Add Enumeration Values to the DI51035 - Communications Provider Data Item

Date of latest update
Type
Change
ID
R0193
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
As the valid list of Communications Providers is being removed from MDD, Elexon have raised a change to propose this list is added to the DI51035 - Communications Provider Data Item.
Proposer
Colin Berry
Impacted REC Documents
Status
Implementation Date
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0193 Solution Document v1.0
Upload document
I0193 Solution Document v1.0.pdf
Archive
Off
Problem Statement
For the industry to maintain an ongoing list of valid Communications Providers after it is removed from MDD, Enumeration Values will be added to the Communication Provider Data Item (DI51035).
SME
SME Role
Lead Assurance Analyst
I0193 - Add Enumeration Values to the DI51035 - Communications Provider Data Item
I0193 Change Report (Proposal Plan) V2.0 (Approved) 17.09.2024
I0193 Consolidated Impact Assessment Responses PUBLIC V1.0
R0193 Change Report (For Consultation) V1.0
R0193 Consolidated Consultation Responses v1.0
R0193 Change Report (Final Recommendation) Post Approval V1.0
Company Name
BSCCo
Review status
Review required

Housekeeping Amendments

Date of latest update
Type
Change
ID
R0192
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/08/24 - Change Proposal approved for implementation on 06 September 2024.
Summary
The Code Manager has identified a number of typographical and formatting errors, as well as opportunities to provide clarity, improve consistency and accuracy across the REC Services and products. These changes have been assessed as meeting the criteria to be progressed via a Housekeeping Change Proposal.
Proposer
Holly Law
Change report - Final Change Report
Change Plan

Housekeeping Report Published

Completed

Start:

25 Jul 2024

Due:

26 Jul 2024

Completion:

26 Jul 2024

Responsible Committee Decision

Completed

Start:

26 Jul 2024

Due:

06 Aug 2024

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.13.0_Superseded

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
API GES Supply Point Switching Technical Specification v1.1
Upload document
API GES Supply Point Switching Technical Specification v1.1.docx
Archive
Off
Document title
Housekeeping legal text changes
Upload document
Sept Housekeeping Log.xlsx
Archive
Off
Problem Statement
This is a Housekeeping Change Proposal subject to the Housekeeping Change Proposal process, rather than the standard change process. The nature of the change is that it makes non-material changes to the REC Products to correct typographical and consistency errors. It also provides an opportunity to introduce necessary clarifications.
Company Name
-
Review status
Review required

Levelisation Reconciliation Electricity Single-rate/Multi-register Split

Date of latest update
Type
Change
ID
R0182
Change Category
Priority
Urgent
Yes
Latest Update
18/11/24 - The Authority has approved R0182 for Implementation. R0182 will now be targeted for an extraordinary release on 08/12/24.
Summary
This Change Proposal seeks to introduce the necessary governance and charging amendments to existing Payment Method Levelisation (PML) Reconciliation arrangements (introduced in R0147) to allow for multi-register reconciliation. The amendments will allow for an ongoing reconciliation that accounts for split in both single-rate and multi-register Metering Assets. Additionally, it will also allow for a one-off retrospective recalculation for the period dating from the proposed effective implementation date of 01 January 2025 back to the implementation of the original reconciliation mechanism on 01 April 2024.
Proposer
Chris Stock
Change Plan

Party Impact Assessment

Completed

Start:

20 Jun 2024

Due:

09 Aug 2024

Completion:

09 Aug 2024

Consultation

Completed

Start:

09 Aug 2024

Due:

20 Sep 2024

Completion:

20 Sep 2024

Responsible Committee Decision

Completed

Start:

20 Sep 2024

Due:

15 Oct 2024

Completion:

15 Oct 2024

Authority Determination Sent

Completed

Start:

15 Oct 2024

Due:

16 Oct 2024

Completion:

16 Oct 2024
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. N/A – No identifiable Consumer impact.
  2. M1 - As a Domestic Supplier, I want my PML Reconciliation payments to be as reflective of my portfolio as possible, by differentiating between single rate and multi register Metering Assets, so that my engagement with the reconciliation is as accurate as possible. M2 - As a Domestic Supplier, I want my PML Reconciliation obligations regarding the retrospective recalculation to be well defined within the REC, so that I am able to engage as efficiently as possible. M3 - As RECCo, I want the PML Reconciliation mechanism to be reflective of REC Parties true costs (based on their single-rate vs multi-register split in their portfolio), so that I am able to deliver the most optimised outcome for PML Reconciliation participants.
Proposed Solution Document
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14.zip
Archive
Off
Document title
R0182 Solution & Legal Text 08.10.24
Upload document
R0182 Solution and legal text 08.10.14 (1).zip
Archive
Off
Problem Statement
PML Reconciliation currently does not distinguish between single-rate and multi-register electricity Metering Assets. This represents a discrepancy, as Price Cap methodology currently does make this distinction. As a result, PML Reconciliation calculation methodology must be updated to distinguish between single-rate and multi-register Metering Assets. This will be effective for all reconciliations going forward from the date of implementation, as well as retrospectively from the start of the PML Reconciliation in April 2024, to the date of implementation.
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0182 - CP Form
Consolidated Consultation Responses
Ofgem Letter on Upcoming PPM Levelisation Single and Multi-Metering Arrangements RFI
R0182 Change Proposal Plan (Approved) V1.0 16.07.24
R0182 Initial Assessment Report V1.0 (Approved) 16.07.24
R0182 Consolidated Impact Assessment Responses V1.0 30.08.24
R0182 Change Report (Post-Vote) V3.0 15.10.24
Authority Decision on REC Modification Proposal R0182
Company Name
RECCo
Review status
Review required

Schedule 14 - Metering Operations Footnote Review

Date of latest update
Type
Change
ID
R0181
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
The footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant. This Change Proposal looks to correct issues within the footnotes and move them into the legal text to prevent this from happening when future Change Proposals impacting this schedule are implemented.
Proposer
Holly Law
Change Plan

Change Proposal Plan and Impact Assessment Report issued

Completed

Start:

06 Jun 2024

Due:

18 Jun 2024

Completion:

18 Jun 2024

Preliminary Change Report issued

Completed

Start:

18 Jun 2024

Due:

19 Jun 2024

Completion:

19 Jun 2024

Consultation issued

Completed

Start:

19 Jun 2024

Due:

19 Jun 2024

Completion:

19 Jun 2024

Consultation Close

Completed

Start:

19 Jun 2024

Due:

10 Jul 2024

Completion:

10 Jul 2024

Final Change Report Issued

Completed

Start:

10 Jul 2024

Due:

11 Jul 2024

Completion:

11 Jul 2024

Responsible Committee Decision

Completed

Start:

11 Jul 2024

Due:

19 Jul 2024

Completion:

19 Jul 2024

Appeal Window Closure

Not Started

Start:

19 Jul 2024

Due:

02 Aug 2024

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.12.0_Superseded

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 02 Nov 2026 PDF - 159.49 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
Metering Operations v4.1 footnote review legal drafting for PCR
Upload document
Metering Operations v4.1 footnote review - PCR.docx
Archive
Off
Document title
Metering Operations v4.1 footnote review legal drafting for FCR
Upload document
Metering Operations v4.1 footnote review - FCR (2).docx
Archive
Off
Problem Statement
REC parties are unable to ensure their processes and procedures correctly reflect their obligations as the footnotes within Schedule 14 - Metering Operations are not in the correct place, are missing or no longer relevant.
R0181 Change Proposal Plan (Approved) 18.06.2024
R0181 Initial Assessment Report (Approved) 18.06.2024
R0181 Preliminary Change Report
Consolidated Consultation Responses
R0181 Final Change Report - approved 22.07.24
Company Name
Code Manager
Review status
Review required

Change Smart Meter Installation Consumer Survey Specification survey questions to a REC Category 2 document

Date of latest update
Type
Change
ID
R0177
Change Category
Change Path
Priority
Urgent
No
Latest Update
This change was implemented on 06 September 2024.
Summary
Adding the Smart Meter Installation Consumer Survey Specification questions to the REC list of documents will allow any amendments to follow the REC change process and allow anyone to propose such amendments.
Proposer
Lorna Mallon
Change Plan

Preliminary Change Report published

Completed

Start:

22 May 2024

Due:

05 Jul 2024

Completion:

04 Jul 2024

Consultation opened

Completed

Start:

05 Jul 2024

Due:

05 Jul 2024

Completion:

04 Jul 2024

Consultation closes

Completed

Start:

05 Jul 2024

Due:

26 Jul 2024

Completion:

26 Jul 2024

Final Change Report published

Completed

Start:

26 Jul 2024

Due:

09 Aug 2024

Completion:

08 Aug 2024

Change Panel decision

Completed

Start:

09 Aug 2024

Due:

20 Aug 2024

Completion:

20 Aug 2024
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.13.0_Superseded

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Domestic or Micro-Business Consumer, I want the Smart Meter Installation survey questions to have robust governance, so I have confidence the right KPIs are being monitored.
  2. As an Energy Supplier, I want the Smart Meter Installation survey questions to be governed by the REC Change Process, so I can suggest and provide feedback on changes to them.
Proposed Solution Document
Document title
REC Baseline Statement DRAFT
Upload document
REC Baseline Statement DRAFT.xlsx
Archive
Off
Problem Statement
The Smart Meter Installation Consumer Survey Specification questions are mandatory for Energy Suppliers to use, but there is no mechanism for Energy Suppliers to raise changes or issues against the questions as they are not held in the REC Baseline Statement.
R0177 Change Proposal Form
R0177 Change Proposal Plan v1.0 Approved
R0177 Initial Assessment Report v1.0 Approved
R0177 Preliminary Change Report v1.0
R0177 Consolidated Consultation Responses v1.0
R0177 Change Report (Final Recommendation) V1.1
Company Name
Gemserv
Review status
Review required

Improvements to the Theft Detection Incentive Scheme (TDIS)

Date of latest update
Type
Change
ID
R0173
Change Category
Urgent
No
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
This Change proposes that not only Confirmed Energy Thefts are incentivised within the Theft Detection Incentive Scheme (TDIS) but also Energy Theft Desktop and Site Visit Investigations.
Proposer
Samantha Briggs
Change Plan

Party Impact Assessment Closure

Completed

Start:

20 May 2024

Due:

04 Oct 2024

Completion:

04 Oct 2024

Consultation

In Progress

Start:

04 Oct 2024

Due:

18 Oct 2024

Completion:

18 Oct 2024

Consultation Closure

Not Started

Start:

18 Oct 2024

Due:

08 Nov 2024

Completion:

Responsible Committee Decision

Not Started

Start:

08 Nov 2024

Due:

03 Dec 2024

Completion:

Send to Authority

Not Started

Start:

03 Dec 2024

Due:

04 Dec 2024

Completion:

Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Lead Analyst
florentina.monea
Solution Development
Proposed Solution Document
Document title
R0173 - Draft Legal Text (26.11.2024)
Upload document
R0173 - Draft Legal Text.zip
Archive
Off
Document title
I0173 - Example Calculations (13.08.2024)
Upload document
I0173 - Example Calculations.pdf
Archive
Off
Document title
R0173 - Solution Development Report v2.4 (26.11.2024)
Upload document
R0173 - Solution Development Report v2.4.pdf
Archive
Off
Problem Statement
Suppliers are not currently meeting their TDIS Theft targets within each TDIS Reporting Year because there may be financial disincentives to undertake investigations where there is no assurance that such investigations would convert into a Confirmed Energy Theft.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
awaghorn@deloitte.co.uk
I0173- Improvements to the Theft Detection Incentive Scheme
I0173 - Change Report (Proposal Plan) Approved 20.08.2024.
R0173 - Consolidated Impact Assessment Responses_NON-CONFIDENTIAL (18.10.2024)
R0173 - Change Report (For Consultation) 18.10.2024
R0173 Consolidated Consultation Responses NONCONFIDENTIAL (26.11.2024)
R0173 Final Change Report (Post-vote)
R0173 Decision Letter
Change Panel Response - Ofgem send back of R0173
Change Panel Response - Ofgem send back of R0173 - Further Clarifications
R0173 Final Decision Letter
Company Name
REC Code Manager
Review status
Review required

Change Process Improvements following Code Manager review

Date of latest update
Type
Change
ID
R0167
Change Category
Change Path
Priority
Urgent
No
Latest Update
19/07/24 - This change was implemented on the 19 July 2024.
Summary
This Change Proposal has been raised to make the required changes to Schedule1 and Schedule 5, to enable process enhancements to be made to support Change Process Improvements project.
Proposer
Helen Fosberry
Change Plan

Preliminary Change Reports Published

Completed

Start:

25 Apr 2024

Due:

17 May 2024

Completion:

17 May 2024

Consultation Published

Completed

Start:

17 May 2024

Due:

17 May 2024

Completion:

17 May 2024

Final Change Report Published

Completed

Start:

17 May 2024

Due:

07 Jun 2024

Completion:

25 Jun 2024

Responsible Committee Decison

Completed

Start:

07 Jun 2024

Due:

18 Jun 2024

Completion:

02 Jul 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.11.1_Superseded
Included changes Affected REC Items
R0167 Change Process Improvements following Code Manager review

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want REC issues and changes that impact Consumers to be developed with Parties and Market Participants input, with minimal delay or hassle, so that I can benefit from positive Consumer outcomes at the earliest opportunity.
  2. As a REC Party or Market Participant, I want to participate effectively and efficiently in the REC Change Process including the development and progression of industry issues, to shape and develop solutions.
Proposed Solution Document
Document title
R0167 - Final Legal Text
Upload document
R0167 - Final Legal Text.zip
Archive
Off
Problem Statement
Feedback gathered has highlighted issues with the current process including speed of the process, engagement, and inefficiencies. Amendments are required to Schedule 1 and Schedule 5, that will support the provision of a suite of enhancements to the Change Process.
Change Proposal Form
R0167 - Change Proposal Plan (Approved)
R0167 - Initial Assessment Report (Approved)
R0167 - Preliminary Change Report v1.1 (Published for Consultation)
R0167 Consolidated Consultation Responses
R0167 Final Change Report v1.0 (Post Vote)
Company Name
REC Code Manager
Review status
Review required

Removal of the Green Deal Panel

Date of latest update
Type
Change
ID
R0166
Change Category
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
This Change Proposal seeks to remove the Green Deal Panel Terms of Reference from the REC Baseline Statement and product set, and to amend the Change Panel Terms of Reference to incorporate consideration of Green Deal business.
Proposer
Paul Rocke
Change Plan

Preliminary Change Report Published

Completed

Start:

22 Apr 2024

Due:

09 May 2024

Completion:

09 May 2024

Consultation Issued

Completed

Start:

09 May 2024

Due:

09 May 2024

Completion:

09 May 2024

Final Change Report Issued

Completed

Start:

09 May 2024

Due:

07 Jun 2024

Completion:

07 Jun 2024

Responsible Committee Decision

Completed

Start:

07 Jun 2024

Due:

18 Jun 2024

Completion:

18 Jun 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.12.0_Superseded

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 02 Nov 2026 PDF - 159.49 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a party I want Green Deal matters, should they arise to be dealt with in a timely fashion. This could be difficult under the current arrangements where it is not possible to get a quorate panel to make decisions.
Proposed Solution Document
Document title
REC Change Panel - Terms of Reference - Red-lined
Upload document
REC Change Panel - Terms of Reference - Red-lined. V0.2.pdf
Archive
Off
Problem Statement
Since the REC was established, no business has been raised that would require the Green Deal Panel to meet and therefore the group has not yet convened. As well as being an unnecessary administrative consideration, it is a challenge to keep the Members and Chair abreast of the wider REC Change Process, and the Green Deal Panel may therefore find it more challenging to discharge its functions in the event that it needs to be convened.
Change Proposal Form
R0166 - Change Proposal Plan v1.0 (Approved)
R0166 - Initial Assessment Report (Approved)
R0166 - Preliminary Change Report V1.0
R0166 Final Change Report v1.0
Company Name
REC Code Manager
Review status
Review required

Prepayment Method Levelisation Reconciliation Housekeeping Change

Date of latest update
Type
Change
ID
R0165
Change Category
Change Path
Priority
Urgent
No
Latest Update
Implemented on 10/05/2024
Summary
The Code Manager has identified typographical and formatting errors, as well as opportunities to provide clarity, improve consistency and accuracy across the REC Services and products. These changes have been assessed as meeting the criteria to be progressed via a Housekeeping Change Proposal. Schedule 31 - Prepayment Method Levelisation Reconciliation: The Electricity and Gas Meter Point Portfolio Example's have typographical and formatting errors.
Proposer
Holly Law
Change Plan

House Keeping Change report published

Completed

Start:

16 Apr 2024

Due:

25 Apr 2024

Completion:

25 Apr 2024

Responsible Committee Decision

Not Started

Start:

25 Apr 2024

Due:

07 May 2024

Completion:

Status
Implementation Date
Status Superseded
EMAR Version 3.10.1_Superseded
Included changes Affected REC Items
R0165 Prepayment Method Levelisation Reconciliation Housekeeping Change
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
holly.law
Solution Development
Proposed Solution Document
Document title
Payment Method Levelisation Reconciliation V1.1
Upload document
Payment Method Levelisation Reconciliation v1.1.doc
Archive
Off
Problem Statement
This is a Housekeeping Change Proposal subject to the Housekeeping Change Proposal process, rather than the standard change process. The nature of the change is that it makes non-material changes to the REC Products to correct typographical and consistency errors. It also provides an opportunity to introduce necessary clarifications.
Gas Template AAA_01.csv
Electricity Template FFFF_01.csv
R0165 Housekeeping Change Report Post Vote
Company Name
Code Manager RPS
Review status
Review required

Removing the Enumerations from Communications Method Data Item (J0386) to align with BSC CP 1594

Date of latest update
Type
Change
ID
R0164
Change Path
Priority
Urgent
No
Latest Update
23/08/2024 - This change was successfully implemented as part of the August 2024 Extraordinary REC Release on 23 August 2024.
Summary
BSC has raised Change Proposal CP1594 which seeks to create an approvals process and a valid set for communications method. This change is proposing to create an approvals process to allow for the managed end dating of older technologies, such as Public switched telephone network (PSTN), Circuit Switched Data (CSD) and later 2G, and the assessment of the validity of newer communications technologies, such as (but not exclusively) Narrow Band-Intern of Things (NBIoT) and Category M (CAT-M). The evolution of metering communication systems underscores the need for timely updates. Legacy systems risk inefficiencies and potential security vulnerabilities. Implementing an approval process, modelled on BSCP601, ensures a standardised approach to introducing new technologies and managing the exit of old ones. Further justifications include: • To allow for the centrally managed end-dating of redundant communications technologies in line with known deadlines for those technologies to become redundant and unreliable. • To allow for the wider industry education of newer types of communication technologies. • To create and expand the already existing central knowledge base of the evolution and attributes of newer communication technologies as they relate to Settlement Metering Equipment. • To ensure transparency for all industry participants on the newer communications types available and the dates for which legacy communications must be removed. CP1594 will create a valid set, linked to the new approval process and using Data Item J0386 as a conduit to detail the approved communication methods as well as end dates for communication methods which are becoming redundant and unreliable.
Proposer
Christopher Day
Change Plan

PARTY IMPACT ASSESSMENT ISSUED

Completed

Start:

16 Apr 2024

Due:

25 Apr 2024

Completion:

25 Apr 2024

PRELIMINARY CHANGE REPORT AND CONSULTATION ISSUED

Completed

Start:

25 Apr 2024

Due:

23 May 2024

Completion:

23 May 2024

FINAL CHANGE REPORT ISSUED

Completed

Start:

23 May 2024

Due:

20 Jun 2024

Completion:

20 Jun 2024

RESPONSIBLE COMMITTEE DECISION

Completed

Start:

20 Jun 2024

Due:

02 Jul 2024

Completion:

02 Jul 2024
Status
Implementation Date
Status Superseded
EMAR Version 3.12.0_Superseded

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 02 Nov 2026 PDF - 159.49 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. As a Supplier/DNO/MEM, I want to ensure that Market Messages I send or receive to contain up-to-date, accurate data, so that I am able to effectively engage with the wider industry.
  2. As a non-REC Party Service User I want to ensure that Market Messages I send or receive to contain up-to-date, accurate data, so that I am able to effectively engage with the wider industry.
Proposed Solution Document
Document title
R0164 - Draft Solution - J0386 Data Item - Data Spec Changes 22.05.24
Upload document
R0164 - Draft Solution - Redlined Data Spec Changes 22.05.24 (1).pdf
Archive
Off
Problem Statement
The BSC are making changes to how permissible Outstation communication methods are captured and recorded within the industry. In order to align with these BSC led changes, the REC Data Specification must be reviewed in order to update the affected Data Item – DI50178 (J0386).
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0164 - Change Proposal Form (Word)
R0164 Change Proposal Form (PDF)
R0164 Change Proposal Plan (Approved) V1.0
R0164 Initial Assessment Report (Approved) V1.0
R0164 Consolidated Impact Assessment Responses v1.0 23.05.24
R0164 Preliminary Change Report (Published For Consultation) V1.0 23.05.24
R0164 Consolidated Consultation Responses v1.0 20.06.24
R0164 Final Change Report (Post-Vote) v1.0 03.07.24
Company Name
Elexon
Review status
Review required