Market Role Code
R
Harmonised context
ERDA
Registration Id Required for MHHS Appointments
Date of latest update
Type
Issue
ID
I0296
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/05/2026 - The Code Manager have developed a solution which has been live since 05 May 2026. More detail can be found on the REC Portal Wiki. A Closure Report has now been published, and this Issue has now been classed as resolved.
Summary
The RegistrationId (DI90043 / DI849) is required by SMRS to be included in the IF-031 'Supplier Agent Appointment Request' Market Message to allow the SMRA to process the appointment request. However not all Suppliers hold the RegistrationId for all Meter Points, in particular those that have not undergone a Registration managed by the Central Switching Service (CSS)
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As part of the solution for REC Issue I0296 - Registration Id Required for MHHS Appointments the REC Code Manager have developed a process to provide Energy Suppliers the Registration Id for Metering Points that have not been through a Central Switching Service (CSS) Registration Managed Switch. This is to allow Energy Suppliers that may not hold the Registration Id for these Metering Points to populate the Market-wide Half Hourly Settlement (MHHS) Agent Appointment Messages required to initiate a MHHS Migration.
- More detail of the solution can be found: https://portal.retailenergycode.co.uk/knowledge-centre/rec-wiki/market-wide-half-hourly-settlement/provision-registration-id-required?utm_source=emailoctopus&utm_medium=email&utm_campaign=Weekly%20Bulletin%20-%202026-05-01
Proposed Solution Document
Document title
I0296 Closure Report_v1.0 (12 May 2026)
Upload document
I0296_Closure report_v1.0.pdf
Archive
Off
Problem Statement
Not all Energy Suppliers hold the RegistrationId for all Meter Points, particularly those Meter Points that have not gone through a Switch, i.e. have not undergone a Registration managed by the CSS. The RegistrationId is currently only available where a Metering Point has been through a CSS managed Registration. Without the RegistrationId available to Energy Suppliers, not all Metering Points will be able to migrate putting the MHHS Migration and Milestone M15 at risk.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0296 submission form
Company Name
RECCo
Review status
Review required
Schedule 8 Review and Best Practice Guidance Development
Date of latest update
Type
Issue
ID
I0187
Change Category
Change Path
Priority
Urgent
No
Latest Update
18/11/2026 The REC Change Panel has approved the Update to Plan as part of the Bulk Update presented at their meeting on 17/11/2026
Summary
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. This Issue seeks to understand if there are any conflicts in the Schedule with best practice and identify any gaps or duplication. Alongside this, a best practice guidance document will be developed which is relevant, complete and aligned to current processes and obligations.
Change Plan
Proposal Plan Approved at Change Panel
Completed
Start:
26 Sep 2024Due:
31 Mar 2027Completion:
21 Jan 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Schedule 8 - Unbilled Energy Code of Practice has not been reviewed since its development for REC go-live. The Schedule needs to be reviewed to ensure it is up to date, understand if there are any conflicts with best practice and identify any gaps or duplication.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0187 - Change Proposal Form
I0187 - Change Report (Proposal Plan) V1.0 (Approved) 21.01.2025
I0187 - Change Report (Extension to Plan) Approved 17.06.2025
I0187 - Change Report (Extension to Plan) 02.09.2025
I0187 - Change Report (Extension to Plan) 13.01.2025 (Pre-Approval)
I0187 - Change Report (Extension to Plan) V1.0 Approved 25.06.2026
I0187 - Change Report (Extension to Plan) 13.01.2025
I0187 - Change Report (Extension to Plan) V5.0 (Approved)
Company Name
Code Manager
Review status
Review required
Consequential Change for CSS Smart Meter Data Retriever Appointments
Date of latest update
Type
Change
ID
R0097
Change Category
Change Path
Urgent
Yes
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
This change looks to make amendments to the Data Specification for the Supplier Arranged Appointments messages exchanged between the Electricity Retail Data Service and Central Switching Service.
Change Plan
Service Provider Impact Assessment started
Completed
Start:
20 Feb 2023Due:
22 Mar 2023Completion:
22 Mar 2023Service Provider Impact Assessment completed
Completed
Start:
22 Mar 2023Due:
03 May 2023Completion:
03 May 2023Preliminary Change Report and Consultation issued
Completed
Start:
03 May 2023Due:
19 May 2023Completion:
19 May 2023Consultation closed
Completed
Start:
19 May 2023Due:
05 Jun 2023Completion:
05 Jun 2023Final Change Report issued
Completed
Start:
05 Jun 2023Due:
21 Jun 2023Completion:
15 Jun 2023Responsible Committee decision
Completed
Start:
21 Jun 2023Due:
28 Jun 2023Completion:
04 Jul 2023Appeal Window opens
Completed
Start:
28 Jun 2023Due:
04 Jul 2023Completion:
04 Jul 2023Appeal Window closes
Completed
Start:
04 Jul 2023Due:
18 Jul 2023Completion:
18 Jul 2023Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
MHHS Programme Milestone M8 (Code changes delivered)
| Included changes | Affected REC Items | |
|---|---|---|
| R0044 | MHHS Programme Changes required to Central Switching Service |
|
| R0173 | Improvements to the Theft Detection Incentive Scheme (TDIS) |
|
| R0209 | Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements |
|
| R0222 | ESME ID Update Rejections | |
| R0223 | Reconciliation of Unallocatable Transactions Review |
|
| R0241 | MHHS Incremental Changes for go live |
|
| R0259 | Update to R0173 Implementation Date | |
| R0264 | Data Specification Housekeeping | |
| R0083 | Changes to Supply Number Format for MHHS | |
| R0097 | Consequential Change for CSS Smart Meter Data Retriever Appointments |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As the CSS Provider, I want to be able to identify which appointment messages received from ERDS require a response, so that I can confirm whether the appointment was successfully made in SMDSP
- As the ERDS Provider, I want to be able to indicate which appointment messages I need to receive a response for, so that I can understand which appointments have been successful in the SMDSP
- As an Electricity Supplier, I want Supplier appointments in the ERDS to match those held in SMDSP
Proposed Solution Document
Document title
R0097 Proposed Solution (Initial Assessment) 14.03.23
Upload document
R0097 Proposed Solution (Initial Assessment) 14.03.23.zip
Archive
Off
Document title
R0097 Proposed Solution (Impact Assessment) 22.03.23
Upload document
R0097 Proposed Solution (Impact Assessment) 22.03.23.zip
Archive
Off
Document title
R0097 Proposed Solution (Consultation) 17.05.23
Upload document
R0097 Proposed Solution (Consultation) 17.05.23.zip
Archive
Off
Document title
R0097 Draft Legal Text (Consultation) 17.05.2023
Upload document
Attachment B_R0097 Proposed Data Specification Changes_v1.6.pdf
Archive
Off
Problem Statement
The implementation of Change Proposal R0044, will result in the Central Switching Service (CSS) providing an asynchronous response to the Electricity Retail Data Service (ERDS) upon a successful, or unsuccessful Smart Meter Data Retriever (SMDR) appointment within the SMDSP. This will significantly increase the volume of CSS messages, as there is currently no mechanism for the CSS to recognise when a response is required. The increased volume could have a significant impact on central system performance.
Stages Selection
SME
SME Role
Lead Technical Analyst
Workgroup
Workgroup(s)
R0097 - Change Proposal Form downloadable version 20.02.2023
R0097 - Change Proposal Plan v2.0 (Approved) 21.03.2023
R0097 - Initial Assessment Report v2.0 (Approved) 21.03.23
R0097 - Preliminary Change Report v1.0 (For Consultation) 19.05.2023
R0097 Consolidated Consultation Responses v1.0 PUBLIC 15.06.2023
R0097 - Final Change Report v2.0 (Post-Vote) 04.07.2023
Company Name
REC Technical Services
Review status
Review required