Provision of Standard industrial Classification (SIC) Code to REC Parties
Date of latest update
Type
Issue
ID
I0327
Priority
Urgent
No
Latest Update
18/11/2026 - On 17 November 2026, the REC Change Panel approved the Change Report (Proposal Plan) for I0327 in line with the Code Manager's recommendation. The Information Request will close on 04 December 2026.
Summary
As part of the planning required to deliver Net Zero, Gas Distribution Networks (GDNs) are obligated to plan Industrial and Commercial (I&C) gas demand at a more granular, site-specific level. To meet this obligation, access to Standard Industrial Classification (SIC) Code data, matched to both Gas and Electricity Meter Point Reference Numbers, would provide a significantly improved understanding of I&C customers.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Solution Development
Problem Statement
As part of the planning required to deliver Net Zero, Gas Distribution Networks (GDNs) are obligated to plan Industrial and Commercial (I&C) gas demand at a more granular, site-specific level. Ofgem, DESNZ and NESO increasingly require GDNs to present detailed information on the types of I&C activities operating within each Network footprint to support robust long-term whole-system planning. To meet this obligation, access to Standard Industrial Classification (SIC) Code data, matched to both Gas and Electricity Meter Point Reference Numbers, would provide a significantly improved understanding of I&C customers. This data would enable GDNs to:
- characterise current I&C gas demand more accurately,
- identify patterns and drivers of consumption across different industrial and commercial sectors, and
- engage more effectively with site operators to understand their ongoing and future energy needs.
By improving visibility of the industrial and commercial landscape across the network, GDNs would be able to plan current demand more effectively, better identify areas requiring continued investment, and support whole system partners such as DNOs where cross vector interactions may be relevant, ensuring planning decisions remain aligned with customers’ needs while supporting the broader Net Zero transition. This data would also improve targeted engagement with strategically significant I&C sites, allowing networks to better understand operation drivers, decarbonisation constraints and long-term energy requirements rather than that of current and historic consumption trends.
- characterise current I&C gas demand more accurately,
- identify patterns and drivers of consumption across different industrial and commercial sectors, and
- engage more effectively with site operators to understand their ongoing and future energy needs.
By improving visibility of the industrial and commercial landscape across the network, GDNs would be able to plan current demand more effectively, better identify areas requiring continued investment, and support whole system partners such as DNOs where cross vector interactions may be relevant, ensuring planning decisions remain aligned with customers’ needs while supporting the broader Net Zero transition. This data would also improve targeted engagement with strategically significant I&C sites, allowing networks to better understand operation drivers, decarbonisation constraints and long-term energy requirements rather than that of current and historic consumption trends.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0327 submission form
Change Report - Proposal Plan
I0327 Change Report (Proposal Plan) Approved 17.11.26
Company Name
-
Review status
Review required
Use of REL Data to Support Key Regulations
Date of latest update
Type
Change
ID
R0324
Change Category
Change Path
Priority
Urgent
No
Latest Update
29/10/2026 - The Change Report (Final Recommendation) in line with the Code Manager recommendation, the REC Technical Expert Panel approved this Change Proposal for implementation on 26 February 2027. The appeal window is open until 12 November 2026.
Summary
The REC Electricity Enquiry Service (EES) Service Definition and Electricity Data Access Matrix (DAM) limits access of REL data to the Authority. This Issues seeks to extend access to the Code Manager and government departments in Great Britain to facilitate key government reporting and REC processes.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
15 Sep 2026Final Recommendation approved at TEP
Completed
Start:
Due:
Completion:
28 Oct 2026Impacted REC Documents
Impacted REC Services
Status
Implementation Date
26 February 2027
| Included changes | Affected REC Items | |
|---|---|---|
| R0292 | Obligate Energy Suppliers to provide photo evidence of Theft in Conveyance to Network Parties | |
| R0322 | Erroneous Switch Review: I0237 Clarifications | |
| R0324 | Use of REL Data to Support Key Regulations |
|
| R0339 | REC Change to align with BSC CP Clarify Supplier obligations for IF-002 messages where a Switch is cancelled |
|
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0324 Draft Legal Text
Upload document
I0324 Draft Legal Text (1).zip
Archive
Off
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0324 submission form
I0324 Change Report (Proposal Plan and Consultation) v1.1 Pre-Approval
R0324 Change Report (Consultation) Approved 15.09.26
R0324 - Consolidated Consultation Responses v1.0
R0324 Change Report (Final Recommendation) v1.0 Pre Approval
R0324 Change Report (Final Recommendation) v2.0 Approved 28.10.26
Company Name
REC Code Manager
Review status
Review required
Extending R0067 Refresh Functionality
Date of latest update
Type
Issue
ID
I0281
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/09/2026 - The update to plan has been approved by the Technical Expert Panel on 30 September 2026.
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSPs) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Issue originally aimed to extend the Refresh functionality, implemented for the Gas Retail Data Agent (GRDA).to the Electricity Retail Data Agent (ERDA). Following solution development for I0281, it was agreed that the Refresh functionality would be made available for all Market Participants in receipt of the in-scope messages.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0281_Proposed_Legal text_PIA_V1.0.
Upload document
I0281_Proposed_Legal text_PIA_V1.0.zip
Archive
Off
Problem Statement
CSS messages are not received by the SDSPs in the order in which they were originally sent, or after Gate Closure, so it can be difficult to detect and often requires significant manual effort to resolve. This issue can directly impact Consumer switching experiences, causing disruption and possible delays in a switch.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0281_Change Report (Update to Plan) v1.0 (Pre-approval)
I0281_Change Report (Update to Plan) v2.0 Approved
I0281_Change Report (Update to Plan) v2.0 (Pre-approval)
I0281_Change Report (Update to Plan) v1.0 Approved 20.05.2026
I0281_Change Report (Proposal Plan) v1.0_Approved 04.11.2025
Company Name
REC Technical Services
Review status
Review required
Data Latency SLA Alignment for Gas Enquiry Service
Date of latest update
Type
Change
ID
R0277
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
The current performance level for the processing of Data from CDSP is no longer fit for purpose and does not reflect the operational capability of the service. The performance level was originally conceived as part of the CSS programme in 2022 and operational reality has shown it is not required by industry. A revision of the performance level will align service performance metrics with system performance and deliver economic benefit.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
07 Oct 2025Final Recommendation approved at TEP
Completed
Start:
Due:
Completion:
26 Nov 2025Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0277 Legal Text For Consultation
Upload document
R0277 Legal Text For Consultation.zip
Archive
Off
Problem Statement
The current performance levels for the processing of data from CDSP is no longer fit for purpose and does not align with system or service performance. The CSDP is also not meeting these performance levels on a monthly basis. While there are no known issues on data latency raised by users, this change to clarify performance levels is needed for the GES reinstated contract and to ensure ongoing service delivery.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0277 submission form
I0277 Change Report (Proposal Plan) approved 07/10/2025
R0277 Change Report (For Consultation) v1.0
R0277 Change Report (Final Recommendation) Approved 26.11.25 v1.0
Company Name
RECCo
Review status
Review required
Gas Pressure and Capacity Information Transparency
Date of latest update
Type
Issue
ID
I0274
Change Category
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - Change Report (Proposal Re-Plan) approved at Change Panel
Summary
As per Section 13.4.18 of CoMCoP, retrieving gas pressure and capacity information from Transporters via the GT1 process can be time consuming for Energy Suppliers/MAMs and/or Consumers. The process of retrieving this information is inconsistent and service timescales are varied between transporters. Gas pressure and capacity information should be readily available through the Gas Enquiry Service to enable timely processing of site work and requests to enable MAM’s and Suppliers to appropriately service their customers.
Change Plan
Change Report (Proposal Plan) approved at Change Panel
Completed
Start:
Due:
Completion:
18 Nov 2025Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
For some Energy Suppliers, MAMs and consumers, retrieving pressure and capacity information via the GT1 process can be time consuming. This is due to elements like response timescales and methods (batch responses vs individual responses) being varied among GTs. This ultimately has a negative impact on customers waiting on site work, such as a new connection, for example.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0274 submission form
I0274 Change Report (Proposal Plan) V1.0 approved 18.11.25
IG174 Change Proposal Re-Plan v2.0 approved 21.07.2026
Company Name
OVO Energy
Review status
Review required
Proposal to Enable Broader Use of Retail Energy Location (REL) Data for Non-Switching Applications
Date of latest update
Type
Issue
ID
I0218
Change Category
Change Path
Priority
Urgent
No
Latest Update
05/11/2026 - Service Provider Impact Assessments are in progress and will close on 06 November 2026. A refreshed Code Manager Initial Assessment will be carried out given the change of scope since the original assessment.
Summary
The problem being addressed is the current restriction within the Retail Energy Code (REC) that limits the use of Retail Energy Location (REL) data solely to switching purposes. This restriction prevents the full utilisation of REL data, which could be valuable for a broader range of operational, regulatory, and industry applications. Key Issues: - Currently, REL data, enriched with Unique Property Reference Numbers (UPRNs), is available via the Electricity and Gas Enquiry Services. However, Schedule 29 (Address Management) of the REC restricts its use to switching purposes only, preventing its use in other important industry initiatives. - Various industry stakeholders, including REC and non-REC data requestors as well as Ofgem (the regulator), have expressed a strong interest in utilising REL data for non-switching purposes. The restriction is seen as a limitation, especially for initiatives that require accurate property data to support wider operational and regulatory functions. - By restricting the use of REL data to switching, stakeholders are unable to fully leverage it for improving operational efficiency, regulatory compliance, and overall service delivery. Lifting this restriction would enable the wider use of REL data, allowing stakeholders to benefit from its full potential across various non-switching applications.
Change Plan
Proposal plan approved at Change Panel
Completed
Start:
Due:
Completion:
21 Jan 2025Extension to Proposal Plan approved by REC Change Panel
Completed
Start:
Due:
Completion:
06 May 2025Update to Plan approved at Change Panel
Completed
Start:
Due:
Completion:
18 Nov 2025Extension to Plan approved at Change Panel
Completed
Start:
Due:
Completion:
04 Aug 2026Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- RECCo would acquire a AddressBase Core license from Ordinance Survey and the REC would be updated to allow parties to take full advantage of this data. In order for parties to use the REL data, they would need to acquire an AddressBase Premium license from Ordinance Survey or other relevant license.
Problem Statement
Retail Energy Location (REL) data currently is not permitted for uses such as improving customer service and streamlining internal processes. This means that stakeholders, such as Ofgem and data requestors, have been unable to benefit from this data and Consumers are therefore unable to benefit from the full potential use of their data.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue proposal form
I0218 - Change Report (Proposal Plan) V2.0 (07.05.2025)
I0218 - Extension to Plan V1.0 (06.05.2025) (Approved)
I0218 - Update to Plan V2.0 (09.09.2025) (Approved)
I0218 - Update to Plan V3.0 (18.11.2025) Approved
I0218 Extension to Plan V1.0 Pre-Approval
I0218 - Extension to Plan V2.0 (04.08.2026) Approved
Company Name
RECCo
Review status
Review required
Addition of MEMs to the Gas Enquiry Service (GES) API
Date of latest update
Type
Issue
ID
I0195
Urgent
No
Latest Update
16/10/2024 - This Change Issue has been rejected as is already being progressed under the data access change process implemented as R0118.
Summary
Empty
Status
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Stages Selection
I0195-~1.doc
Company Name
Code Manager
Review status
Review required
Metering Asset Manager (MAM) Communication Method Register
Date of latest update
Type
Change
ID
R0198
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the February 2026 REC Release.
Summary
Studies conducted by the REC Performance Assurance (RPA) function of the REC Code Manager have concluded that gas market data fidelity may be improved by reducing the frequency of missed messages between Metering Asset Managers and other REC Parties. This Issue seeks to explore mechanisms by which a reduction in the number of permissible communication methods used by MAMs could support the data quality improvement objective.
Impacted REC Parties and Market Participants
Status
Implementation Date
27 February 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0179 | Proposal for Limiting Queries in EES API Calls (Single Query per API Call) | |
| R0190 | Related Meter Point RMP status rules |
|
| R0198 | Metering Asset Manager (MAM) Communication Method Register | |
| R0242 | Missing Scenario Variant from R0043 |
|
| R0244 | C21 to be introduced into STIRG Document |
|
| R0235A | Missing Scenario Variants in D0179 Alternate Solution | |
| R0256 | MM00023 /D0135 - Asset Condition Report clarification of intent on R0021/R0101 |
|
| R0270 | Clarification of SIP Qualification Requirements |
|
| R0271 | Clarification of ASP, AMI, and EMO Accession Requirements |
|
| R0272 | Enabling transparency of the CRS Provider’s REC service level performance |
|
| R0277 | Data Latency SLA Alignment for Gas Enquiry Service |
|
| R0280 | CSS Certificate Authority audit clarification |
|
| R0283 | Annual Address Management Plan Updates |
|
| R0287 | Clarification and Amendments to Annulment Definition in Schedule 23 – Alignment with SLC Obligations |
|
| R0293 | Housekeeping February 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register
Upload document
I0198 Proposed Solution V1.0.zip
Archive
Off
Document title
R0198 - Draft Schedule 14 - Metering Operations & Draft Communications Method Register V2.0
Upload document
R0198 Proposed Solution V2.0.zip
Archive
Off
Problem Statement
MAMs communicate with each other, and with other parties, using up to three possible methods as they send Market Messages in line with their obligations in the REC. It has been suggested that moving to a single communication method might help mitigate gas data quality issues. This Issue seeks to explore an interim solution to facilitate this.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0198 Change Proposal (pdf)
I0198 Change Report (Plan) (Approved) V2.0 03.04.2
I0198 Change Proposal Re-Plan V1.0 28.03.25
I0198 Change Report (IA) V1.0 03.04.25
R0198 Consolidated IA Responses V1.0 Non-Confidential
R0198 Change Report (Consultation) V1.0 11.06.25
R0198 Change Proposal Re-Plan V2.0 02.07.25
Change Report (Consultation) V2.0 11.07.25
R0198 Consolidated Consultation Responses V1.0 06.08.25
R0198 Change Report (Final Recommendation: Pre-Vote) V1.1 13.08.25
R0198 Change Report (Final Reccomendation - Post-Vote) V1.0 13.08.25
Company Name
-
Review status
Review required
Amendment Proposal: RECCo Access Provision to RECCo Services
Date of latest update
Type
Change
ID
R0185
Change Path
Priority
Urgent
No
Latest Update
08/08/2024 - the Proposer has withdrawn this Change Proposal.
Summary
RECCo is tasked with fulfilling several obligations. This proposal has been raised to amend some of the wording within the REC, which would benefit from reassessment. When the REC was originally drafted, references to RECCo in the code were originally intended to refer to the activities directly managed and overseen by the REC Board, and were considered separately to activities managed by the Code Manager.
Impacted REC Documents
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0185- CP Form Amendment Proposal RECCo Access Provision to RECCo Services.docx
Company Name
RECCo
Review status
Review required
Creation of new Enquiry Service User Category
Date of latest update
Type
Change
ID
R0131
Change Category
Change Path
Priority
Urgent
No
Latest Update
17/06/2024 - this Change Proposal has been withdrawn at the request of the Proposer. The adoption window is closed.
Summary
Empty
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
R0131 - Change Proposal Form (downloadable version) 22.06.2023
Company Name
-
Review status
Review required