Market Role Code
Other
Harmonised context
Other
REC change to align with BSC IF-045 notification for Import/Export MPAN meter type misalignment
Date of latest update
Type
Change
ID
R0347
Change Category
Other Industry Codes impacted
Change Path
Impact Assessment
Urgent
No
Latest Update
05/11/2026 The Party impact assessment was published on 05 November 2026 and will remain open to responses until 27 November 2026. The Issue progressed to a Change Proposal on 05 November 2026.
Summary
Elexon are raising a CP that would introduce additional SMRS validation controls and a new IF-045 notification scenario to identify and manage metering misalignment across associated Import and Export MPANs. As this places obligations on MOAs, an impact to REC Schedule 14 has been identified.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0347 Legal Text Draft for Party impact assessment
Upload document
R0347 - Legal Text for Party IA.zip
Archive
Off
Problem Statement
The BSC CP CP1652 – Introduction of IF-045 notification from Registration Service for meter type misalignment was raised at the Supplier Volume Allocation Group on 06 October 2026. Following MHHS migration activity, Distribution Network Operators (DNOs) have identified and removed a population of Import and Export MPAN associations that contained inconsistent metering characteristics, including instances where one MPAN was configured with Smart Metering and the other with Advanced Metering. BSC CP1652 is seeking to create a new IF-045 notification scenario for the Supplier and the MOA to identify and manage misalignment issues. As BSC CP1652 relies on a new obligation on MOAs to agree on an approach to resolve the issue with the Electricity Supplier, a REC Issue is required to update Schedule 14 – Metering Operations.
Stages Selection
I0347 Change Report (Proposal Plan) Approved
Company Name
Code Manager
Review status
Review required
Improved Validation for DI51599 - Electricity Smart Meter Equipment (ESME ID)
Date of latest update
Type
Issue
ID
I0341
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
18/11/2026 - The Change Report (Proposal Plan) was approved by the REC Change Panel
Summary
A DNO has raised an issue with the ESME ID data stored in MPRS. Some of the ESMEs are passing MPRS basic validation but are being rejected by the proposed Metering Service preventing a change of service.
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
Solution Development
Problem Statement
A DNO has raised an issue with the ESME ID data stored in MPRS. Some of the ESMEs are passing MPRS basic validation but are being rejected by the proposed Metering Service preventing a change of service (Rejection of IF-033 with IF-035 Response R). Basic REC R032 Validation on IF-005/D0312: XX-XX-XX-XX-XX-XX-XX-XX (0-9, A-Z)
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0341 submission form
Change Report - Proposal Plan
Company Name
-
Review status
Review required
Tariff Interoperability Phase 1a – Supplier Performance Assurance Requirements
Date of latest update
Type
Change
ID
R0323
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 27 October 2026, the REC Performance Assurance Board, in line with the Code Manager recommendation Approved R0323
Summary
Obligations are being introduced into the REC to require Suppliers to make Tariff Pricing Data available to Tariff Interoperability Users (TI Users) using a new Tariff Interoperability Application Programming Interface (TI API). This proposal will provide Code Manager with data to assure supplier performance against obligations in a new REC Schedule: Tariff Interoperability Arrangements.
Impacted REC Parties and Market Participants
Status
Implementation Date
18 February 2027
| Included changes | Affected REC Items | |
|---|---|---|
| R0323 | Tariff Interoperability Phase 1a – Supplier Performance Assurance Requirements |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
This proposal will provide the Code Manager with data to assure Supplier performance against obligations in a new REC Schedule: Tariff Interoperability Arrangements. If Suppliers do not meet their Tariff Interoperability obligations, this could lead to Consumers’ Energy supply not being optimised, meaning that Consumers may incur higher charges. If price signals are not responded to through optimisation, this may also have other impacts such as reduced Net Zero benefits and reduced response to capacity constraints.
Stages Selection
Workgroup
Workgroup(s)
I0323 submission form
I0323 - REC Prioritisation Matrix
I0323 Change Report (Proposal Plan) Approved
R0323 Legal Drafting
I0323 Party IA Request
I0323 Consolidated Party IA Responses NON-CONFIDENTIAL
R0323 Change Report (For Consultation)
R0323 Consolidated Non-Confidential Consultation Responses
R0323 Change Proposal Re-Plan v1.0 Approved 29.09.26
R0323 Legal drafting - Final
R0323 Change Report (Final Recommendation) V1.1 Approved
Company Name
RECCo
Review status
Review required
Introduction of Consumer Consent Service
Date of latest update
Type
Change
ID
R0318
Date of next activity
Change Category
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
18/11/2026 - The Issue was progressed to Change Proposal on 17 November 2026. Following industry consultation on the REC drafting a number of refinements to the CCS design and drafting are being made. On progression to Change Proposal and Modification, the title has been updated to Introduction of Consumer Consent Service (not Solution) to reflect the new service that will be introduced.
Summary
This initiative will support the transformation of how energy is managed and consumed by giving consumers control over their energy (gas, electricity, heat, or other) data, enabling innovation through third-party services, and advancing sustainability goals. This REC Issue is being raised to promote visibility and awareness of opportunities for engagement, in advance of the CCS Change Proposal being progressed.
Change Plan
Proposal Plan (Approved)
Completed
Start:
02 Apr 2026Due:
02 Apr 2026Completion:
02 Apr 2026Update to Plan (Approved)
Completed
Start:
30 Sep 2026Due:
30 Sep 2026Completion:
30 Sep 2026Definition
Completed
Start:
02 Apr 2026Due:
17 Nov 2026Completion:
17 Nov 2026Business Case Assessment
In Progress
Start:
18 Nov 2026Due:
18 Dec 2026Completion:
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
RECCo | Consumer Consent Programme page
Archive
Off
Document title
Consumer Consent Hub - REC Portal
Archive
Off
Document title
Consumer Consent Solution Design Consultation (March 2026)
Archive
Off
Document title
RECCo's response to the CCS Design Consultation - 28 May 2026
Archive
Off
Problem Statement
A new set of arrangements for a Consumer Consent Solution (CCS) is currently being developed under the RECCo CCS project. The new arrangements will need to be implemented within the REC so that they can be governed under the REC on an enduring basis.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0318 submission form
RECCHIG_26_0305 - I0318 Consumer Consent Solution
I0318 Change Proposal Re-Plan v2.0 APPROVED 30.09.2026.
I0318 Change Report (Proposal Plan) v1.0 APPROVED 02.04.2026
Company Name
Retail Energy Code Company Ltd
Review status
Review required
Meter Manufacturers Make and Type not Populated in SMRS
Date of latest update
Type
Issue
ID
I0297
Change Path
Priority
Urgent
No
Latest Update
On 30 September 2026, the REC Technical Expert Panel voted to approve the Update to Plan for I0297, and to place this REC Issue on hold.
Summary
The Meter Manufacturers Make and Type (J0410 / DI-048) was not populated as part of the MHHS Programme's data cleanse. However it is part of the SMRS maintained Meter Technical Details (MTDs) for Smart Meters which replace the DTC MTD Market Messages for Smart Meters in the MHHS environment. It is not currently possible to populate this item in the legacy arrangements.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Following MHHS Migration, the MTDs provided by SMRS do not include the Meter Manufacturers Make and Type, as this replaces the existing D0149/D0150 Market Messages it could lead to the information being lost. This will mean Energy Suppliers and MOAs will not know the make and type of meter installed at a particular Site.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0297 submission form
I0297 Change Report (Proposal Plan) V1.0
I0297 Update to plan
I0297 Legal Drafting
I0297 Update to plan v1.0 Approved 30.09.26
Company Name
RECCo
Review status
Review required
Review of Schedule 1 Interpretations and Definitions
Date of latest update
Type
Change
ID
R0291
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
During the quality checks of REC Schedules for MHHS, several capitalised terms throughout schedules were identified with no entry in Schedule 1. It has also been identified that there are definitions that link to Schedules (such as 2, 20 and 21) which are no longer live REC Schedules. The Code Manager has reviewed these and determined some changes are required to Schedule 1.
Change Plan
Change Report (Proposal Plan) approved by Change Panel
Completed
Start:
Due:
Completion:
17 Feb 2026Approved at Change Panel for implementation in June 2026
Completed
Start:
Due:
Completion:
21 Apr 2026Impacted REC Documents
Status
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0291 REC Main Body draft V0.1
Upload document
R0291 REC Main Body draft V0.1.docx
Archive
Off
Document title
R0291 Schedule 1 draft V0.1
Upload document
R0291 Schedule 1 draft V0.1 (1).docx
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Upload document
R0291 Schedule 25 (CSS) draft V0.1.docx
Archive
Off
Document title
R0291 Schedule 1 draft V0.2
Upload document
R0291 Schedule 1 draft V0.2.docx
Archive
Off
Document title
R0291 REC Main Body draft V0.1
Upload document
R0291 REC Main Body draft V0.1 (1).docx
Archive
Off
Document title
R0291 Schedule 25 (CSS) draft V0.1
Upload document
R0291 Schedule 25 (CSS) draft V0.1 (1).docx
Archive
Off
Problem Statement
Without clear definitions of all defined terms within the REC, there may be confusion for REC Parties and other industry participants who use REC documents.
Stages Selection
I0291 submission form
I0291 Change Report (Proposal Plan) V1.0
R0291 Change Report (For Consultation) V1.0
R0291 Consolidated Consultation Responses v1.0
R0291 Change Report (Final Recommendation) V1.1 approved 21.04.26
Company Name
REC Code Manager
Review status
Review required
Missing Scenario Variant from R0043
Date of latest update
Type
Change
ID
R0242
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
There is a missing scenario variant from the introduction of R0043 – Schedule 14 Metering Operations states the Crowded Meter Room MOA (CMRM) should send a D0139 to the Supplier and DNO but the scenario variant of CMRM to DNO is missing.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
18 Mar 2025Final vote at Technical Expert Panel
Completed
Start:
Due:
Completion:
25 Jun 2025Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
CMRMs currently cannot send all the Market Messages required of them in Schedule 14 Metering Operations.
Stages Selection
Change Proposal form
R0242 Change Report (Proposal Plan) V1.0 Approved 18.03.25
R0242 Consolidated Impact Assessment Responses
R0242 Change Report (For Consultation) V1.0
R0242 Consolidated Consultation Responses v1.0
R0242 Change Report (Final Recommendation) V1.0 approved 25.06.25
Company Name
-
Review status
Review required
D0303 flow following MHHS design changes
Date of latest update
Type
Issue
ID
I0230
Change Path
Priority
Urgent
No
Latest Update
29/04/2026 - This Issue has been withdrawn by the Proposer, as there was not a strong preference amongst MAPs of which temporary solution option (if any) should be progressed. Many MAPs already have workarounds in place, and a permanent solution is expected to be progressed in the future through a joint REC / BSC change. The adoption window has closed.
Summary
As part of Market Wide Half Hourly Settlement (MHHS) design, the requirement to provide Data Item Effective from Settlement Date {REGI} (J0049 / DI50025) in the Notification of Meter Operator, Supplier and Metering Assets installed / removed by the MOP to the MAP Market Message (D0303 / MM00240) has been changed from mandatory to optional. This means Meter Asset Providers (MAP) may not receive it.
Change Plan
Change Report (Proposal Plan) approved at Change Panel
Completed
Start:
Due:
Completion:
04 Nov 2025Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The Effective from Settlement Date {REGI} Data Item being optional rather than mandatory inside the Notification of Meter Operator, Supplier and Metering Assets installed / removed by the MOP to the MAP Market Message means that MAPs may not receive this information required for billing purposes.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
Issue Proposal Form
I0230 Change Report (Proposal Plan) V1.0 approved 04.11.25
I0230 and I0261 Solution Development Report V1.0
I0230 I0261 Q&A session V1.0
I0230 and I0261 Consolidated IR Responses PUBLIC V1.0
Company Name
Calisen Asset Management Limited
Review status
Review required
Stranded RMPs in Defunct Suppliers
Date of latest update
Type
Issue
ID
I0219
Change Path
Priority
Urgent
No
Latest Update
27/02/2025 - Change is now not being merged into any other changes and will proceed as a standalone change. A potential solution has been identified, but will be discussed for potential cross code impacts
Summary
Currently within Schedule 23 a Registration can only be undertaken on RMPs with an Operational or Dormant RMP Status, and not Terminated. Terminated is a status that the RMP is set to when the Meter Point Status is no longer operational or the site is isolated. It is right that these sites are not able to be Registered as there is a risk that Suppliers could inadvertently Register such Meter Points. We do have instances where such sites are stranded in defunct Supplier portfolios - and the Supplier no longer has the capability to take the relevant action to Deactivate the Registrations. This may because the operational staff have left and the business is in administration.
Change Plan
Discussed at Technical Change Workshop
Completed
Start:
Due:
Completion:
25 Feb 2025Impacted Consumers
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue Proposal Form
Company Name
Xoserve
Review status
Review required
Introducing Third Party Intermediary (energy broker) assurance and accreditation (Alternate)
Date of latest update
Type
Change
ID
R0137A
Change Category
Urgent
No
Latest Update
16/05/2025 - the Authority have published their decision to reject R0137 and R0137A.
Summary
This change seeks to expand the obligation for Energy Suppliers to only work with TPIs who are adhering to principles as set out in the REC TPI Code of Practice to all Non-Domestic Consumers. It also looks to reduce the burden on Energy Suppliers having to perform their own audits by introducing a REC Services Accreditation Scheme and allowing companies to qualify as an Industry-Recognised Accreditation Body.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Legal Text R0137A Consultation
Upload document
Legal Text R0137A Consultation.zip
Archive
Off
Document title
Legal Text for R0137A - Final
Upload document
R0137A Final Legal Text.zip
Archive
Off
Problem Statement
Non-Domestic Consumers have more limited protections than Domestic and Microbusiness Consumers in the energy market, and so may not always experience best practice from all parties they interact with. The aim is to expand these protections while limiting the audit burdens on Suppliers and TPIs.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0137A Change Proposal Form
Authority decision on REC modification proposal R0137 and R0137A
Company Name
REC Code Manager
Review status
Review required