Changes to allow DNOs to reinstate disconnected MPANs

Date of latest update
Type
Change
ID
R0095
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
The Code Manager have taken R0095 off of hold and published an Information Request for R0095 on 22 October 2026, this is open to responses until 13 November 2026.
Summary
When Meter Point Administration Numbers (MPANs) are erroneously disconnected, they cannot be reinstated. As a result, Consumers suffer billing issues and Registered Suppliers cannot settle against the disconnected MPAN. This change seeks to introduce a mechanism to restore erroneously disconnected MPANs.
Proposer
Leanne Yates
Change Plan

Solution Development

Completed

Start:

17 Feb 2023

Due:

26 Jan 2024

Completion:

26 Jan 2024
Impacted Consumers
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I do not want the erroneous disconnection of my MPAN to affect the continuity of my supply contract and billing arrangements.
  2. As a DNO, I want to be able to reverse erroneous disconnections with no lasting effect so that I don’t need to create a new MPAN to resolve the issue, thereby avoiding DUoS payment collection issues. 2 - As a Supplier, I want to be able to reverse erroneous disconnections with no lasting effect so that I can correctly bill my consumers. 3 - As the CSS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate. 4 - As MPRS, I want users to be able to effectively resolve discrepancies, so that industry data for their portfolio is accurate.
Problem Statement
When MPANs are incorrectly identified and targeted for disconnection, the RMP will be erroneously terminated following receipt of Termination Market Messages by the CSS. This process is irreversible once triggered, meaning that there is no mechanism to restore the MPAN as it was previously. This results in a poor Consumer experience, and settlement misbalancing for Registered Suppliers. Currently, there is no mechanism to mitigate the negative impact on Registered Suppliers/DNO and Consumers.
SME
SME Role
Lead Technical Analyst
R0095 - Change Proposal form downloadable version 17.02.2023
R0095 Change Proposal Plan v1.0 (Approved) - 20.09.23
R0095 Initial Assessment Report v1.0 (Approved) - 20.09.2023
R0095 - Change Proposal Re-Plan (Approved) v1.0-13.12.23
Company Name
-
Review status
Review required

Enabling Software Product Qualification

Date of latest update
Type
Change
ID
R0075
Priority
Urgent
No
Latest Update
26/03/2024 - Adoption window closed and change fully withdrawn.
Summary
This change proposes that specific software product sets should be allowed to complete qualification independently of any specific REC Party. The product set would then be subject to its own maintenance of qualification by following the REC Maintenance of Qualification processes. Any REC Party using that product set would then be able to ‘place reliance’ on this qualification as part of their own market entry and annual maintenance statements.
Proposer
Elaine Eyles
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0075 - Change Proposal Form
Company Name
-
Review status
Review required

Creating a Meter Operator Agent and MOCoP Installer

Date of latest update
Type
Change
ID
R0064
Change Category
Change Path
Priority
Urgent
No
Latest Update
28/06/2024 - Change implemented as part of the June 2024 REC Release
Summary
This Change Proposal seeks to clarify the obligations of each type of metering provider by reintroducing the distinction between Meter Operator Agents and MOCOPA Meter Installers which was removed by Retail Code Consolidation. At Retail Code Consolidation these organisations were merged into a new category, Metering Equipment Managers, which also included gas metering providers. Whilst both types of organisation can provide metering services, not all MEM obligations in the REC apply to both organisations.
Proposer
Anton Moden
Change Plan

Solution analysis and development

Completed

Start:

22 Aug 2022

Due:

14 Jul 2023

Completion:

13 Jul 2023

Service Impact assessment commenced

Completed

Start:

14 Jul 2023

Due:

14 Jul 2023

Completion:

14 Jul 2023

Impact Assessment Period Ended

Completed

Start:

09 Oct 2023

Due:

03 Nov 2023

Completion:

03 Nov 2023

Preliminary Change Report issued

Completed

Start:

03 Nov 2023

Due:

24 Nov 2023

Completion:

24 Nov 2023

Consultation issued

Completed

Start:

24 Nov 2023

Due:

07 Dec 2023

Completion:

07 Dec 2023

Final Change report issued

Completed

Start:

07 Dec 2023

Due:

26 Jan 2024

Completion:

26 Jan 2024

REC Change Panel decision

Completed

Start:

26 Jan 2024

Due:

06 Feb 2024

Completion:

06 Feb 2024

Appeal Window closed

Completed

Start:

06 Feb 2024

Due:

20 Feb 2024

Completion:

20 Feb 2024

Draft Legal Text Changes (Including Legal Review)

Completed

Start:

11 Aug 2023

Due:

15 Sep 2023

Completion:

15 Sep 2023

Service Provider Impact Assessment Completed

Completed

Start:

14 Jul 2023

Due:

11 Aug 2023

Completion:

11 Aug 2023

Impact Assessment Period Started

Completed

Start:

15 Sep 2023

Due:

09 Oct 2023

Completion:

06 Oct 2023
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.11.0_Superseded
Included changes Affected REC Items
R0043 Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 12 - Data Access
  • Data Access Matrix (Electricity)
  • Data Item Catalogue
  • Market Message Catalogue
R0158 Amendment to the ‘Supplier Registration Report (MAP)’ report methodology
R0160 Electricity Supply to Hydrogen Electrolysers
  • Schedule 1 - Interpretations and Definitions
R0064 Creating a Meter Operator Agent and MOCoP Installer
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 9 - Qualification and Maintenance
R0070 Provision of Enduring Test Environments
  • Schedule 1 - Interpretations and Definitions
  • Schedule 5 - Change Management
  • Schedule 26 - Switching Service Management
  • Schedule 25 - Central Switching Service

Documents

Name Version Last updated Actions
159.49 KB
Version 1.0 - 16 Nov 2026 PDF - 159.49 KB
1.0 16 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an electricity MEM, I want to be clear on the obligations I need to meet, based on the type of metering activity I complete. I want to meet my obligations efficiently and effectively and without the need to seek additional input/advice from the Code Manager.
  2. As the Code Manager, I want to be able to differentiate between electricity MEMs based on the type of activity they are responsible for and their interaction with central systems, so that I can engage appropriately. I need to be clear on the obligations that each MEM should be meeting and the performance reporting that should be provided.
Proposed Solution Document
Document title
R0064 - DRAFT legal text 24.11.2023
Upload document
R0064 - Draft Legal Text for Consultation.zip
Archive
Off
Document title
R0064 - Roles Version F for Impact Assessment 4.10.2023
Upload document
R0064 - Roles Version F for Impact Assessment 4.10.2023 (2).pptx
Archive
Off
Problem Statement
The REC currently groups all electricity metering providers within the MEM category. Previously, under the Master Registration Agreement (MRA) they were either classified as Meter Operator Agent or MOCOPA Meter Installers. Not all MEM obligations in the REC are intended to apply to both types of organisations. This can result in ambiguity on the obligations set out in the REC that need to be met by the different types of electricity MEM, not being able to target information to REC Parties appropriately and MEMs not being clear on their new entrant or Maintenance of Qualification obligations.
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0064 - Change Proposal Form
R0064 - Change Proposal Plan v1.0 (Approved)
R0064 - Initial Assessment Report v1.0 (Approved)
R0064 - Change Proposal Plan v2.0 (Approved) 21.02.2023
R0064 - Change Proposal Plan v3.0 (Approved) 23.6.2023
R0064 - Change Proposal Plan v4.0 (Approved) 14.8.2023
R0064 - Change Proposal Plan v5.0 (Approved) 14.09.2023
R0064 - Change Proposal Plan v6.0 (Approved) 10.11.2023
Consolidated Impact Assessment Responses 29.11.2023
R0064 - Preliminary Change Report - V1.1 (Approved) 05.12.2023
R0064 - Consolidated Consultation Responses
R0064 - Final Change Report v1.0 (Approved)
Company Name
-
Review status
Review required

Resolution of invalid CSS data by Data Owners

Date of latest update
Type
Change
ID
R0061
Change Category
Change Path
Priority
Urgent
No
Latest Update
04 March 2024 - Change has been withdrawn following implementation of a solution outside of the REC Change Process. 10WD window to adopt change will close on 18 March 2024.
Summary
Data is sent via the Supplier or MEM to update MPRS, which is then sent to CSS. If the data is considered invalid at CSS, an error is returned to MPRS. MPRS is the conduit of data from the Suppliers & MEMs to CSS, and ERDAs are not responsible for the data, therefore only the supplier/MEM can correct the data. The incidents must be put on hold until the owner of the data corrects the issue, this is to prevent SLA breaches. SLAs does not apply to the Supplier/MEM explicitly, so the incidents remain in the DNOs/IDNOs queue with the need to chase every few days to prevent the incident being closed. The responsibility for the incidents should be on the data owners (Suppliers/MEMs).
Proposer
Elise Handy
Change Plan

Solution Analysis and Development

Completed

Start:

22 Aug 2022

Due:

15 Aug 2023

Completion:

15 Aug 2023

Service Provider Impact Assessment Due

Completed

Start:

15 Aug 2023

Due:

19 Oct 2023

Completion:

19 Oct 2023
Status
Implementation Status
Date Raised
REC Decision Maker
Lead Analyst
Lydia Bentley
Solution Development
Proposed solution summary
  1. As a Consumer, I want data relating to my energy supply to be accurate, so that I can have a consistent and faultless switching experience. As a Consumer, I want any data issues related to my switch to be resolved quickly and by the party responsible, to ensure a fast and efficient switching experience.
  2. As a DNO, I want my service level requirements to be reflective of my data ownership responsibilities, so that data queries can be resolved more efficiently. As the CSS Service Desk provider, I want my tickets to be allocated to the most appropriate party able to resolve them.
Proposed Solution Document
Document title
R0061 Solution - Service Desk Guidance Article
Archive
Off
Problem Statement
DNO/iDNOs are obligated to resolve data mismatches identified by the CSS during the switch process. However, they are unable to do so in cases where the Supplier/MEM owns data required to resolve the mismatch. Tickets assigned to the DNO (via MPRS) are therefore not going to the party best placed to resolve them, resulting in DNOs chasing the incident resolution every few days to prevent them being closed incorrectly.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0061 - Change Proposal Form
R0061 - Initial Assessment Report v1.0 (Approved) - 18.07.2023
R0061 - Change Proposal Plan v1.0 (Approved) - 18.07.2023
R0061 Change Proposal Re-Plan (Approved) v1.0 - 19.10.23
Company Name
St Clements Services
Review status
Review required

Revised Implementation Date for R0011

Date of latest update
Type
Change
ID
R0039
Change Category
Change Path
Priority
Urgent
Yes
Latest Update
-
Summary
-
Proposer
patrick.bibby
Change Plan

Party Impact Assessment Issued

Completed

Start:

25 Mar 2022

Due:

08 Apr 2022

Completion:

08 Apr 2022

Preliminary Change Report Issued

Completed

Start:

08 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Consultation Issued

Completed

Start:

29 Apr 2022

Due:

29 Apr 2022

Completion:

29 Apr 2022

Final Change Report Issued

Completed

Start:

29 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Responsible Committee Decision

Completed

Start:

13 May 2022

Due:

17 May 2022

Completion:

17 May 2022
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Live
EMAR Version 01.06.2022_live
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Market Participant, I need the industry Market Message/Data Specification to be implemented by all Parties at the same time so that I am able to validate EMRS invoices and credits without having to request additional supporting data or without my Market Messages failing.
  2. As LCCC I need to delay the implementation of R0011 so that changes to industry Market Message/Data Specification can be implemented by all Parties at the same time so that industry Market Messages don’t fail validation between Parties.
Problem Statement
Following a review of its delivery pipeline, the LCCC has determined it is unable to deploy the changes required in time for the current approved implementation date of 04 November 2022. In order to communicate a revised date and to limit the impacts to industry parties and delivery partners, this change needs to be assessed as a matter of urgency.
R0039 Change Proposal Form
R0039 - Change Proposal Plan v1.0 (Approved)
R0039 Initial Assessment Report v1.0
R0039 Preliminary Change Report v1.0
R0039 - Final Change Report v2.0
Company Name
Low Carbon Contracts Company
Review status
Review required

Invalid Requests for Site Technical Details

Date of latest update
Type
Change
ID
R0017
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
03/11/23 - This change was implemented on 03 November 2023 as part of the November 2023 REC Release
Summary
This Change Proposal seeks to provide clarity to Distribution Network Operators (DNOs) and Metering Equipment Managers (MEMs) on the process for requesting and sending Site Technical Details as part of Meter Asset Installation, Switch or Change of Agent processes.
Proposer
Elaine Carr
Change Plan

ANALYSIS AND ENGAGEMENT WITH BSC

Completed

Start:

01 Nov 2022

Due:

30 Nov 2022

Completion:

30 Nov 2022

PRESENT UPDATED CHANGE PROPOSAL PLAN TO CHANGE PANEL

Completed

Start:

22 Nov 2021

Due:

01 Nov 2022

Completion:

01 Nov 2022

Part Impact Assessment Issued

Completed

Start:

30 Nov 2022

Due:

13 Jan 2023

Completion:

13 Jan 2023

Party Impact Assessment Closes

Completed

Start:

13 Jan 2023

Due:

03 Feb 2023

Completion:

03 Feb 2023

Present Updated Plan to Change Panel

Completed

Start:

03 Feb 2023

Due:

07 Feb 2023

Completion:

07 Feb 2023

Preliminary Change Report issued

Completed

Start:

07 Feb 2023

Due:

31 Mar 2023

Completion:

31 Mar 2023

Metering Expert Panel approval of PCR

Completed

Start:

31 Mar 2023

Due:

12 Apr 2023

Completion:

12 Apr 2023

Consultation start date (aligned with BSC)

Completed

Start:

12 Apr 2023

Due:

14 Apr 2023

Completion:

14 Apr 2023

Consultation end date (aligned with BSC)

Completed

Start:

14 Apr 2023

Due:

08 May 2023

Completion:

08 May 2023

Final Change Report issued

Completed

Start:

08 May 2023

Due:

26 May 2023

Completion:

26 May 2023

Metering Expert Panel decision

Completed

Start:

26 May 2023

Due:

07 Jun 2023

Completion:

07 Jun 2023
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.6.0_Superseded
Included changes Affected REC Items
R0110 A review of Supplier access to data on GES
R0138 Combined progression of Change Proposals R0058, R0104 and R0129
R0140 Housekeeping amendments
R0059 Maintenance of Qualification Schedule Change
  • Schedule 1 - Interpretations and Definitions
  • Schedule 9 - Qualification and Maintenance
R0088 Make Shipper NExA values available on the GES portal
R0017 Invalid Requests for Site Technical Details
  • Schedule 14 - Metering Operations
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
222.91 KB
Version 1.0 - 02 Nov 2026 PDF - 222.91 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer I want my existing or new meter to be read regularly to ensure I receive accurate bills.
  2. As a Distribution Network Operator I want to receive appropriate Requests for Site Technical Details. As a Distribution Network Operator I want the difference between my obligations and best practice to be clear in relation to provision of Site Technical Details for sites with and without Measurement Transformers.
  3. As a Metering Equipment Manager I want to be provided with Site Technical Details for all relevant sites so I can correctly install, commission and maintain the Metering Equipment.
Proposed Solution Document
Document title
R0017 - Schedule 14 - Metering Operations (Final Approved) v1.0 08.06.2023
Upload document
R0017 - Schedule 14 - Metering Operations (Final Approved) v1.0 08.06.2023.pdf
Archive
Off
Document title
R0017 - Schedule 14 - Metering Operations (For FCR) v1.0 26.05.2023
Upload document
R0017 - Schedule 14 - Metering Operations (For FCR) v1.0 26.05.2023 (1).docx
Archive
Off
Document title
R0017 - Schedule 14 - Metering Operations (For PCR) - 31.03.2023
Upload document
R0017 - Schedule 14 - Metering Operations (For PCR) v1.0 - 31.03.2023.docx
Archive
Off
Document title
R0017 Draft Legal Text (for Party IA) 13.01.23
Upload document
Schedule 14 - Metering Operations - R0017 v5 REDLINED.docx
Archive
Off
Document title
Link to EMAR Change Set
Archive
Off
Problem Statement
Distribution Network Operators (DNOs) have reported that they are receiving a high volume of requests for Site Technical Details for Domestic and Microbusiness sites following a Switch or Change of Agent, resulting in increased workload for DNOs to validate and process these requests. It is not clear if these requests are all necessary or required by the MEMs and justify the effort required by the DNO to process these requests.
SME
SME Role
Lead Technical Analyst
R0017 - Initial Assessment Report v1.0 (Approved)
R0017 - Change Proposal Plan v7.0 (Approved) 09.03.2023
R0017 - Consolidated Impact Assessment Responses v1.0 - 23.02.2023
R0017 - Preliminary Change Report v2.0 (Approved) 14.04.2023
R0017 - NON-CONFIDENTIAL Consolidated consultation responses v1.0 26.05.2023
R0017 - Final Change Report v2.0 (Post-Vote) 08.06.2023
Company Name
SPEN
Review status
Review required

Housekeeping amendments to REC V2

Date of latest update
Type
Change
ID
R0012
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
Jonathan Hawkins
Change Plan

Initial Assessment Report published

Completed

Start:

04 Oct 2021

Due:

12 Oct 2021

Completion:

12 Oct 2021

Change Panel review

Completed

Start:

12 Oct 2021

Due:

19 Oct 2021

Completion:

19 Oct 2021

Preliminary Change Report issued

Completed

Start:

19 Oct 2021

Due:

22 Oct 2021

Completion:

22 Oct 2021

Change Panel review

Completed

Start:

22 Oct 2021

Due:

16 Nov 2021

Completion:

16 Nov 2021

Consultation starts

Completed

Start:

16 Nov 2021

Due:

17 Nov 2021

Completion:

17 Nov 2021

Consultation ends

Completed

Start:

17 Nov 2021

Due:

08 Dec 2021

Completion:

08 Dec 2021

Final Change Report issued

Completed

Start:

08 Dec 2021

Due:

10 Dec 2021

Completion:

10 Dec 2021

Change Panel decision

Completed

Start:

10 Dec 2021

Due:

21 Dec 2021

Completion:

21 Dec 2021
Impacted Consumers
Impacted REC Services
Status
Implementation Date
Status Superseded
EMAR Version REC V2.2.0_SUPERSEDED
Included changes Affected REC Items
R0020 ETTOS Report Dissemination
  • Schedule 7 - Energy Theft Reduction
R0012 Housekeeping amendments to REC V2
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 11 - Prepayment Arrangements
  • Schedule 6 - Performance Assurance
  • Schedule 8 - Unbilled Energy Code of Practice
  • ASPCoP (since removed)
  • Schedule 12 - Data Access
  • Schedule 10 - Charging Methodology
  • Standards Definition Document
  • Data Item Catalogue
  • Market Message Catalogue

Documents

Name Version Last updated Actions
198.05 KB
Version 1.0 - 02 Nov 2026 PDF - 198.05 KB
1.0 02 Nov 2026
255.31 KB
Version 1.0 - 02 Nov 2026 DOCX - 255.31 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
  2. As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.
Proposed Solution Document
Document title
Legal Text (Tracked Changes)
Upload document
Legal Drafting (3).zip
Archive
Off
Document title
Link to Change Set (Clean)
Archive
Off
Problem Statement
The implementation of REC V2, as part of the Retail Code Consolidation SCR, was due to consolidate the existing provisions in other codes into the REC on a like-for-like basis. The Code Manager has identified that there were changes made to previous codes that weren’t reflected in the REC V2 drafting that was implemented. This means that the current processes being operated by industry parties are not reflected in the REC. REC Party's and Service Providers rely on the REC to provide a consistent baseline to ensure the industry operate in an effective and interoperable way. There are currently inconsistencies between the drafting of the REC, and the processes operated by REC Party's and Service Providers, which could cause issues in the effective operation and assurance of the retail energy market.
R0012 - Change Proposal Plan v1.0 (Approved)
R0012 - Initial Assessment Report v1.0 (Approved)
R0012 - Preliminary Change Report v1.0
R0012 - Preliminary Change Report v2.0 (Approved)
R0012 - Final Change Report v1.0 (Pre-Vote)
R0012 - Final Change Report v2.0 (Post-Vote)
Company Name
REC Code Manager
Review status
Review required

Reporting of Additional EMR Backing Data to Suppliers

Date of latest update
Type
Change
ID
R0011
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/06/2023 - This change was implemented on 30 June 2023 as part of the June 2023 REC Release
Summary
The aim of this proposal is to reduce the extra assistance required by Electricity Market Reform (EMR) parties in the invoice validation by updating the backing data within the Market Messages to align to what is being invoiced. The associated Market Messages should be structured and named in line with the actual output of Settlement systems to facilitate validation of Capacity Market (CM) Scheme and the Contracts for Difference (CfD) financial settlement.
Proposer
Gemma Dixon
Change Plan

Initial Assessment Report published

Completed

Start:

08 Sep 2021

Due:

12 Oct 2021

Completion:

12 Oct 2021

Change Panel review

Completed

Start:

12 Oct 2021

Due:

19 Oct 2021

Completion:

19 Oct 2021

Preliminary Change Report issued

Completed

Start:

19 Oct 2021

Due:

12 Nov 2021

Completion:

12 Nov 2021

Technical Expert Panel review

Completed

Start:

12 Nov 2021

Due:

24 Nov 2021

Completion:

24 Nov 2021

Consultation starts

Completed

Start:

24 Nov 2021

Due:

30 Nov 2021

Completion:

29 Nov 2021

Consultation ends

Completed

Start:

30 Nov 2021

Due:

21 Dec 2021

Completion:

21 Jan 2022

Final Change Report issued

Completed

Start:

21 Dec 2021

Due:

14 Jan 2022

Completion:

14 Jan 2022

Technical Expert Panel decision

Completed

Start:

14 Jan 2022

Due:

26 Jan 2022

Completion:

26 Jan 2022
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.5.0_Superseded
Included changes Affected REC Items
R0101 Revision of the Implementation Date and approved solution for R0021
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0102 Revision of the approved solution for R0032
  • Data Item Catalogue
  • Market Message Catalogue
R0114 Housekeeping amendments
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 2 - REC Transition Schedule
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
R0015 Remote communication obligations for electricity Advanced Meters
  • Schedule 14 - Metering Operations
R0010 New Meter Types for Auxiliary Proportional Controllers (APCs)
  • Data Item Catalogue
  • Market Message Catalogue
R0011 Reporting of Additional EMR Backing Data to Suppliers
  • Data Item Catalogue
  • Market Message Catalogue
R0021 Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier
  • MOCoPA (since removed)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
R0030 Erroneous Transfer Cancellations
  • Schedule 1 - Interpretations and Definitions
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Data Item Catalogue
  • Market Message Catalogue
R0066 Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change)
R0032 New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS)
  • Data Item Catalogue
  • Market Message Catalogue
R0090 Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text

Documents

Name Version Last updated Actions
1.0 02 Nov 2026
4.64 MB
Version 1.0 - 02 Nov 2026 PPTX - 4.64 MB
1.0 02 Nov 2026
199.58 KB
Version 1.0 - 02 Nov 2026 PDF - 199.58 KB
1.0 02 Nov 2026
124.69 KB
Version 1.0 - 02 Nov 2026 PDF - 124.69 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Market Participant, I need to be able to validate EMRS invoices and credits without having to request additional supporting data.
  2. As EMR Settlement Ltd, I need to have an efficient mechanism in place that enables me to provide Market Participants with all the relevant data that they need to validate their invoices and credit notes, to reduce/remove the need for Market Participants to contact the service desk for additional information.
Proposed Solution Document
Document title
R0011 Tracked Changes 08.03.2023
Upload document
R0011 Tracked Changes 08.03.2023.zip
Archive
Off
Document title
Link to EMAR Change Set
Archive
Off
Problem Statement
There is no method for Suppliers and Generators to validate their invoices based on the data currently provided within the relevant Market Messages. Parties are able to request all relevant data from EMRS; however, this is time consuming for Parties, EMRS and LCCC/ESC
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
R0011 - Change Proposal Plan v1.0 (Approved)
R0011 – Initial Assessment Report v1.0 (Approved)
MRA SPF 107 - IA Response Summary
R0011 - Preliminary Change Report v2.0 (Approved)
R0011 - Final Change Report v2.0
Company Name
-
Review status
Review required