Schedule 11 - Prepayment Arrangements 2.8
– Implemented on
Market Participant Applicability
| Market participant | All Sections |
|---|---|
| Domestic Suppliers | Mandatory |
| Non-Domestic Suppliers | Mandatory |
| Gas Transporters | N/A |
| Distribution Network Operators | N/A |
| DCC | N/A |
| Metering Equipment Managers | N/A |
| Non-Party REC Service Users | N/A |
Loading...
Crossed Meters Process: Clarifications and Support
Date of latest update
Type
Issue
ID
I0314
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 30 October 2026, the REC Change Panel approved an Extension to Plan for I0314 via ex-committee.
Summary
This issue seeks to solve is the gap between the documented REC Crossed Meters process and how it is being applied operationally. The aim is to ensure all parties fully understand the process, apply it consistently, and have the support necessary to achieve timely, correct resolution of Crossed Meter cases.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0314 submission form
I0314 Change Report (Proposal Plan) Approved 21.04.26
I0314 Extension to Plan V1.0 (Approved) 30.10.26
Company Name
REC Code Manager
Review status
Review required
Schedule 11 - Prepayment Arrangements 2.7
– Implemented on
Loading...
Reconciliation of Unallocatable Transactions Review
Date of latest update
Type
Change
ID
R0223
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
The process for Reconciliation of Unallocatable Transactions is set out in Section 10 of Schedule 11. During the most recent reconciliation delivery (the gas process from July 2024) several areas of improvement were identified, critically a lack of clarity regarding historic Supplier Licences and how to include or exclude them from the calculations. The Code Manager believes that this lack of clarity and past precedent would lead to material impact on one or more Party.
Change Plan
Findings from Information Request were presented at Change Issues Group
Completed
Start:
Due:
Completion:
06 Feb 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
MHHS Programme Milestone M8 (Code changes delivered)
| Included changes | Affected REC Items | |
|---|---|---|
| R0044 | MHHS Programme Changes required to Central Switching Service |
|
| R0173 | Improvements to the Theft Detection Incentive Scheme (TDIS) |
|
| R0209 | Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements |
|
| R0222 | ESME ID Update Rejections | |
| R0223 | Reconciliation of Unallocatable Transactions Review |
|
| R0241 | MHHS Incremental Changes for go live |
|
| R0259 | Update to R0173 Implementation Date | |
| R0264 | Data Specification Housekeeping | |
| R0083 | Changes to Supply Number Format for MHHS | |
| R0097 | Consequential Change for CSS Smart Meter Data Retriever Appointments |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- A review of the process with specific regard to: - Clarity within the process regarding historic Supplier Licences - Alignment between fuels - Re-introducing an independent audit.
Proposed Solution Document
Document title
Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.2025
Upload document
Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.docx
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.docx
Archive
Off
Document title
Schedule 11 - Prepayment Arrangements (R0223 - Consultation) 24.07.2025
Upload document
Schedule 11 - Prepayment Arrangements (R0223 - Consultation).docx
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Consultation) 24.07.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Consultation).docx
Archive
Off
Document title
Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025
Upload document
Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025.pdf
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025.pdf
Archive
Off
Problem Statement
During the most recent reconciliation delivery (the gas process from July 2024) several areas of improvement were identified, critically a lack of clarity regarding historic Supplier Licences and how to include or exclude them from the calculations.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0223 - Submission Form
I0223 - Information Request Responses
I0223 - Change Report (Proposal Plan) V2.0 (Approved) 20.05.2025
I0223 - Proposal Plan Update V1.0 (Approved) 20.05.2025
I0223 - Change Report (Impact Assessment) V1.0 (06.06.2025)
I0223 - Party Impact Assessment Consolidated Responses V1.0 (11.07.2025)
R0223 - Change Report (For Consultation) V1.0 (24.07.2025)
R0223 - Change Report (Final Recommendation) V2.0 (Approved) 02.09.2025
Company Name
Code Manager
Review status
Review required
Schedule 11 - Prepayment Arrangements 2.6
– Implemented on
Loading...
Schedule 11 - Prepayment Arrangements 2.5
– Implemented on
Market Participant Applicability
| Market participant | All Sections |
|---|---|
| Domestic Suppliers | Mandatory |
| Non-Domestic Suppliers | Mandatory |
| Gas Transporters | N/A |
| Distribution Network Operators | N/A |
| DCC | N/A |
| Metering Equipment Managers | N/A |
| Non-Party REC Service Users | N/A |
Loading...
Non dual-fuel Gas PSR Consumer
Date of latest update
Type
Issue
ID
I0186
Change Category
Change Path
Priority
Urgent
No
Latest Update
02/09/2025 - the Change Panel approved placing this Issue on hold while the proposer progresses a sandbox trial
Summary
Non dual-fuel Consumers who register upon the PSR, will have their PSR data flow across energy industry data flows to mean that all parties are aware of any PSR Needs Codes, allowing us all to provide equal access to our services and support. This will be achieved via the utilisation of existing processes and systems. Initially a pilot will take place for a minimum of 3 months between participating companies before extending this to the whole industry”.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The majority of domestic customers in the UK are what are called in the industry ‘dual-fuel’ - this means that with two types of energy (electricity & gas) a domestic dwelling has a single supplier ie they pay their bill to one organisation. This ‘dual-fuel’ position has supported the industry improvements to Priority Services Register (PSR) data flows by allowing previous divides to be overstepped in terms of data flows between energy types. There is however a problem which this RECC request aims to resolve. That is, where a customer who has both fuel types, also has two suppliers and they want to register upon the PSR. This was always a ‘known’ gap shared with our regulator when the many improvements were implemented across the PSR and considered to be something that would be addressed at a later date. This ‘gap’ means that without the dual-fuel link, currently data flows do not complete across energy types via the supplier data flow triggers.
Stages Selection
Stages Selection
Change Proposal Form - Non dual-fuel Gas PSR Customer
I0186 - Change Report (Proposal Plan) V1.0 (Approved) 18.02.2025
Company Name
British Gas
Review status
Review required
Formalising the Submission of PPMIP Unallocated Transaction Report (UTR) Files
Date of latest update
Type
Change
ID
R0082
Change Category
Change Path
Priority
Urgent
No
Latest Update
09/04/2024 - Due to the MHHS impact on Service Providers, the technical code freeze and any MHHS impacts on the proposed solution, the Code Manager has reconsidered the priority of R0082 and believes that should be progressed following MHHS go-live. This Change Proposal has been withdrawn, and the Code Manager will consider raising a new change at the appropriate time following MHHS with consideration of the Codes Roadmap.
Summary
This CP seeks to address the following issues regarding the Unallocated Transaction Report (UTR) files provided by PPMIPs to the Code Manager each month: 1. There is no REC requirement for PPMIPs to submit a monthly file to the Code Manager 2. PPMIPs are currently submitting files in two different file formats 3. C&C is only able to load one of the two file formats The CP has been raised to introduce a requirement in the REC for PPMIPs to provide monthly Unallocated Transaction Report (UTR) files to the Code Manager in a single file format, set out in the REC Data Specification. With this format being one that can be loaded by C&C.
Change Plan
Solution analysis and development
Completed
Start:
28 Nov 2022Due:
12 Jan 2024Completion:
11 Jan 2024Service Provider Impact Assessment start date
Completed
Start:
12 Jan 2024Due:
15 Jan 2024Completion:
15 Jan 2024Service Provider Impact Assessment close
Completed
Start:
15 Jan 2024Due:
11 Mar 2024Completion:
11 Mar 2024Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a PPMIP, I want to have clear guidance on how and when I should submit my Unallocated Transaction Report files.
- As a Supplier, I want to receive accurate Unallocated Transactions in relation to prepayment meters that are not smart meters.
- As the Code Manager, I want visibility of the Unallocated Transaction Report.
- As the EES Provider, I want to be able to efficiently upload the Unallocated Transaction Reports.
Problem Statement
PPMIPs aren’t submitting UTR files in the same format, and one of these formats cannot be loaded by the EES Provider. There is also no obligation in the REC for these reports to be provided.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0082 - Change Proposal Form
R0082 - Change Proposal Plan (Approved) 17.10.2023
R0082 Initial Assessment Report (Approved) 17.10.2023
Company Name
REC Code Manager
Review status
Review required
Schedule 11 - Prepayment Arrangements 2.4
– Implemented on
Market Participant Applicability
| Market participant | All Sections |
|---|---|
| Domestic Suppliers | Mandatory |
| Non-Domestic Suppliers | Mandatory |
| Gas Transporters | N/A |
| Distribution Network Operators | N/A |
| DCC | N/A |
| Metering Equipment Managers | N/A |
| Non-Party REC Service Users | N/A |
Loading...