Stranded RMPs in Defunct Suppliers
Date of latest update
Type
Issue
ID
I0219
Change Path
Priority
Urgent
No
Latest Update
27/02/2025 - Change is now not being merged into any other changes and will proceed as a standalone change. A potential solution has been identified, but will be discussed for potential cross code impacts
Summary
Currently within Schedule 23 a Registration can only be undertaken on RMPs with an Operational or Dormant RMP Status, and not Terminated. Terminated is a status that the RMP is set to when the Meter Point Status is no longer operational or the site is isolated. It is right that these sites are not able to be Registered as there is a risk that Suppliers could inadvertently Register such Meter Points. We do have instances where such sites are stranded in defunct Supplier portfolios - and the Supplier no longer has the capability to take the relevant action to Deactivate the Registrations. This may because the operational staff have left and the business is in administration.
Change Plan
Discussed at Technical Change Workshop
Completed
Start:
Due:
Completion:
25 Feb 2025Impacted Consumers
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue Proposal Form
Company Name
Xoserve
Review status
Review required
Removal of Facsimile as a Method of Code Communication
Date of latest update
Type
Change
ID
R0157
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Public Switched Telephone Networks (PSTN) will be switched off in December 2025 by all telecom companies and will be replaced with an Internet Protocol (IP) digital network. Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC. All communication methods referencing fax or facsimile will need to be removed and replaced with email (where this is not an existing option), unless an alternative form of communication is needed. Please note: The government have published preparatory guidance which includes migrating to IP-supported technology in advance of the planned decommissioning. UK transition from analogue to digital landlines - GOV.UK (www.gov.uk) Critical National Infrastructure (CNI) (“assets, facilities, systems, networks or processes and the essential workers that operate and facilitate them”) which is subdivided into 13 sectors including Energy, are advised to consider how they move to digital alternatives smoothly to avoid unnecessary interruption following the PSTN switch-off. Openreach's Energy Guidance Factsheet can be found in the CPs Accompanied Documents.
Change Plan
Preliminary Change Report and Consultation Issued
Completed
Start:
03 Jan 2024Due:
09 Feb 2024Completion:
09 Feb 2024Final Change Report Issued
Completed
Start:
23 Feb 2024Due:
12 Mar 2024Completion:
12 Mar 2024Responsible Committee Decision
Completed
Start:
12 Mar 2024Due:
19 Mar 2024Completion:
19 Mar 2024Appeal Window Closure
Not Started
Start:
19 Mar 2024Due:
02 Apr 2024Completion:
Consultation Close
Completed
Start:
09 Feb 2024Due:
23 Feb 2024Completion:
23 Feb 2024Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
07 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0152 | Revision to the Consolidated Metering Code of Practice (CoMCoP) |
|
| R0157 | Removal of Facsimile as a Method of Code Communication |
|
| R0191 | Introduction of SLA for Supplier De-Registration on Disconnected Meters |
|
| R0205 | Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches | |
| R0212 | Protecting Crimestoppers and their Contacts | |
| R0215 | Schedule 30 Switch Meter Reading Problems - Rejections and Timings |
|
| R0060 | ERDS Service Definition timezone correction |
|
| R0232 | Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) | |
| R0243 | Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership |
|
| R0248 | REC Changes to tie in with DCP451 - Suspending Registrations |
|
| R0254 | Non-Domestic Change of Occupier Reporting (R0155 Solution) | |
| R0255 | Terms of Reference Updates | |
| R0257 | Change to REC for Data processing outside of EEA | |
| R0263 | Sharing Confirmed Energy Theft Data with the BSCCo |
|
| R0269 | Schedule 5 – Change Management: Clarity and Typographical Review |
|
| R0279 | Housekeeping November 2025 |
|
| R0227 | Domestic Elective HH Switching |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- All communication methods referencing fax or facsimile will need to be removed and replaced with email
Proposed Solution Document
Document title
Existing References to Fax and "e-mail" in the REC (January 2024)
Upload document
Existing Fax References in the REC.pdf
Archive
Off
Document title
R00157 - Legal Text Changes (All Affected REC Products and Documents)
Upload document
R00157 - Draft Legal Text Changes.zip
Archive
Off
Problem Statement
Existing fax machines that are incompatible with new all IP digital networks will become obsolete and no longer capable of meeting Code Communications as prescribed in the REC
Stages Selection
CP Form - Removal of a Fax as a Code Communication method
R0157 - Change Proposal Plan V1.0 (Approved) 30.01.2024
R0157 - Initial Assessment Report V1.0 (Approved) 30.01.2024
R0157 - Consolidated Consultation Responses
R0157 - Preliminary Change Report V1.0 (For Consultation) 09.02.2024
R0157 - Final Change Report V2.0 (Post-Vote) 19.03.2024
Open Reach Energy Industry Factsheet
Company Name
REC Code Manager
Review status
Review required
Make Shipper NExA values available on the GES portal
Date of latest update
Type
Change
ID
R0088
Change Path
Priority
Urgent
No
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Summary
This Change Proposal seeks to deliver the consequential REC changes for Uniform Network Code (UNC) Modification 0701 Aligning Capacity Booking under the UNC and arrangements set out in relevant NExAs. Modification (MOD) 0701 will ensure that the daily capacity allowed by the Network Exit Agreement (NExA) and that permitted by the UNC are aligned.
Change Plan
Initial Assessment and Change Proposal Plan issued
Completed
Start:
16 Jan 2023Due:
24 Mar 2023Completion:
24 Mar 2023Initial Assessment Report and Change Plan approved
Completed
Start:
24 Mar 2023Due:
04 Apr 2023Completion:
04 Apr 2023Service Provider Impact Assessment
Completed
Start:
04 Apr 2023Due:
25 Apr 2023Completion:
24 Apr 2023Party Impact Assessment
Completed
Start:
25 Apr 2023Due:
31 May 2023Completion:
31 May 2023Preliminary Change Report published
Completed
Start:
31 May 2023Due:
16 Jun 2023Completion:
16 Jun 2023Consultation
Completed
Start:
16 Jun 2023Due:
21 Jul 2023Completion:
21 Jul 2023Final Change Report published
Completed
Start:
21 Jul 2023Due:
18 Aug 2023Completion:
18 Aug 2023Responsible Committee decision
Completed
Start:
18 Aug 2023Due:
30 Aug 2023Completion:
30 Aug 2023Status
Implementation Date
03 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0110 | A review of Supplier access to data on GES | |
| R0138 | Combined progression of Change Proposals R0058, R0104 and R0129 | |
| R0140 | Housekeeping amendments | |
| R0059 | Maintenance of Qualification Schedule Change |
|
| R0088 | Make Shipper NExA values available on the GES portal | |
| R0017 | Invalid Requests for Site Technical Details |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer, where I have entered a bi-lateral NExA with the relevant Transporter, I want my Shipper and Transporter to have access to all the data they need when capacity referrals to the Gas Transporters are required.
- As a Gas Transporter, I want the details of the NExA to be held in GES, to increase visibility of the existence of the NExA and to provide details of the offtake parameters.
- As a Gas Shipper, I need to understand both that a NExA exists, and that I have visibility of the offtake parameters relative to the site, so that I can ensure that I take the necessary actions to ensure the Consumer has the appropriate booked Supply Point Capacity.
Proposed Solution Document
Document title
R0088 Gas DAM v3.1 at FCR (18.08.2023)
Upload document
R0088 Draft V3.1 GES Data Access Matrix at FCR.xlsx
Archive
Off
Problem Statement
XRN 5186 will make updates to the GES to implement the solution for UNC MOD 701. Following Ofgem’s decision to approve MOD 701, a REC Change Proposal is required to make changes to the REC DAM to enable the delivery of the full cross code solution.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0088 - Initial Assessment Report v1.0 (Approved) 04.04.2023
R0088 - Preliminary Change Report (Post-Vote) 28.06.2023
R0088 - Change Proposal Plan v1.0 (Approved) 04.04.2023
R0088 - Final Change Report v2.0 (Approved) 30.08.2023
R0088 - Final Change Report v1.0 (Pre-Vote) 18.08.2023
Company Name
Xoserve
Review status
Review required