Retrospective Implementation of Distribution Connection Use of System Agreement (DCUSA) DCP 383
Date of latest update
Type
Change
ID
R0117
Change Category
Change Path
Priority
Urgent
No
Latest Update
01/12/2023 - this change has been withdrawn and the adoption window is closed.
Summary
This change seeks to retrospectively deliver the consequential REC changes for the DCUSA Change Proposal DCP383 – Provision for Distributors to move meters for service alterations. DCP383 created a mechanism for licensed Distributors to move Whole Current (WC) meters as part of customer requested works to alter the service position.
Change Plan
Appeal window closure
Not Started
Start:
10 Jan 2024Due:
24 Jan 2024Completion:
Responsible Committee decision
Not Started
Start:
29 Dec 2023Due:
10 Jan 2024Completion:
Final Change Report issued
Not Started
Start:
08 Dec 2023Due:
29 Dec 2023Completion:
Consultation close
Not Started
Start:
17 Nov 2023Due:
08 Dec 2023Completion:
Preliminary Change Report published and Consultation triggered
Not Started
Start:
06 Nov 2023Due:
17 Nov 2023Completion:
Party Impact Assessment trigger
Completed
Start:
12 May 2023Due:
13 Oct 2023Completion:
13 Oct 2023Party Impact Assessment close
Not Started
Start:
13 Oct 2023Due:
06 Nov 2023Completion:
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer, I want industry systems to contain accurate information on my service so that future works or billing are not impacted.
- As a Metering Equipment Manager, I want to ensure my obligations are clear as to which Market Messages I am required to action and how this should be completed.
Problem Statement
Following the implementation of DCP383, MEMs are receiving Market Messages from the DNO however, there is no process defined within the REC on how to action them and their systems have not been configured to accept and process them. This has led to a backlog within the MEMs gateways and the Data Collector is not being updated on the meter’s new location.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0117 - Change Proposal Form 12.05.2023
R0117 - Change Proposal Plan v1.0 (Approved) 01.08.2023
R0117 - Initial Assessment Report v1.0 (Approved) 01.08.2023
R0117 - Change Plan Re-baseline (Approved) 29.09.2023
R0117 Change Report (For Consultation) v1.0
Company Name
REC Code Manager
Review status
Review required
TPI access to the Meter Asset Manager data via the GES
Date of latest update
Type
Change
ID
R0116
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/06/2024 - Adoption window closed. Withdrawn.
Summary
Empty
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0116 - Change Proposal Form (Downloadable version) 05.05.2023
Company Name
Ginger Energy Limited
Review status
Review required
Supplier compensation for Network Party driven MPXN or GSP Group changes
Date of latest update
Type
Change
ID
R0112
Priority
Urgent
No
Latest Update
28/07/2023 - The Proposer has withdrawn R0112. This Change Proposal is open for adoption for 10 Working Days, after which time it will be fully withdrawn on the REC Portal. If you wish to adopt the Change Proposal, you can do this via the ‘Adopt Proposal’ button by 23:59 on 12 August 2023.
Summary
Empty
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0112 - CP Form (Downloadable Version)
Company Name
ScottishPower Energy Retail Ltd
Review status
Review required
Provision of Grid Supply Point Group ID from a Postcode search in EES
Date of latest update
Type
Change
ID
R0111
Change Category
Change Path
Priority
Urgent
No
Latest Update
05/04/2024 - The Code Manager has rejected the progression of R0111 as Postcode itself does not always have a direct correlation to the GSP Group and believes that a full address should be provided so that accurate quotes are given to a Consumer.
Summary
Empty
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0111 - CP Form (Downloadable version)
Company Name
GB Group plc
Review status
Review required
Aligning electricity and gas timescale requirements for sharing Meter Technical Detail information
Date of latest update
Type
Change
ID
R0109
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/03/2024 - Withdrawn.
Summary
Empty
Impacted Consumers
Impacted REC Documents
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0109 - Change Proposal Form
Company Name
Utility Warehouse
Review status
Review required
CSS Message Time Stamping
Date of latest update
Type
Change
ID
R0107
Urgent
No
Latest Update
11/08/2023 - This Change Proposal has been withdrawn. During the progression of the Preliminary Impact Assessment work, it was found that an existing data item ‘EventDate’ could be leveraged to address the issue stated in the Change Proposal. R107 will be open for adoption until 25/08/2023.
Summary
Empty
Change Plan
Test
In Progress
Start:
14 Apr 2023Due:
19 Mar 2026Completion:
19 Mar 2026Status
Implementation Status
Date Raised
Solution Development
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
caroline.milner@capgemini.com
R0107 - Change Proposal Form
Company Name
DCC
Review status
Review required
Review of ONAGE SLAs
Date of latest update
Type
Change
ID
R0105
Change Category
Change Path
Priority
Urgent
No
Latest Update
11/09/24 - Change Report REJECTED by REC Metering Expert Panel
Summary
In light of the changes introduced as part of the Faster Switching Programme, this Change Proposal has been raised to review the SLAs and lead times around the sending and receiving/processing of the ONAGE and associated Market Messages.
Change Plan
Solution Development Closes
Completed
Start:
06 Apr 2023Due:
31 May 2024Completion:
31 May 2024Party Impact Assessment Published
Completed
Start:
31 May 2024Due:
04 Jul 2024Completion:
04 Jul 2024Preliminary Change Report & Consultation Published
Completed
Start:
04 Jul 2024Due:
08 Aug 2024Completion:
08 Aug 2024Final Change Report Published
Not Started
Start:
08 Aug 2024Due:
04 Sep 2024Completion:
Responsible Committee Decision
Not Started
Start:
04 Sep 2024Due:
11 Sep 2024Completion:
Appeal Window Closure
Not Started
Start:
11 Sep 2024Due:
25 Sep 2024Completion:
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer, I want to have continual Meter Equipment Manager coverage, so that I am confident that work on my Metering Asset can be conducted even during a Switch.
- As a MEM, I want my obligations relating to appointment and de-appointment to be considered and practicable, so that my operational processes are not unduly onerous. 2 - As a Gas Supplier, I want to be able to reliably and predictably appoint and de-appoint MEMs during a Switch, so that I am confident that my Consumers are not left without a MEM at any stage. 3 - As the Code Manager, I want REC processes to operate within SLAs that are reflective of both the realistic operational capacities of REC Parties, and also of the needs of the broader market, so that the end Consumer has the best possible Switching experience.
Problem Statement
Current ONAGE SLAs may no longer be proportionate to the length of the Switching process as a result of the Faster Switching programme. Lengthy ONAGE SLAs relative to the timescale of the switching process may result in Consumers being left without a MEM during the switch process. The proposer has asked the Code Manager to conduct a review of the ONAGE SLAs to explore whether these SLAs are still appropriate, and therefore ensure that Consumers are subject to any detriment.
Stages Selection
SME
SME Role
Lead Assurance Analyst
R0105 - Change Proposal Form (downloadable version) 06.04.2023
R0105 Change Proposal Plan (Approved) V2.0 31.05.24
R0105 Initial Assessment Report (Approved) V1.0 16.04.24
R0105 Change Proposal Re-Plan (Approved) V1.0 31.05.24
R0105 Consolidated IA Responses V1.0 08.08.24
R0105 Change Report (Published for Consultation) v1.0 08.08.24
R0105 Consolidated Consultation Responses V1.0 02.09.2024
R0105 Change Report (Rejected) V2.0 11.09.24
Company Name
-
Review status
Review required
Performance Assurance Report Catalogue V5.1
Date of latest update
Type
Change
ID
R0106
Urgent
No
Latest Update
15/11/2023 - R0106 has been withdrawn. Further changes to the Performance Assurance Report Catalogue (PARC) are required and will be delivered through a separate Change Proposal.
Summary
The Report Catalogue has been updated following our annual product review and in line with changes made to the Retail Risk Register, which are going through consultation in parallel.
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
RECPAB_23_Performance Assurance Report Catalogue V5.1 - REDLINE.xlsx
Company Name
REC Code Manager
Review status
Review required
Clarifying requirement for continuous billing following an Erroneous Switch
Date of latest update
Type
Change
ID
R0104
Urgent
No
Latest Update
04/10/2023 - Following the approval of R0138, this change has been withdrawn.
Summary
Schedule 30 (Resolution of Consumer Facing Switching and Billing Issues) includes requirements on Suppliers relating to the identification and resolution of Erroneous Switches. This includes a set of principles and outcomes that Supplier's must adhere to. One of the required outcomes of an Erroneous Switch is that the consumer is only billed once for the period of the Erroneous Switch, and that they are only billed by the Supplier they have a valid contract with. Paragraph 5.2 of the CFSB Schedule sets out that the Losing Supplier should accept responsibility for billing during the period of the Erroneous Switch. However, it is not explicitly clear that the Gaining Supplier should not bill the consumer for consumption during the period of the erroneous supply. This Change Proposal has been raised to review the wording of paragraph 5.2, or the resolution outcomes more generally, so there it is clear to Suppliers, and the REC PAB in their assurance activities, what the expectations are.
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0104 Change Proposal form (downloadable version) 02.04.2023
Company Name
RECCo
Review status
Review required
Update to Error Handling Documents
Date of latest update
Type
Change
ID
R0100
Change Category
Change Path
Priority
Urgent
No
Latest Update
Following further solution development under R0178 - Improvements to CSS Business Process Logic, the Code Manager has now determined that the REC products previously considered for amendments under R0100 will require further updates under R0178. As such, R0100 will now be considered under the scope of R0178 rather than progressed as a separate change.
Summary
There are duplications between the CSS Message Business Data Validation Rules document (a Category 2 document) and the CSS Error Processing guide (a Category 3 guidance document), which is resulting in confusion and complications within the error handling process. This Change Proposal has been raised to update the Business Data Validation Rules document, to capture the appropriate information that is removed from the CSS Error Processing guide and to ensure alignment with newly created knowledge articles
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0100 - Change Proposal Form 16.03.2023
Company Name
-
Review status
Review required