Housekeeping amendments to REC V2
Date of latest update
Type
Change
ID
R0012
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Change Plan
Initial Assessment Report published
Completed
Start:
04 Oct 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Completed
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Preliminary Change Report issued
Completed
Start:
19 Oct 2021Due:
22 Oct 2021Completion:
22 Oct 2021Change Panel review
Completed
Start:
22 Oct 2021Due:
16 Nov 2021Completion:
16 Nov 2021Consultation starts
Completed
Start:
16 Nov 2021Due:
17 Nov 2021Completion:
17 Nov 2021Consultation ends
Completed
Start:
17 Nov 2021Due:
08 Dec 2021Completion:
08 Dec 2021Final Change Report issued
Completed
Start:
08 Dec 2021Due:
10 Dec 2021Completion:
10 Dec 2021Change Panel decision
Completed
Start:
10 Dec 2021Due:
21 Dec 2021Completion:
21 Dec 2021Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
31 January 2022
| Included changes | Affected REC Items | |
|---|---|---|
| R0020 | ETTOS Report Dissemination |
|
| R0012 | Housekeeping amendments to REC V2 |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
- As an Energy Consumer, I need Energy Companies to operate consistent processes, to ensure my energy supply is managed efficiently and to retain my trust in the functioning of the energy market.
- As a REC Party, I need the REC to provide a consistent baseline, so I can operate in an interoperable way with other Market Participants.
Proposed Solution Document
Document title
Legal Text (Tracked Changes)
Upload document
Legal Drafting (3).zip
Archive
Off
Document title
Link to Change Set (Clean)
Archive
Off
Problem Statement
The implementation of REC V2, as part of the Retail Code Consolidation SCR, was due to consolidate the existing provisions in other codes into the REC on a like-for-like basis. The Code Manager has identified that there were changes made to previous codes that weren’t reflected in the REC V2 drafting that was implemented. This means that the current processes being operated by industry parties are not reflected in the REC. REC Party's and Service Providers rely on the REC to provide a consistent baseline to ensure the industry operate in an effective and interoperable way. There are currently inconsistencies between the drafting of the REC, and the processes operated by REC Party's and Service Providers, which could cause issues in the effective operation and assurance of the retail energy market.
Stages Selection
R0012 - Change Proposal Plan v1.0 (Approved)
R0012 - Initial Assessment Report v1.0 (Approved)
R0012 - Preliminary Change Report v1.0
R0012 - Preliminary Change Report v2.0 (Approved)
R0012 - Final Change Report v1.0 (Pre-Vote)
R0012 - Final Change Report v2.0 (Post-Vote)
Company Name
REC Code Manager
Review status
Review required
Missing Meter Technical Details
Date of latest update
Type
Change
ID
R0006
Change Category
Change Path
Priority
Urgent
No
Latest Update
08/07/2024 - R0006 has been withdrawn as the issue has been addressed under R0121 - SDEP Review Improvements - Process Types.
Summary
When a Switch occurs, with a concurrent change of Metering Equipment Manager (MEM), and the Meter Technical Details (MTD) are not received by the Gaining Supplier’s MEM, they are unable to provide them to the Gaining Supplier. Lack of MTDS can impact Consumers, Suppliers, and other industry Parties. The Change Proposer has highlighted that there is currently no defined escalation process available to Suppliers, enabling them to chase for missing MTDs following a Switch.
Change Plan
Initial Assessment Report published
Completed
Start:
08 Sep 2021Due:
12 Oct 2021Completion:
12 Oct 2021Change Panel review
Completed
Start:
12 Oct 2021Due:
19 Oct 2021Completion:
19 Oct 2021Updated Change Proposal Plan presented to Change Panel
Completed
Start:
19 Oct 2021Due:
04 Oct 2022Completion:
04 Oct 2022Solution Development
Completed
Start:
04 Oct 2022Due:
05 Oct 2022Completion:
08 Jan 2023Updated plan Presented to Change Panel
Completed
Start:
05 Oct 2022Due:
06 Dec 2022Completion:
06 Dec 2022Service Provider Impact Assessment
Missing Meter Technical Details > Change Plan
Start:
06 Dec 2022Due:
09 Jan 2023Completion:
Party Impact Assessment
Completed
Start:
09 Jan 2023Due:
03 Feb 2023Completion:
24 Feb 2023Preliminary Change Report Issued
Missing Meter Technical Details > Change Plan
Start:
03 Feb 2023Due:
28 Apr 2023Completion:
Responsible Committee Review
Missing Meter Technical Details > Change Plan
Start:
28 Apr 2023Due:
10 May 2023Completion:
Consultation Issued
Missing Meter Technical Details > Change Plan
Start:
10 May 2023Due:
12 May 2023Completion:
Final Change Report Issued
Missing Meter Technical Details > Change Plan
Start:
12 May 2023Due:
30 Jun 2023Completion:
Responsible Committee Decision
Missing Meter Technical Details > Change Plan
Start:
30 Jun 2023Due:
12 Jul 2023Completion:
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As a Consumer: I want my new Supplier to set up my account in a timely manner, ensuring that I receive timely and accurate bills. I want to my meter to be read regularly to ensure I receive accurate bills I want to receive my final invoice from my old Supplier in a timely manner
- As a Losing Supplier I want to agree a closing meter reading to allow me to produce a final invoice and collect any outstanding payments
- As a Gaining Supplier I want to set up the energy account correctly for the consumer, receive an opening reading and produce a timely first invoice As a Gaining Supplier’s MEM I want to receive the MTD to enable me to update my data and trigger the necessary Market Messages to the new Supplier, new DC and DNO As a new Data Collector I want to receive the MTD to enable me to set up the correct meter reading schedule and collect meter readings.
Proposed Solution Document
Document title
R0006 - Solution Document v1.0
Upload document
R0006_Solution Document v1.0 (1).pdf
Archive
Off
Problem Statement
On a CoS the new MEM and Supplier need to receive the MTDs from the previous MEM to complete the setup of the customer’s account and billing records. Where MTD are not sent there is no dispute or escalation process to resolve this. This prevents the new Supplier from setting up the customer’s account and issuing a timely and accurate bill.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0006 - Change Proposal Plan v4.0 (Approved)
R0006 - Initial Assessment Report v1.0 (Approved)
Company Name
ScottishPower
Review status
Review required