Erroneous Switch Review: Amendments to Clause 4.5
Date of latest update
Type
Change
ID
R0313
Change Category
Change Path
Priority
Urgent
No
Latest Update
30/10/2026 REC Change Panel voted to approve the Extension to Plan for R0313 via an ex-committee decision.
Summary
Schedule 30, Section B, Clause 4.5 currently permits Energy Suppliers to raise an Erroneous Switch (ES) within 24 months of the suspected ES taking place. However, analysis from the I0237 Erroneous Switch Review shows that 98% of ESs are raised within the first 12 months.
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- Amend Schedule 30 – Resolution of Consumer Facing Switching and Billing Issues, Section B, Clause 4.5 to reduce the timeframe to 12 months and ensure Consumer contact is made in a reasonable timescales.
Problem Statement
The existing 24‑month allowance no longer reflects operational practice and maintains an unnecessarily long resolution period that adds complexity and increases the potential for data quality issues, Consumer confusion, and prolonged operational uncertainty. When the original 24‑month time limit was introduced (prior to REC Go‑Live), it was expected that this would later be reduced to 12 months soon after implementation. However, this subsequent reduction did not take place.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
R0313 submission form
R0313 - Change Report (Proposal Plan) V1.0 (Approved) 19.05.2026
R0313 - Change Report (Extension to Plan) V1.0 Approved 27.08.2026
R0313 - Change Report (Update to Plan) V1.0 (Approved)
Company Name
REC Code Manager
Review status
Review required
Review of export meter work arrangements
Date of latest update
Type
Change
ID
R0312
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/11/2026 The Party impact assessment has now opened until 23:59 on 04/12/2026
Summary
The REC Metering Operations Schedule has limited distinction between the activities for import and export metering. These provisions were not specifically developed to support a market with high volumes of small-scale microgeneration with shared metering assets for import and export.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
There is a lack of distinction within REC Schedule 14 – Metering Operations between activities for Import and Export Metering, and how to manage work arrangements where is a shared Metering Asset between Import and Export Suppliers.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0312 submission form
I0312 Change Report (Proposal Plan) v1.0 Approved 21.04.26
Change Report (Update to Plan) V1.0 Pre-Approval 10.11.26
R0312 Process Maps and Proposed Solution Requirements
Company Name
-
Review status
Review required
REC Change to Align with DCP467 Asset Condition Reporting
Date of latest update
Type
Change
ID
R0306
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
11/11/2026 - the Metering Expert Panel voted to approve placing this Change Proposal on hold until the solution of DCP467 has been finalised.
Summary
DCUSA change DCP467 has been raised to propose that Category A and B defects reported currently using the Asset Condition Report (D0135) or phone call to the DNO, should instead be reported via an online reporting tool where the DNO has one available. This is expected to have impacts to the REC.
Impacted REC Parties and Market Participants
Status
Implementation Date
06 November 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0180 | Clarity on use of on hold for switching issues, including the obligations of CSS Users |
|
| R0207 | Import / Export MOA Charging Clarification |
|
| R0253 | Theft - DNO/Networks not providing photos |
|
| R0261 | Addition of Export flag in D0303 flows | |
| R0266 | REC Data Specification Clarifications |
|
| R0317 | Number of Displayed Register Digits Data Item linkage | |
| R0328 | Removal of D0383 & D0384 requirements from Sharing MTDs process |
|
| R0336 | Legal text to support REC Change R0180 |
|
| R0343 | MSC - Amending Statement Production Timescales | |
| R0345 | Housekeeping November 2026 |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 11 Nov 2026 | ||
| 1.0 | 11 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0306 STIRG Guidance Document draft V0.1
Upload document
I0306 STIRG Guidance Document draft V0.1.docx
Archive
Off
Document title
I0306 Data Spec changes v0.1
Upload document
I0306 Data Spec changes.docx
Archive
Off
Document title
R0306 STIRG Guidance Document draft V0.2
Upload document
I0306 STIRG Guidance Document draft V0.2.docx
Archive
Off
Document title
R0306 Data Spec changes V0.2
Upload document
I0306 Data Spec changes V0.2.docx
Archive
Off
Problem Statement
Where DNOs have enhanced reporting tools for Category A or Category B situations, it is not mandatory for Parties to submit reports using this method. This may lead to a detrimental Consumer experience, as it is limited what information can be provided over the telephone or via Market Message (e.g. it is not possible to provide photographs of the situation).
Stages Selection
Workgroup
Workgroup(s)
I0306 submission form
I0306 Change Report (Proposal Plan) V1.0 approved 03.02.26
I0306 Consolidated Impact Assessment Responses V1.0
R0306 Change Report (For Consultation) V1.1
R0306 Consolidated Consultation Responses v1.1 PUBLIC
R0306 Change Proposal Re-Plan v1.0 approved 08.07.26
R0306 Change Proposal Re-Plan v2.0 approved 11.11.26
Company Name
-
Review status
Review required
Categorisation of Gas Address Amendment SDEP Cases
Date of latest update
Type
Issue
ID
I0305
Priority
Urgent
No
Latest Update
20/01/2026 - Issue accepted in by Code Manager
Summary
The Market Message PT0055 is specifically used for SDEP cases related to Gas Crossed Meter queries. We have identified a large number of cases requesting resolutions relating to Gas Address Amendments that are being raised in PT0055.
Status
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
Stages Selection
I0305 submission form
Company Name
OVO Energy
Review status
Review required
Implementation of Ofgem-led code modification prioritisation within the REC
Date of latest update
Type
Change
ID
R0304
Change Category
Change Path
Urgent
No
Latest Update
This Change Proposal was implemented on 29 May 2026.
Summary
Ofgem has consulted on, and is progressing towards a decision on, the introduction of a harmonised code modification prioritisation framework across all industry codes, under its transitional powers in Schedule 12 to the Energy Act 2023. This Issue is being raised to provide the formal REC change vehicle through which Ofgem’s prioritisation reforms can be tracked, developed and implemented in the REC, once the Authority has published its decision and statutory modification notice.
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
In the absence of REC changes, the REC would not align with Ofgem’s harmonised approach to code modification prioritisation, creating inconsistency with other industry codes and undermining the objectives of Energy code reform.
Stages Selection
I0304 submission form
I0304 Change Report (Proposal Plan) V1.0
New Priority Status
Company Name
RECCo
Review status
Review required
Potential Consumer detriment for Smart Economy 7
Date of latest update
Type
Issue
ID
I0303
Urgent
No
Latest Update
09/04/2026 Following a review of responses to the joint information request on REC Issues I0273 - Sharing of SSC and TPR Information for MHHS Smart and Advanced Meters and I0303 - Potential Consumer detriment for Smart Economy 7, the Code Manager has determined that the scope of REC Issue I0303 can be considered as part of the solution development for REC Issue I0273. I0303 has now been classed as resolved and will not be progressed further as a separate Issue. For further engagement with this issue, please refer to I0273 directly.
Summary
There is a potential for Consumer detriment under the Market-wide Half Hourly Settlement arrangements where a customer unknowingly selects a tariff (i.e. single rate) where they have an Economy 7 type configuration on a Smart meter for water/storage heating.
Status
Implementation Status
Date Raised
Solution Development
Problem Statement
There is a potential for Consumer detriment under the Market-wide Half Hourly Settlement arrangements where a customer unknowingly selects a tariff (i.e. single rate) where they have an Economy 7 type configuration on a Smart meter for water/storage heating. A solution is required that enables a Supplier to identify a Smart E7 Consumer during the Switch process to ensure they can offer the correct tariff and prevent consumer detriment.
Stages Selection
Stages Selection
Workgroup
Workgroup(s)
I0303 submission form
Company Name
Centrica
Review status
Review required
Provision of data to the GES Provider
Date of latest update
Type
Issue
ID
I0302
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/08/2026 On 26 August 2026, in line with the Code Manager's recommendation, TEP approved the extension to plan for I0302.
Summary
RECCo has commenced work on developing a dual-fuel Enquiry Service which will involve the migration of data from its legacy services.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Ahead of the introduction of a dual-fuel Enquiry Service and in the case that the GES Provider is not the same entity as the CDSP and GRDA, this Issue seeks to enable the migration of gas data from legacy services into a new physical interface.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0302 submission form
I0302 Change Report (Proposal Plan) v1.0
I0302 Change Report (Update to Plan) v1.0 Approved 15.04.26
I0302 Change Report (Extension to Plan) v1.0 Approved 26.08.2026
Company Name
REC Code Manager
Review status
Review required
Updates to Enquiry Service API endpoints to support migration to RECCo’s API Gateway
Date of latest update
Type
Issue
ID
I0301
Change Path
Urgent
No
Latest Update
06/11/2026 - Following further analysis, it was determined that I0301 is no longer required. While the Issue was originally raised to support a dual-fuel approach to RECCo’s Enquiry Service evolution, the initial focus on GES means that no changes to the REC are currently required to update the relevant API endpoints.
Summary
As part of RECCo’s plan to procure a dual-fuel Enquiry Service, there will be a single point of entry to API services. A migration plan has been developed with two independent stages. For stage one, all current Enquiry Service API users will need to connect through RECCo’s API Gateway rather than connecting directly to the existing EES and GES APIs. This will require users to amend the URLs they call when accessing the services.
Status
Status
Implementation Status
Date Raised
Fuel
Solution Development
Stages Selection
Stages Selection
I0301 submission form
Company Name
REC Code Manager
Review status
Review required
Meter Manufacturers Make and Type not Populated in SMRS
Date of latest update
Type
Issue
ID
I0297
Change Path
Priority
Urgent
No
Latest Update
On 30 September 2026, the REC Technical Expert Panel voted to approve the Update to Plan for I0297, and to place this REC Issue on hold.
Summary
The Meter Manufacturers Make and Type (J0410 / DI-048) was not populated as part of the MHHS Programme's data cleanse. However it is part of the SMRS maintained Meter Technical Details (MTDs) for Smart Meters which replace the DTC MTD Market Messages for Smart Meters in the MHHS environment. It is not currently possible to populate this item in the legacy arrangements.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Following MHHS Migration, the MTDs provided by SMRS do not include the Meter Manufacturers Make and Type, as this replaces the existing D0149/D0150 Market Messages it could lead to the information being lost. This will mean Energy Suppliers and MOAs will not know the make and type of meter installed at a particular Site.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0297 submission form
I0297 Change Report (Proposal Plan) V1.0
I0297 Update to plan
I0297 Legal Drafting
I0297 Update to plan v1.0 Approved 30.09.26
Company Name
RECCo
Review status
Review required
Registration Id Required for MHHS Appointments
Date of latest update
Type
Issue
ID
I0296
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
12/05/2026 - The Code Manager have developed a solution which has been live since 05 May 2026. More detail can be found on the REC Portal Wiki. A Closure Report has now been published, and this Issue has now been classed as resolved.
Summary
The RegistrationId (DI90043 / DI849) is required by SMRS to be included in the IF-031 'Supplier Agent Appointment Request' Market Message to allow the SMRA to process the appointment request. However not all Suppliers hold the RegistrationId for all Meter Points, in particular those that have not undergone a Registration managed by the Central Switching Service (CSS)
Change Report - Initial Assessment and Change Plan Report
Impacted Consumers
Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- As part of the solution for REC Issue I0296 - Registration Id Required for MHHS Appointments the REC Code Manager have developed a process to provide Energy Suppliers the Registration Id for Metering Points that have not been through a Central Switching Service (CSS) Registration Managed Switch. This is to allow Energy Suppliers that may not hold the Registration Id for these Metering Points to populate the Market-wide Half Hourly Settlement (MHHS) Agent Appointment Messages required to initiate a MHHS Migration.
- More detail of the solution can be found: https://portal.retailenergycode.co.uk/knowledge-centre/rec-wiki/market-wide-half-hourly-settlement/provision-registration-id-required?utm_source=emailoctopus&utm_medium=email&utm_campaign=Weekly%20Bulletin%20-%202026-05-01
Proposed Solution Document
Document title
I0296 Closure Report_v1.0 (12 May 2026)
Upload document
I0296_Closure report_v1.0.pdf
Archive
Off
Problem Statement
Not all Energy Suppliers hold the RegistrationId for all Meter Points, particularly those Meter Points that have not gone through a Switch, i.e. have not undergone a Registration managed by the CSS. The RegistrationId is currently only available where a Metering Point has been through a CSS managed Registration. Without the RegistrationId available to Energy Suppliers, not all Metering Points will be able to migrate putting the MHHS Migration and Milestone M15 at risk.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0296 submission form
Company Name
RECCo
Review status
Review required