion:

17 Feb 2026

Approved at Change Panel for implementation in June 2026

Completed

Start:

Due:

Completion:

21 Apr 2026
Status
Status
Implementation Date
Status Superseded
EMAR Version 4.3.0
Included changes Affected REC Items
R0267 Smart Meter Installation Surveys - Microbusiness requirements
  • Smart Meter Installation Schedule (since removed)
R0276 SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
  • Market Message Catalogue
R0286 Clarification on Detailed Impact Assessment Activities
  • Schedule 5 - Change Management
R0291 Review of Schedule 1 Interpretations and Definitions
  • Schedule 1 - Interpretations and Definitions
R0299 Data Latency Targets for the GES Service Definition
R0300 Amendments to D0312 to align with BSC CP1622
  • Data Item Catalogue
R0307 Release and Licensing of the CoMCoP Logo for Accredited Parties
R0308 Update CCSG ToRs to include cross-code prioritisation as per Code Reform
R0310 Addition of value 11 to data item J0418
  • Data Item Catalogue
R0311 CoMCoP 2-year Audit Cycles
  • Schedule 15 - Metering Accreditation
R0316 Clarification of Data Items within the Payment Method Levelisation Supplier Data Reporting Specification
R0319 Clarification of in-year amendments to the CRS budget
R0320 Housekeeping June 2026
  • Schedule 1 - Interpretations and Definitions
  • Schedule 11 - Prepayment Arrangements
  • Schedule 7 - Energy Theft Reduction
  • Schedule 17 - Secure Data Exchange
  • Schedule 12 - Data Access
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0291 REC Main Body draft V0.1
Upload document
R0291 REC Main Body draft V0.1.docx
Archive
Off
Document title
R0291 Schedule 1 draft V0.1
Upload document
R0291 Schedule 1 draft V0.1 (1).docx
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Upload document
R0291 Schedule 25 (CSS) draft V0.1.docx
Archive
Off
Document title
R0291 Schedule 1 draft V0.2
Upload document
R0291 Schedule 1 draft V0.2.docx
Archive
Off
Document title
R0291 REC Main Body draft V0.1
Upload document
R0291 REC Main Body draft V0.1 (1).docx
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Upload document
R0291 Schedule 25 (CSS) draft V0.1 (1).docx
Archive
Off
Problem Statement
Without clear definitions of all defined terms within the REC, there may be confusion for REC Parties and other industry participants who use REC documents.
I0291 submission form
I0291 Change Report (Proposal Plan) V1.0
R0291 Change Report (For Consultation) V1.0
R0291 Consolidated Consultation Responses v1.0
R0291 Change Report (Final Recommendation) V1.1 approved 21.04.26
Company Name
REC Code Manager
Review status
Review required

Rationalisation of reports produced by CSS - CRS improvements project

Date of latest update
Type
Issue
ID
I0289
Change Path
Urgent
No
Latest Update
15/01/2026 The Code Manager has rejected this Change Proposal as it does not impact any REC products. Further feedback, and any information on the CRS Improvements project as a whole, can be provided via the usual channels, including the Switching Operator Forum, your OAM teams and the Change Management team.
Summary
Ensuring the reports generated from CSS (Into ServiceNow) are being utilised and where they are not utilised reducing cadence or potentially removing completely.
Proposer
Leo Brown
Status
Implementation Status
Date Raised
Fuel
Solution Development
Proposed Solution Document
Document title
I0289 submission form
Upload document
I0289 submission form.pdf
Archive
Off
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Issue Proposal Form
I0289 Information Request Consolidated Responses
Company Name
DCC
Review status
Review required

Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations

Date of latest update
Type
Change
ID
R0287
Change Category
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The current wording of the Annulment definition in REC Schedule 23 – Registration Services does not sufficiently align with the obligations set out in Ofgem’s Electricity Supply Standard Licence Conditions (SLC) 14.2(d),14.4(c) and 14.10. This misalignment has led to inconsistent interpretations of the usage of the Annulment process across the industry compared to the intention of the REC change and the licence obligation. This Issue is seeking further amendments to REC Schedule 23 - Registration Services and clearer guidance. This clarification is essential to prevent retention-based misuse, ensure regulatory compliance, and uphold Consumer trust in the Switching process.
Proposer
Ben Atkinson
Change Plan

Proposal Plan approved at Change Panel

Completed

Start:

Due:

Completion:

02 Dec 2025

Final Recommendation approved at Change Panel

Completed

Start:

Due:

Completion:

20 Jan 2026
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Status
Implementation Date
Status Superseded
EMAR Version 4.2.0_Superseded
Included changes Affected REC Items
R0179 Proposal for Limiting Queries in EES API Calls (Single Query per API Call)
R0190 Related Meter Point RMP status rules
  • Schedule 28 - Related Metering Points
R0198 Metering Asset Manager (MAM) Communication Method Register
R0242 Missing Scenario Variant from R0043
  • Market Message Catalogue
R0244 C21 to be introduced into STIRG Document
  • Data Item Catalogue
R0235A Missing Scenario Variants in D0179 Alternate Solution
R0256 MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101
  • Market Message Catalogue
R0270 Clarification of SIP Qualification Requirements
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 15 - Metering Accreditation
R0271 Clarification of ASP, AMI, and EMO Accession Requirements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
R0272 Enabling transparency of the CRS Provider’s REC service level performance
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 26 - Switching Service Management
  • Schedule 24 - Switching Data Management
R0277 Data Latency SLA Alignment for Gas Enquiry Service
  • Schedule 1 - Interpretations and Definitions
R0280 CSS Certificate Authority audit clarification
  • Schedule 1 - Interpretations and Definitions
R0283 Annual Address Management Plan Updates
  • Schedule 1 - Interpretations and Definitions
  • Schedule 6 - Performance Assurance
  • Schedule 29 - Address Management
R0287 Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 23 - Registration Services
R0293 Housekeeping February 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0287 Draft Legal Changes - For Consultation
Upload document
I0287 Draft Legal Changes - For Consultation.docx
Archive
Off
Problem Statement
The current wording of the Annulment definition in the REC Schedule 23 – Registration Services is insufficiently aligned with the obligations set out in Ofgem’s Electricity Supply Standard Licence Conditions (SLC). This has led to inconsistent interpretations of the usage of the Annulment process.
SME
SME Role
Lead Technical Analyst
SME User
vaishnsharma@deloitte.co.uk
SME Role
Lead Assurance Analyst
I0287 submission form
R0287 and R0287A Change Report (Proposal Plan and Consultation) v1.0 approved 02.12.25
R0287 and R0287A Consolidated Consultation Responses PUBLIC
R0287 and R0287A Change Report (Final Recommendation) Post Vote 20.01.2026 v1.0
Ofgem decision to approve R0287
Company Name
Centrica
Review status
Review required

Clarification on Detailed Impact Assessment Activities

Date of latest update
Type
Change
ID
R0286
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
The first complex technical change R0067 (Introduction of CSS Refresh Functionality) encountered a number of challenges within the design and implementation process, the change was scheduled for implementation on the 6th December 2023, however, the change was deployed with defects and was not fully operational until February 2024. Following that session, the Code Manager held discussions, and a formal Lessons Learned session with all Service Providers and identified a number of challenges with the technical change process. Some of these challenges can be attributed to the timing of the detailed design, Detailed Impact Assessments (DIA) and party impact assessments
Proposer
April Harbour
Change Report - Initial Assessment and Change Plan Report
Change report - Final Change Report
Impacted Consumers
Impacted REC Documents
Status
Status
Implementation Date
Status Superseded
EMAR Version 4.3.0
Included changes Affected REC Items
R0267 Smart Meter Installation Surveys - Microbusiness requirements
  • Smart Meter Installation Schedule (since removed)
R0276 SFIC to CMRM - missing Scenario Variant in D0126 / MM00016
  • Market Message Catalogue
R0286 Clarification on Detailed Impact Assessment Activities
  • Schedule 5 - Change Management
R0291 Review of Schedule 1 Interpretations and Definitions
  • Schedule 1 - Interpretations and Definitions
R0299 Data Latency Targets for the GES Service Definition
R0300 Amendments to D0312 to align with BSC CP1622
  • Data Item Catalogue
R0307 Release and Licensing of the CoMCoP Logo for Accredited Parties
R0308 Update CCSG ToRs to include cross-code prioritisation as per Code Reform
R0310 Addition of value 11 to data item J0418
  • Data Item Catalogue
R0311 CoMCoP 2-year Audit Cycles
  • Schedule 15 - Metering Accreditation
R0316 Clarification of Data Items within the Payment Method Levelisation Supplier Data Reporting Specification
R0319 Clarification of in-year amendments to the CRS budget
R0320 Housekeeping June 2026
  • Schedule 1 - Interpretations and Definitions
  • Schedule 11 - Prepayment Arrangements
  • Schedule 7 - Energy Theft Reduction
  • Schedule 17 - Secure Data Exchange
  • Schedule 12 - Data Access
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. An update to the REC Schedule 5 - Change Management.
Proposed Solution Document
Document title
R0286 Proposed legal text v1.1
Upload document
R0286_Draft legal text_v1.1.docx
Archive
Off
Problem Statement
The technical change process currently creates five challenges which can be attributed to the timing of the detailed design, PIA and DIAs. These are as follows: Lack of Clarity, Limited Feedback, Misalignment, High Contingency Costs and Inaccurate Timelines.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Change Management v3.5 RedLine for IA Clarifications
I0286 submission form
R0286_Consolidated Consultation responses V1.0
Company Name
REC Technical Services
Review status
Review required