Changes to allow DNOs to reinstate disconnected MPANs
Date of latest update
Type
Change
ID
R0095
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
The Code Manager have taken R0095 off of hold and published an Information Request for R0095 on 22 October 2026, this is open to responses until 13 November 2026.
Summary
When Meter Point Administration Numbers (MPANs) are erroneously disconnected, they cannot be reinstated. As a result, Consumers suffer billing issues and Registered Suppliers cannot settle against the disconnected MPAN. This change seeks to introduce a mechanism to restore erroneously disconnected MPANs.
Change Plan
Solution Development
Completed
Start:
17 Feb 2023Due:
26 Jan 2024Completion:
26 Jan 2024Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
- As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Problem Statement
When MPANs are incorrectly identified and targeted for disconnection, the RMP will be erroneously terminated following receipt of Termination Market Messages by the CSS. This process is irreversible once triggered, meaning that there is no mechanism to restore the MPAN as it was previously. This results in a poor Consumer experience, and settlement misbalancing for Registered Suppliers. Currently, there is no mechanism to mitigate the negative impact on Registered Suppliers/DNO and Consumers.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0095 - Change Proposal form downloadable version 17.02.2023
R0095 Change Proposal Plan v1.0 (Approved) - 20.09.23
R0095 Initial Assessment Report v1.0 (Approved) - 20.09.2023
R0095 - Change Proposal Re-Plan (Approved) v1.0-13.12.23
Company Name
-
Review status
Review required
DCC Service Level Agreements for the Switching Incentive Regime
Date of latest update
Type
Change
ID
R0092
Change Category
Priority
Urgent
No
Latest Update
22/07/2024 - The Authority rejected R0092 and approved R0092A for implementation 08/11/2024. R0092A Change Proposal page link: https://recportal.co.uk/group/guest/-/dcc-service-level-agreements-for-the-switching-incentive-regime-1
Summary
Requirements for the Central Switching Service (CSS) were identified during the Design, Build and Test Phase of the Ofgem-led Switching Programme as a basis for the procurement of Switching systems. These requirements were later baselined in the REC Service Definitions as Service Level Agreements (SLAs). Following the successful go-live of the CSS, these SLAs merit a review, in order to ensure that they are realistic, given the physical systems design and the actual behaviours of users, compared to the assumptions that were made in the early design phase of the Switching Programme. This Change Proposal has been raised as the vehicle to complete the review and take forward any identified changes.
Change Plan
Solution Development
Completed
Start:
01 Feb 2023Due:
05 Oct 2023Completion:
05 Oct 2023Service Provider Impact Assessment
Completed
Start:
05 Oct 2023Due:
20 Nov 2023Completion:
13 Nov 2023Party Impact Assessment
Completed
Start:
20 Nov 2023Due:
03 Jan 2024Completion:
10 Nov 2023Preliminary Change Report issued
Completed
Start:
03 Jan 2024Due:
20 Feb 2024Completion:
16 Feb 2024Preliminary Change Report - Committee Review
Completed
Start:
20 Feb 2024Due:
27 Feb 2024Completion:
27 Feb 2024Consultation close
Completed
Start:
01 Mar 2024Due:
04 Apr 2024Completion:
04 Apr 2024Final Change Report issued
Completed
Start:
04 Apr 2024Due:
23 Apr 2024Completion:
19 Apr 2024Responsible Committee Decision
Completed
Start:
23 Apr 2024Due:
30 Apr 2024Completion:
30 Apr 2024Sent to Authority for Determination
Not Started
Start:
30 Apr 2024Due:
01 May 2024Completion:
Consultation published
Completed
Start:
27 Feb 2024Due:
01 Mar 2024Completion:
01 Mar 2024Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer, I want the CRS Provider to provide an effective service so that my Switch is not delayed.
- As the REC Code Manager, I want to ensure the CRS Provider has appropriate SLAs set, which incentivises the effective functioning of the Switching Service.
- As the CRS Provider, I want to ensure that the appropriate SLAs are in place to incentivise the effective functioning of the Switching Service and if these SLAs are not met by the CRS Provider, the commercial impact is proportionate to the detriment experienced by CSS Users and Consumers.
Proposed Solution Document
Document title
R0092 DCC Red line Proposal (26.01.2024)
Upload document
R0092 DCC Red line Proposal.pptx
Archive
Off
Document title
R0092_Legal Text at FCR (19.04.2024)
Upload document
R0092_Legal Text at FCR.zip
Archive
Off
Problem Statement
Following the introduction of Performance Charges, on 01 April 2023, charges will apply based on the CRS Provider's performance against the defined SLAs. The SLAs were developed based on assumptions made in the early phases of the Switching Programme. The DCC has proposed that these are reviewed, to ensure they are fit for purpose and any Performance Charges applied are proportionate to CSS User detriment and Consumer impact.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Switching Performance Measures - DCC's proposed changes.pdf
DCC Service Level Agreements for the Switching Incentive Regime - Change Proposal Form
Switching Performance Regime PMEL Candidates v2.0
R0092 - Change Proposal Plan (Approved) 06.06.2023
R0092 Extension to Change Plan 1.0 (Approved) 15.08.2023
R0092 - Initial Assessment Report (Approved) 06.06.2023
R0092 - Rebaselined Change Plan (Approved 12.01.2024)
R0092_Consolidated Impact Assessment Responses_NON-CONFIDENTIAL (16.02.2024)
R0092 and R0092A - Preliminary Change Report v1.1 (Approved) 28.02.2024
R0092 and R0092A - Consolidated Consultation Responses (19.04.2024)
R0092 and R0092A - Final Change Report v2.0 (Post-Vote) 30.04.2024
R0092A_Authority_Decision (22.07.2024)
Company Name
DCC
Review status
Review required
Removal of Pre-COVID AQ Value from Data Access Matrix
Date of latest update
Type
Change
ID
R0089
Priority
Urgent
No
Latest Update
05/01/2024 - This change proposal has been withdrawn. Since the implementation of R0118 – Review of Schedule 12 and processes to manage access to data, the Gas Data Access Matrix has been made a Category 3 document and the removal of the Pre-COVID AQ value has been progressed through C3-0058 – Administrative Changes to align to the Data Permissions Matrix. C3-0058 is due for implementation on 26 January 2024. It will be open for adoption until 23:59 19 January 2024.
Summary
Empty
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Company Name
Xoserve
Review status
Review required
MAP GES data access
Date of latest update
Type
Change
ID
R0087
Change Category
Change Path
Priority
Urgent
No
Latest Update
20/01/25 - Change Proposal withdrawn at proposers request.
Summary
As a MAP I want to be able to track my daily position of my portfolio. As a MAP I want to be able to track changes in my portfolio over time. As a MAP I want to understand who are using my assets and identify where assets are not being used
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
Company Name
Correla
Review status
Review required
ERDS Upload File in the Data Specification and clarification of cancellation code
Date of latest update
Type
Change
ID
R0086
Priority
Urgent
No
Latest Update
06/11/2023 - Withdrawal adoption window closed.
Summary
The MPAS/ERDS Upload file has historically been a part of the Data Specification however during transition from the MRA, the process has been omitted. This change seeks to restore the file to the specification. Secondly, the file previously provided a cancellation reason code for Switches. Under the current REC arrangements (i.e. since CSS go live) Reason codes are not provided and have been defaulting to W which indicated a reason of “withdrawn” which may now be misleading. This Change Proposal has been raised to address these issues
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0086 - Change Proposal Form (downloadable version)
Company Name
-
Review status
Review required
Switching Programme Designation of the Steady State Commencement Date
Date of latest update
Type
Change
ID
R0085
Priority
Urgent
No
Latest Update
16/05/2023 - This change has been withdrawn by the Code Manager. The changes required to reflect the designation of the Steady State Commencement Date have been approved under Housekeeping Change Proposal. R0114 will be implemented as part of the June release on 30 June 2023.
Summary
Following Ofgem’s designation of the “Steady State Commencement Date” as 00:01 hours on 31 October 2022, this CP will remove redundant text and make the necessary changes to reflect the designation.
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0085 - Change Proposal Form (downloadable version)
Ofgem Designation of the Steady State Commencement Date.pdf
Company Name
-
Review status
Review required
Changes to Supply Number Format for MHHS (Alternative)
Date of latest update
Type
Change
ID
R0083A
Priority
Urgent
No
Latest Update
17/11/2023 - The Authority has rejected R0083A, but has approved R0083 for implementation on MHHS M8 *This Change Proposal is a consequential change from the Market-wide Half Hourly Settlement programme
Summary
The Electricity Supply License requires Suppliers to provide the Supply Number to each Consumer on every bill, or at least once per year where no bill has been sent. The Supply Number format is prescribed by the REC and is detailed in the Energy Market Data Specification. The MHHS design is changing the data associated with each individual metering point, including those data items currently displayed within the Supply Number top line. This is an Alternative Change Proposal to R0083, which proposes to replace the format of the top line in the Supply Number Format. This Change Proposal proposes to remove the top line completely from the S Number format. Both solutions are being progressed together to allow for a clear assessment of the benefits and drawbacks and impacts to consumers.
Original CP
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As an electricity Consumer I want to be able to provide my prospective Energy Supplier with the necessary information for them to provide a suitable tariff. As a Non-Domestic Consumer, I want to have the necessary information that will allow me to access tariff information, specific to my business, to help me manage my energy. As an electricity Consumer, I want to have access to the data that will help me appoint my own Metering Equipment Manager (MEM) where permitted.
- As a Supplier, I want to know how to populate and format the Supply Number, so that I can meet my obligations to include it in Consumer bills or statements. As a Third Party Intermediary (TPI), I want Consumers to be able to provide me with the right information to provide appropriate quotes.
- As an independent Distribution Network Operator, I want to be able to identify and use the DUoS Tariff Id so that I can provide transparency on charging that is being applied to my customers. As the Electricity Enquiry Service (EES) Provider, I want to know how to populate the Supply Number so that I can make it available on the EES
Problem Statement
The Market-wide Half Hourly Settlement design is impacting the Data Items that are used in the top line of the Supply Number, which Energy Suppliers are obliged to provide to Consumers at least once a year under their Licence. A revised definition of the Supply Number format is required so that Electricity Suppliers have a clear understanding of the approach to populating the Supply Number for metering points that have migrated to the new MHHS arrangements.
Stages Selection
SME
SME Role
Lead Technical Analyst
Workgroup
Workgroup(s)
R0083A - Change Proposal Form 05.12.2022
Decision to Reject Change Proposal R0083A - Change to Supply Number Format Alternate
Company Name
-
Review status
Review required
Formalising the Submission of PPMIP Unallocated Transaction Report (UTR) Files
Date of latest update
Type
Change
ID
R0082
Change Category
Change Path
Priority
Urgent
No
Latest Update
09/04/2024 - Due to the MHHS impact on Service Providers, the technical code freeze and any MHHS impacts on the proposed solution, the Code Manager has reconsidered the priority of R0082 and believes that should be progressed following MHHS go-live. This Change Proposal has been withdrawn, and the Code Manager will consider raising a new change at the appropriate time following MHHS with consideration of the Codes Roadmap.
Summary
This CP seeks to address the following issues regarding the Unallocated Transaction Report (UTR) files provided by PPMIPs to the Code Manager each month: 1. There is no REC requirement for PPMIPs to submit a monthly file to the Code Manager 2. PPMIPs are currently submitting files in two different file formats 3. C&C is only able to load one of the two file formats The CP has been raised to introduce a requirement in the REC for PPMIPs to provide monthly Unallocated Transaction Report (UTR) files to the Code Manager in a single file format, set out in the REC Data Specification. With this format being one that can be loaded by C&C.
Change Plan
Solution analysis and development
Completed
Start:
28 Nov 2022Due:
12 Jan 2024Completion:
11 Jan 2024Service Provider Impact Assessment start date
Completed
Start:
12 Jan 2024Due:
15 Jan 2024Completion:
15 Jan 2024Service Provider Impact Assessment close
Completed
Start:
15 Jan 2024Due:
11 Mar 2024Completion:
11 Mar 2024Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a PPMIP, I want to have clear guidance on how and when I should submit my Unallocated Transaction Report files.
- As a Supplier, I want to receive accurate Unallocated Transactions in relation to prepayment meters that are not smart meters.
- As the Code Manager, I want visibility of the Unallocated Transaction Report.
- As the EES Provider, I want to be able to efficiently upload the Unallocated Transaction Reports.
Problem Statement
PPMIPs aren’t submitting UTR files in the same format, and one of these formats cannot be loaded by the EES Provider. There is also no obligation in the REC for these reports to be provided.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0082 - Change Proposal Form
R0082 - Change Proposal Plan (Approved) 17.10.2023
R0082 Initial Assessment Report (Approved) 17.10.2023
Company Name
REC Code Manager
Review status
Review required
CSS Market Message Retry Strategy
Date of latest update
Type
Change
ID
R0081
Priority
Urgent
No
Latest Update
15/11/2023 - Change Proposal has been withdrawn. Market message success data for September 2023 was reviewed to ensure that a stable period was analysed which represented ‘normal’ conditions. Upon completion of the review, it has been concluded that the success of the current retry strategy has significantly improved since this change proposal was raised. The Code Manager will introduce cyclical reviews of performance to ensure this continues at the expected levels.
Summary
The prescriptive nature of the Market Message retry drafting is currently impeding on the CSS Service Provider’s ability to ensure all Market Messages are sent and received successfully between the CSS and the CSS User. This CP proposes a move to a principles-based obligation that allows for flexibility to ensure the CSS and CSS User are able to attempt retries but not have to follow specific timings or have a maximum number of retries.
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0081 - Change Proposal Form
Proposed legal text submitted with the CP
Company Name
-
Review status
Review required
Addition of Previous MEM to the EES API
Date of latest update
Type
Change
ID
R0079
Change Category
Change Path
Priority
Urgent
No
Latest Update
14/05/2024 - As this Change Proposal is affected by the MHHS Code Freeze, the Proposer has withdrawn this CP and may reraise it post M10.
Summary
This change aims to add the previously appointed MEM as a data item viewable in the EES API
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Addition of Previous MEM to the EES API.docx
Company Name
EDF
Review status
Review required