04/09/2026 - This Issue has now been withdrawn given an anticipated wider review of Schedule 15 which will identify and implement clarifications throughout this Schedule, including clarification that were proposed under this Issue. If you wish to adopt this Issue, please contact the Code Manager by COB 18 September 2026.
Summary
This Change Proposal seeks to ensure that the REC is reflective of current practice regarding initial approval of Metering Equipment Manager, Electricity Metering Operative, Approved Meter Installer, and approved AMR Service Provider, that have been determined by the Metering Scheme Auditor, Wilcock Consultants Ltd, in April 2023.
Status
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Stages Selection
I0334 submission form
Company Name
Retail Energy Code
Review status
Review required
Smart Meter Communication Licence Code Changes
Date of latest update
Type
Change
ID
R0333
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented on 01 October 2026.
Summary
Ofgem has awarded the Smart Meter Communications Licence 2 (SMCL2) to DCC2 Limited, a subsidiary of Smart Energy Code Company Limited (SECCo). To enable a smooth transition and ensure continuity of service, changes to both the Smart Energy Code (SEC) and the Retail Energy Code (REC) will be required.
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0333 - Legal Text V1.1 28.08.26
Upload document
R0333 - Legal Text V1.1 28.08.26.pdf
Archive
Off
Document title
R0333 - Legal Text V1.0 28.07.26
Upload document
I0333 - Legal Text V1.0 28.07.26 (1).pdf
Archive
Off
Stages Selection
SME
SME Role
Lead Assurance Analyst
I0333 Submission Form (PDF)
R0333 Change Report (Consultation) (Approved) 04.08.26
R0333 Consolidated Consultation Responses V1.0 08.09.26
R0333 Change Report (Final Recommendation) (Post-Vote) 15.09.26
Company Name
Code Manager RPS
Review status
Review required
Regulatory Alliance Creation Rejections
Date of latest update
Type
Change
ID
R0331
Change Category
Change Path
Priority
Urgent
No
Latest Update
20/10/2026 The Change Report (Update to Plan) was approved by the REC Change Panel on 20 October 2026, and the Issue progressed to a Change Proposal on 22 October 2026.
Summary
An incident where Network Parties did not submit Regulatory Alliances on time to the Central Switching Service (CSS) Provider, or did submit the Regulatory Alliances but did not action rejections from the CSS Provider in a timely manner, led to over 200 Consumers being delayed in Switching to their chosen Energy Supplier. This Change Proposal has been raised to review this process.
Change Plan
Change Report (Proposal Plan) approved at Change Panel
Completed
Start:
Due:
Completion:
18 Aug 2026Presented at Change Issues Group
Completed
Start:
Due:
Completion:
03 Sep 2026Update to plan approved by Change Panel
Completed
Start:
Due:
Completion:
20 Oct 2026Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0331 Schedule 24 Switching Data Management
Upload document
I0331 Schedule 24 Switching Data Management v0.6.docx
Archive
Off
Problem Statement
The lack of Service Level Agreements (SLAs) on Network Parties to submit Regulatory Alliances to the CSS Provider or to work any rejections received from the CSS Provider can lead to delays in Consumers being able to Switch to their chosen Energy Supplier.
Stages Selection
SME
SME Role
Lead Assurance Analyst
I0331 submission form
I0331 Change Report (Update to Plan) - Approved 20/10/26
I0331 Change Report (Proposal Plan) V1.0 approved 18.08.26
I0331 Consolidated Impact Assessment Responses v2.0
I0331 Update to Plan Approved 20.10.2026
Company Name
SQE Energy
Review status
Review required
A review of the Misdirected Payments and Debt Assignment Processes
Date of latest update
Type
Issue
ID
I0329
Change Category
Change Path
Priority
Urgent
No
Latest Update
04/08/2026 - On 04 August 2026, the REC Change Panel approved this Proposal Plan.
Summary
This Issue seeks to assess and identify any gaps, inconsistencies or process improvements opportunities for the Misdirected Payments and Debt Assignment processes.
Status
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0329 Submission Form
I0329 Change Report (Proposal Plan) V1.1 Approved
Company Name
REC Code Manager
Review status
Review required
Provision of Standard industrial Classification (SIC) Code to REC Parties
Date of latest update
Type
Issue
ID
I0327
Priority
Urgent
No
Latest Update
18/11/2026 - On 17 November 2026, the REC Change Panel approved the Change Report (Proposal Plan) for I0327 in line with the Code Manager's recommendation. The Information Request will close on 04 December 2026.
Summary
As part of the planning required to deliver Net Zero, Gas Distribution Networks (GDNs) are obligated to plan Industrial and Commercial (I&C) gas demand at a more granular, site-specific level. To meet this obligation, access to Standard Industrial Classification (SIC) Code data, matched to both Gas and Electricity Meter Point Reference Numbers, would provide a significantly improved understanding of I&C customers.
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Solution Development
Problem Statement
As part of the planning required to deliver Net Zero, Gas Distribution Networks (GDNs) are obligated to plan Industrial and Commercial (I&C) gas demand at a more granular, site-specific level. Ofgem, DESNZ and NESO increasingly require GDNs to present detailed information on the types of I&C activities operating within each Network footprint to support robust long-term whole-system planning. To meet this obligation, access to Standard Industrial Classification (SIC) Code data, matched to both Gas and Electricity Meter Point Reference Numbers, would provide a significantly improved understanding of I&C customers. This data would enable GDNs to:
- characterise current I&C gas demand more accurately,
- identify patterns and drivers of consumption across different industrial and commercial sectors, and
- engage more effectively with site operators to understand their ongoing and future energy needs.
By improving visibility of the industrial and commercial landscape across the network, GDNs would be able to plan current demand more effectively, better identify areas requiring continued investment, and support whole system partners such as DNOs where cross vector interactions may be relevant, ensuring planning decisions remain aligned with customers’ needs while supporting the broader Net Zero transition. This data would also improve targeted engagement with strategically significant I&C sites, allowing networks to better understand operation drivers, decarbonisation constraints and long-term energy requirements rather than that of current and historic consumption trends.
- characterise current I&C gas demand more accurately,
- identify patterns and drivers of consumption across different industrial and commercial sectors, and
- engage more effectively with site operators to understand their ongoing and future energy needs.
By improving visibility of the industrial and commercial landscape across the network, GDNs would be able to plan current demand more effectively, better identify areas requiring continued investment, and support whole system partners such as DNOs where cross vector interactions may be relevant, ensuring planning decisions remain aligned with customers’ needs while supporting the broader Net Zero transition. This data would also improve targeted engagement with strategically significant I&C sites, allowing networks to better understand operation drivers, decarbonisation constraints and long-term energy requirements rather than that of current and historic consumption trends.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0327 submission form
Change Report - Proposal Plan
I0327 Change Report (Proposal Plan) Approved 17.11.26
Company Name
-
Review status
Review required
Erroneous Switch Review: Assurance Reporting Update
Date of latest update
Type
Issue
ID
I0326
Change Path
Priority
Urgent
No
Latest Update
On 30 October 2026, the REC Change Panel voted to approve this Extension to Plan for I0326 via ex-committee decision.
Summary
There is gap in the Erroneous Switch (ES) Performance Assurance reporting as the DTN does not provide MPXN level data up front. It requires individual ES permission before MPXNs are provided. However, CSS reporting does provide monthly MPXN level report. As such end-to-end monitoring of the ES process cannot be carried out at a MPXN level.
Status
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Problem Statement
There is a lack of consistency in the level of data granularity provided for ES Performance Assurance reporting across industry systems. Specifically, the DTN provides only aggregated data unless explicit permission is obtained from individual Energy Suppliers for each MPxN, whereas the CSS routinely produces monthly reports at MPxN level. This misalignment restricts the ability to access comparable, detailed datasets across platforms and prevents effective end-to-end monitoring and assurance of the ES process at MPxN level.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0326 submission form
I0326 Change Report (Proposal Plan) (Approved) v1.1 07.07.26
I0326 Change Report (Update to Plan) Pre-Approval
I0326 Change Report (Update to Plan) v1.0 Approved 30.10.26
Company Name
RECCo
Review status
Review required
Post-MHHS Full Transition Complete (M15) REC updates
Date of latest update
Type
Change
ID
R0325
Change Category
Change Path
Priority
Urgent
No
Latest Update
29/09/2026 - A Change Report (Update to Plan) has been published for review at the Change Panel on 06 October 2026, any comments on this plan must be received by 23:59 05 October 2026.
Summary
The REC was updated, primarily through R0209 and R0241, to add requirements that support the transition to, and enduring operation of the MHHS arrangements. As part of the transition, each impacted Metering Point will be migrated using processes defined in Codes, including the REC. Once this migration activity is complete, the legacy and transitional arrangements will become redundant and should be removed from the REC to support its efficient operation
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Retention of redundant obligations within the REC would make it more complex to navigate for Market Participants and could cause confusion on the obligations that are in effect to support the efficient operation of the Great British Energy retail market. It is also worth noting that until Ofgem formally closes the MHHS Significant Code Review (SCR), this REC Issue could potentially impact that SCR.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0325 submission form
I0325 Scope list
I0325 Schedules CHIG 03092026.zip
I0325 Schedules CHIG 01102026.zip
I0325 Schedule1 CHIG 05112026.pdf
I0325_Change Report (Update to Plan) v1.0
R0325 Legal drafting
Company Name
RECCO
Review status
Reviewed - Accepted
Introduction of Consumer Consent Service
Date of latest update
Type
Change
ID
R0318
Date of next activity
Change Category
Other Industry Codes impacted
Priority
Urgent
No
Latest Update
18/11/2026 - The Issue was progressed to Change Proposal on 17 November 2026. Following industry consultation on the REC drafting a number of refinements to the CCS design and drafting are being made. On progression to Change Proposal and Modification, the title has been updated to Introduction of Consumer Consent Service (not Solution) to reflect the new service that will be introduced.
Summary
This initiative will support the transformation of how energy is managed and consumed by giving consumers control over their energy (gas, electricity, heat, or other) data, enabling innovation through third-party services, and advancing sustainability goals. This REC Issue is being raised to promote visibility and awareness of opportunities for engagement, in advance of the CCS Change Proposal being progressed.
Change Plan
Proposal Plan (Approved)
Completed
Start:
02 Apr 2026Due:
02 Apr 2026Completion:
02 Apr 2026Update to Plan (Approved)
Completed
Start:
30 Sep 2026Due:
30 Sep 2026Completion:
30 Sep 2026Definition
Completed
Start:
02 Apr 2026Due:
17 Nov 2026Completion:
17 Nov 2026Business Case Assessment
In Progress
Start:
18 Nov 2026Due:
18 Dec 2026Completion:
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
RECCo | Consumer Consent Programme page
Archive
Off
Document title
Consumer Consent Hub - REC Portal
Archive
Off
Document title
Consumer Consent Solution Design Consultation (March 2026)
Archive
Off
Document title
RECCo's response to the CCS Design Consultation - 28 May 2026
Archive
Off
Problem Statement
A new set of arrangements for a Consumer Consent Solution (CCS) is currently being developed under the RECCo CCS project. The new arrangements will need to be implemented within the REC so that they can be governed under the REC on an enduring basis.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0318 submission form
RECCHIG_26_0305 - I0318 Consumer Consent Solution
I0318 Change Proposal Re-Plan v2.0 APPROVED 30.09.2026.
I0318 Change Report (Proposal Plan) v1.0 APPROVED 02.04.2026
Company Name
Retail Energy Code Company Ltd
Review status
Review required
REC Portal Solution to R0224
Date of latest update
Type
Issue
ID
I0315
Priority
Urgent
No
Latest Update
18/02/2026 - accepted in by Code Manager
Summary
As part of R0224, the technical solution creates a CSS replica (read-only) database view that can be used by RECCo and the REC Code Manager to generate reports on demand for market participants. For users to be able to access this database and request generation of the appropriate reports, this change is seeking to develop that front end portal capability to manage user’s requests and allow for completed reports to be downloaded via the REC Portal.
Status
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Stages Selection
I0315 submission form
Company Name
REC Code Manager
Review status
Review required
Crossed Meters Process: Clarifications and Support
Date of latest update
Type
Issue
ID
I0314
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 30 October 2026, the REC Change Panel approved an Extension to Plan for I0314 via ex-committee.
Summary
This issue seeks to solve is the gap between the documented REC Crossed Meters process and how it is being applied operationally. The aim is to ensure all parties fully understand the process, apply it consistently, and have the support necessary to achieve timely, correct resolution of Crossed Meter cases.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0314 submission form
I0314 Change Report (Proposal Plan) Approved 21.04.26
I0314 Extension to Plan V1.0 (Approved) 30.10.26
Company Name
REC Code Manager
Review status
Review required