Changes to allow DNOs to reinstate disconnected MPANs
Solution Development
Start:
17 Feb 2023Due:
26 Jan 2024Completion:
26 Jan 2024- As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
- As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Enabling Software Product Qualification
Creating a Meter Operator Agent and MOCoP Installer
Solution analysis and development
Start:
22 Aug 2022Due:
14 Jul 2023Completion:
13 Jul 2023Service Impact assessment commenced
Start:
14 Jul 2023Due:
14 Jul 2023Completion:
14 Jul 2023Impact Assessment Period Ended
Start:
09 Oct 2023Due:
03 Nov 2023Completion:
03 Nov 2023Preliminary Change Report issued
Start:
03 Nov 2023Due:
24 Nov 2023Completion:
24 Nov 2023Consultation issued
Start:
24 Nov 2023Due:
07 Dec 2023Completion:
07 Dec 2023Final Change report issued
Start:
07 Dec 2023Due:
26 Jan 2024Completion:
26 Jan 2024REC Change Panel decision
Start:
26 Jan 2024Due:
06 Feb 2024Completion:
06 Feb 2024Appeal Window closed
Start:
06 Feb 2024Due:
20 Feb 2024Completion:
20 Feb 2024Draft Legal Text Changes (Including Legal Review)
Start:
11 Aug 2023Due:
15 Sep 2023Completion:
15 Sep 2023Service Provider Impact Assessment Completed
Start:
14 Jul 2023Due:
11 Aug 2023Completion:
11 Aug 2023Impact Assessment Period Started
Start:
15 Sep 2023Due:
09 Oct 2023Completion:
06 Oct 202328 June 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0043 | Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms |
|
| R0158 | Amendment to the ‘Supplier Registration Report (MAP)’ report methodology | |
| R0160 | Electricity Supply to Hydrogen Electrolysers |
|
| R0064 | Creating a Meter Operator Agent and MOCoP Installer |
|
| R0070 | Provision of Enduring Test Environments |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an electricity MEM, I want to be clear on the obligations I need to meet, based on the type of metering activity I complete. I want to meet my obligations efficiently and effectively and without the need to seek additional input/advice from the Code Manager.
- As the Code Manager, I want to be able to differentiate between electricity MEMs based on the type of activity they are responsible for and their interaction with central systems, so that I can engage appropriately. I need to be clear on the obligations that each MEM should be meeting and the performance reporting that should be provided.
Resolution of invalid CSS data by Data Owners
Solution Analysis and Development
Start:
22 Aug 2022Due:
15 Aug 2023Completion:
15 Aug 2023Service Provider Impact Assessment Due
Start:
15 Aug 2023Due:
19 Oct 2023Completion:
19 Oct 2023- As a Consumer, I want data relating to my energy supply to be accurate, so that I can have a consistent and faultless switching experience. As a Consumer, I want any data issues related to my switch to be resolved quickly and by the party responsible, to ensure a fast and efficient switching experience.
- As a DNO, I want my service level requirements to be reflective of my data ownership responsibilities, so that data queries can be resolved more efficiently. As the CSS Service Desk provider, I want my tickets to be allocated to the most appropriate party able to resolve them.
Revised Implementation Date for R0011
Party Impact Assessment Issued
Start:
25 Mar 2022Due:
08 Apr 2022Completion:
08 Apr 2022Preliminary Change Report Issued
Start:
08 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Consultation Issued
Start:
29 Apr 2022Due:
29 Apr 2022Completion:
29 Apr 2022Final Change Report Issued
Start:
29 Apr 2022Due:
13 May 2022Completion:
13 May 2022Responsible Committee Decision
Start:
13 May 2022Due:
17 May 2022Completion:
17 May 202201 June 2022
- As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
- As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Invalid Requests for Site Technical Details
ANALYSIS AND ENGAGEMENT WITH BSC
Start:
01 Nov 2022Due:
30 Nov 2022Completion:
30 Nov 2022PRESENT UPDATED CHANGE PROPOSAL PLAN TO CHANGE PANEL
Start:
22 Nov 2021Due:
01 Nov 2022Completion:
01 Nov 2022Part Impact Assessment Issued
Start:
30 Nov 2022Due:
13 Jan 2023Completion:
13 Jan 2023Party Impact Assessment Closes
Start:
13 Jan 2023Due:
03 Feb 2023Completion:
03 Feb 2023Present Updated Plan to Change Panel
Start:
03 Feb 2023Due:
07 Feb 2023Completion:
07 Feb 2023Preliminary Change Report issued
Start:
07 Feb 2023Due:
31 Mar 2023Completion:
31 Mar 2023Metering Expert Panel approval of PCR
Start:
31 Mar 2023Due:
12 Apr 2023Completion:
12 Apr 2023Consultation start date (aligned with BSC)
Start:
12 Apr 2023Due:
14 Apr 2023Completion:
14 Apr 2023Consultation end date (aligned with BSC)
Start:
14 Apr 2023Due:
08 May 2023Completion:
08 May 2023Final Change Report issued
Start:
08 May 2023Due:
26 May 2023Completion:
26 May 2023Metering Expert Panel decision
Start:
26 May 2023Due:
07 Jun 2023Completion:
07 Jun 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0110 | A review of Supplier access to data on GES | |
| R0138 | Combined progression of Change Proposals R0058, R0104 and R0129 | |
| R0140 | Housekeeping amendments | |
| R0059 | Maintenance of Qualification Schedule Change |
|
| R0088 | Make Shipper NExA values available on the GES portal | |
| R0017 | Invalid Requests for Site Technical Details |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer I want my existing or new meter to be read regularly to ensure I receive accurate bills.
- As a Distribution Network Operator I want to receive appropriate Requests for Site Technical Details. As a Distribution Network Operator I want the difference between my obligations and best practice to be clear in relation to provision of Site Technical Details for sites with and without Measurement Transformers.
- As a Metering Equipment Manager I want to be provided with Site Technical Details for all relevant sites so I can correctly install, commission and maintain the Metering Equipment.
Housekeeping amendments to REC V2
Initial Assessment Report published
Start:
04 Oct 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
22 Oct 2021Completion:
22 Oct 2021Change Panel review
Start:
22 Oct 2021Due:
16 Nov 2021Completion:
16 Nov 2021Consultation starts
Start:
16 Nov 2021Due:
17 Nov 2021Completion:
17 Nov 2021Consultation ends
Start:
17 Nov 2021Due:
08 Dec 2021Completion:
08 Dec 2021Final Change Report issued
Start:
08 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Change Panel decision
Start:
10 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 202131 January 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0020 | ETTOS Report Dissemination |
|
| R0012 | Housekeeping amendments to REC V2 |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
- As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.
Reporting of Additional EMR Backing Data to Suppliers
Initial Assessment Report published
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Start:
19 Oct 2021Due:
12 Nov 2021Completion:
12 Nov 2021Technical Expert Panel review
Start:
12 Nov 2021Due:
24 Nov 2021Completion:
24 Nov 2021Consultation starts
Start:
24 Nov 2021Due:
30 Nov 2021Completion:
29 Nov 2021Consultation ends
Start:
30 Nov 2021Due:
21 Dec 2021Completion:
21 Jan 2022Final Change Report issued
Start:
21 Dec 2021Due:
14 Jan 2022Completion:
14 Jan 2022Technical Expert Panel decision
Start:
14 Jan 2022Due:
26 Jan 2022Completion:
26 Jan 202230 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Market Participant, I need to be able to validate EMRS invoices and credits without having to request additional supporting data.
- As EMR Settlement Ltd, I need to have an efficient mechanism in place that enables me to provide Market Participants with all the relevant data that they need to validate their invoices and credit notes, to reduce/remove the need for Market Participants to contact the service desk for additional information.