Consequential Change for CSS Smart Meter Data Retriever Appointments

Date of latest update
Type
Change
ID
R0097
Change Category
Change Path
Urgent
Yes
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
This change looks to make amendments to the Data Specification for the Supplier Arranged Appointments messages exchanged between the Electricity Retail Data Service and Central Switching Service.
Proposer
Michael Taylor
Change Plan

Service Provider Impact Assessment started

Completed

Start:

20 Feb 2023

Due:

22 Mar 2023

Completion:

22 Mar 2023

Service Provider Impact Assessment completed

Completed

Start:

22 Mar 2023

Due:

03 May 2023

Completion:

03 May 2023

Preliminary Change Report and Consultation issued

Completed

Start:

03 May 2023

Due:

19 May 2023

Completion:

19 May 2023

Consultation closed

Completed

Start:

19 May 2023

Due:

05 Jun 2023

Completion:

05 Jun 2023

Final Change Report issued

Completed

Start:

05 Jun 2023

Due:

21 Jun 2023

Completion:

15 Jun 2023

Responsible Committee decision

Completed

Start:

21 Jun 2023

Due:

28 Jun 2023

Completion:

04 Jul 2023

Appeal Window opens

Completed

Start:

28 Jun 2023

Due:

04 Jul 2023

Completion:

04 Jul 2023

Appeal Window closes

Completed

Start:

04 Jul 2023

Due:

18 Jul 2023

Completion:

18 Jul 2023
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 4.0.0_Superseded
Included changes Affected REC Items
R0044 MHHS Programme Changes required to Central Switching Service
  • Schedule 1 - Interpretations and Definitions
  • Schedule 27 - RMP Lifecycle
R0173 Improvements to the Theft Detection Incentive Scheme (TDIS)
  • Schedule 1 - Interpretations and Definitions
  • Schedule 7 - Energy Theft Reduction
R0209 Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 27 - RMP Lifecycle
  • Schedule 28 - Related Metering Points
  • Schedule 29 - Address Management
  • Schedule 9 - Qualification and Maintenance
  • Schedule 12 - Data Access
  • Schedule 24 - Switching Data Management
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Standards Definition Document
  • Data Item Catalogue
  • Market Message Catalogue
R0222 ESME ID Update Rejections
R0223 Reconciliation of Unallocatable Transactions Review
  • Schedule 11 - Prepayment Arrangements
R0241 MHHS Incremental Changes for go live
  • Schedule 15 - Metering Accreditation
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 27 - RMP Lifecycle
  • Schedule 28 - Related Metering Points
  • Schedule 29 - Address Management
  • Schedule 9 - Qualification and Maintenance
  • Schedule 24 - Switching Data Management
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Standards Definition Document
  • Data Item Catalogue
  • Market Message Catalogue
R0259 Update to R0173 Implementation Date
R0264 Data Specification Housekeeping
R0083 Changes to Supply Number Format for MHHS
R0097 Consequential Change for CSS Smart Meter Data Retriever Appointments
  • Data Item Catalogue
  • Market Message Catalogue
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As the CSS Provider, I want to be able to identify which appointment messages received from ERDS require a response, so that I can confirm whether the appointment was successfully made in SMDSP
  2. As the ERDS Provider, I want to be able to indicate which appointment messages I need to receive a response for, so that I can understand which appointments have been successful in the SMDSP
  3. As an Electricity Supplier, I want Supplier appointments in the ERDS to match those held in SMDSP
Proposed Solution Document
Document title
R0097 Proposed Solution (Initial Assessment) 14.03.23
Upload document
R0097 Proposed Solution (Initial Assessment) 14.03.23.zip
Archive
Off
Document title
R0097 Proposed Solution (Impact Assessment) 22.03.23
Upload document
R0097 Proposed Solution (Impact Assessment) 22.03.23.zip
Archive
Off
Document title
R0097 Proposed Solution (Consultation) 17.05.23
Upload document
R0097 Proposed Solution (Consultation) 17.05.23.zip
Archive
Off
Document title
R0097 Draft Legal Text (Consultation) 17.05.2023
Upload document
Attachment B_R0097 Proposed Data Specification Changes_v1.6.pdf
Archive
Off
Problem Statement
The implementation of Change Proposal R0044, will result in the Central Switching Service (CSS) providing an asynchronous response to the Electricity Retail Data Service (ERDS) upon a successful, or unsuccessful Smart Meter Data Retriever (SMDR) appointment within the SMDSP. This will significantly increase the volume of CSS messages, as there is currently no mechanism for the CSS to recognise when a response is required. The increased volume could have a significant impact on central system performance.
SME
SME Role
Lead Technical Analyst
Workgroup
Workgroup(s)
R0097 - Change Proposal Form downloadable version 20.02.2023
R0097 - Change Proposal Plan v2.0 (Approved) 21.03.2023
R0097 - Initial Assessment Report v2.0 (Approved) 21.03.23
R0097 - Preliminary Change Report v1.0 (For Consultation) 19.05.2023
R0097 Consolidated Consultation Responses v1.0 PUBLIC 15.06.2023
R0097 - Final Change Report v2.0 (Post-Vote) 04.07.2023
Company Name
REC Technical Services
Review status
Review required

ERDS Upload File in the Data Specification and clarification of cancellation code

Date of latest update
Type
Change
ID
R0086
Priority
Urgent
No
Latest Update
06/11/2023 - Withdrawal adoption window closed.
Summary
The MPAS/ERDS Upload file has historically been a part of the Data Specification however during transition from the MRA, the process has been omitted. This change seeks to restore the file to the specification. Secondly, the file previously provided a cancellation reason code for Switches. Under the current REC arrangements (i.e. since CSS go live) Reason codes are not provided and have been defaulting to W which indicated a reason of “withdrawn” which may now be misleading. This Change Proposal has been raised to address these issues
Proposer
admin
Status
Implementation Status
Date Raised
Solution Development
Stages Selection
R0086 - Change Proposal Form (downloadable version)
Company Name
-
Review status
Review required

Introduction of CSS refresh functionality

Date of latest update
Type
Change
ID
R0067
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/12/2023- This Change was implemented as part of the 6 December 2023 Extraordinary Release
Summary
CSS Market Messages sent by the Central Switching Service (CSS) to Switching Data Service Providers (SDSP) are either not being received, being received after Gate Closure, or are being received out of the order that they were originally sent in. This Change Proposal seeks to introduce a refresh functionality to mitigate these issues.
Proposer
Michael Taylor
Change Plan

Solution Analysis and Development

Completed

Start:

29 Aug 2022

Due:

19 Oct 2022

Completion:

19 Oct 2022

Service Provider Impact Assessment

Completed

Start:

19 Oct 2022

Due:

29 Mar 2023

Completion:

29 Mar 2023

Consultation

Completed

Start:

11 Apr 2023

Due:

09 May 2023

Completion:

28 Apr 2023

Preliminary Change Report Issued

Completed

Start:

29 Mar 2023

Due:

11 Apr 2023

Completion:

05 Apr 2023

Final Change Report Issued

Completed

Start:

Due:

Completion:

21 Jun 2023

Responsible Committee Decision

Completed

Start:

09 May 2023

Due:

28 Jun 2023

Completion:

28 Jul 2023
Impacted Consumers
Impacted REC Parties and Market Participants
Status
Implementation Date
Status Superseded
EMAR Version 3.7.0_Live

Documents

Name Version Last updated Actions
160.82 KB
Version 1.0 - 02 Nov 2026 PDF - 160.82 KB
1.0 02 Nov 2026
1.0 02 Nov 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
  2. As the CSS Provider I want the messages I send to SDSPs to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience. As the CSS Provider, I want the functionality to be available for SDSPs to automatically resolve issues when messages are not received in the correct order or are received after Gate Closure, so that this work does not have to be done manually.
  3. As an SDSP, I want to be able to detect when I have not received the expected CSS messages, so that I am able to request that the missing messages are sent to me to process. As an SDSP I want to be able to request a refresh of CSS messages when they are not received in the correct order or they are received after Gate Closure, so that I am able to maintain an accurate reflection of the current Switch status and minimise impacts on CSS Users and Consumers.
Proposed Solution Document
Document title
R0067 - Legal Text at PCR
Upload document
R0067 - Legal Text at PCR.zip
Archive
Off
Document title
R0067 - Legal Text at FCR
Upload document
R0067 - Legal Text at FCR.zip
Archive
Off
Document title
R0067 - Cost Benefit Analysis and Conclusions v3.0
Upload document
R0067 - Cost Benefit Analysis and Conclusions v3.0.pdf
Archive
Off
Problem Statement
CSS messages not received by the SDSPs in the order they were sent or received, or after Gate Closure, can be difficult to detect and often require significant manual effort to resolve. This issue can directly impact Consumer switching experiences causing disruption and possible delays.
SME
SME Role
Lead Technical Analyst
R0067 - Change Proposal Form
R0067 - Consolidated Consultation Responses
R0067 - Change Proposal Plan v1.0
R0067 - Initial Assessment Report v1.0
R0067 - Change Proposal Plan v2.0 (Approved) 07.03.2023
R0067 - Change Proposal Plan v3.0 04.04.2023
R0067 - Preliminary Change Report v2.0 (Issued for Consultation) 14.04.2023
R0067 - Final Change Report (Post-Vote) 28.06.2023
Company Name
-
Review status
Review required

REC V3.0

Date of latest update
Type
Change
ID
R0041
Change Category
Urgent
Yes
Latest Update
-
Summary
-
Proposer
Alasdair MacMillan
Change Plan

Legal text baselined

Completed

Start:

10 Apr 2022

Due:

13 May 2022

Completion:

13 May 2022

Final Change Report Issued

Completed

Start:

13 May 2022

Due:

20 May 2022

Completion:

20 May 2022

Responsible Committee Decision

Completed

Start:

20 May 2022

Due:

07 Jun 2022

Completion:

07 Jun 2022

Authority Determination (Original)

Completed

Start:

07 Jun 2022

Due:

20 Jun 2022

Completion:

17 Jun 2022

Authority Determination (revoked and re-issued)

Completed

Start:

20 Jun 2022

Due:

29 Jun 2022

Completion:

29 Jun 2022
Impacted Consumers
Status
Implementation Date
Status Superseded
EMAR Version 3.0.0_Superseded
Included changes Affected REC Items
R0038 Performance Assurance Report Catalogue Changes as a consequence of REC V3.0
R0041 REC V3.0
  • REC Main Body
  • Schedule 1 - Interpretations and Definitions
  • Schedule 14 - Metering Operations
  • Schedule 19 - Market Exit and Supplier of Last Resort
  • Schedule 5 - Change Management
  • Schedule 27 - RMP Lifecycle
  • ASPCoP (since removed)
  • Schedule 28 - Related Metering Points
  • Schedule 29 - Address Management
  • Schedule 9 - Qualification and Maintenance
  • Schedule 2 - REC Transition Schedule
  • Schedule 26 - Switching Service Management
  • Schedule 12 - Data Access
  • Schedule 10 - Charging Methodology
  • Schedule 23 - Registration Services
  • Schedule 30 - Resolution of Consumer Facing Switching and Billing Issues
  • Schedule 25 - Central Switching Service
  • Standards Definition Document
  • Data Access Matrix (Electricity)
  • Data Access Matrix (Gas)
  • Data Item Catalogue
  • Market Message Catalogue
R0042 Performance Assurance Board Terms of Reference
  • Performance Assurance Board - Terms of Reference
R0045 Changes to SDEP Messages and Schedule numbering for REC V3.0
  • Market Message Catalogue

Documents

Name Version Last updated Actions
258.97 KB
Version 1.0 - 02 Nov 2026 PDF - 258.97 KB
1.0 02 Nov 2026
257.76 KB
Version 1.0 - 02 Nov 2026 DOCX - 257.76 KB
1.0 02 Nov 2026
219.4 KB
Version 1.0 - 16 Nov 2026 PDF - 219.4 KB
1.0 16 Nov 2026
1.65 MB
Version 1.0 - 02 Nov 2026 PPTX - 1.65 MB
1.0 02 Nov 2026
6.74 MB
Version 1.0 - 02 Nov 2026 PPTX - 6.74 MB
1.0 02 Nov 2026
9.01 MB
Version 1.0 - 02 Nov 2026 PPTX - 9.01 MB
1.0 02 Nov 2026
3.89 MB
Version 1.0 - 02 Nov 2026 PPTX - 3.89 MB
1.0 02 Nov 2026
1.0 02 Nov 2026
16.78 KB
Version 1.0 - 02 Nov 2026 XLSX - 16.78 KB
1.0 02 Nov 2026
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As a Consumer, I want to be able to successfully switch my Energy Supplier with minimal delay or hassle, so that I can start to receive the service and tariff from my chosen Energy Supplier at the earliest opportunity.
  2. As the Authority, I want the necessary changes made to the Retail Energy Code to introduce the obligations, processes and provisions for the new switching arrangements, to enable the successful transition to enduring governance and operational arrangements.
  3. As a REC Party, I want to be clear on the obligations I need to meet and the processes I need to follow post CSS go live, to ensure my organisation is ready for the introduction of the new switching arrangements.
  4. As a REC Service Provider, I want to be clear on the obligations, processes and service standards that I need to meet, to ensure my organisation is ready for the introduction of the new switching arrangements.
Proposed Solution Document
Document title
REC V3.0 Baselined documents
Upload document
R0041 Legal Text.zip
Archive
Off
Document title
REC v3.0 Baselined documents (REC Portal)
Archive
Off
Problem Statement
Changes are required to the REC, to ensure the appropriate obligations, processes and provisions are defined within the REC at CSS go-live, enabling successful transition to enduring governance and operational arrangements developed as part of Ofgem’s Switching Programme.
SME
SME Role
Lead Technical Analyst
SME User
beth.brown@capgemini.com
R0041 - Change Proposal Form
Letter from the Authority to the REC Code Manager - REC V3.0 Authority Change Proposal
R0041 - Change Proposal Plan v1.0 (Approved)
R0041 - Initial Assessment Report v2.0 (Approved)
R0041 - Final Change Report v3.0 (Post-Vote)
R0041 Authority Decision
Company Name
Ofgem
Review status
Review required

Electricity Enquiry Service API Service Status

Date of latest update
Type
Change
ID
R0013
Change Category
Change Path
Priority
Urgent
No
Latest Update
-
Summary
-
Proposer
admin
Change Plan

Initial Assessment Report published

Completed

Start:

11 Oct 2021

Due:

05 Nov 2021

Completion:

05 Nov 2021

Analysis and Solution development activity

In Progress

Start:

05 Nov 2021

Due:

13 Jan 2022

Completion:

Service Provider Impact Assessment completion

Not Started

Start:

13 Jan 2022

Due:

15 Feb 2022

Completion:

REC Party Impact Assessment completion

Not Started

Start:

15 Feb 2022

Due:

23 Mar 2022

Completion:

Preliminary Change Report issued

Not Started

Start:

23 Mar 2022

Due:

20 Apr 2022

Completion:

Technical Expert Panel review

Not Started

Start:

20 Apr 2022

Due:

27 Apr 2022

Completion:

Consultation starts

Not Started

Start:

27 Apr 2022

Due:

05 May 2022

Completion:

Consultation ends

Not Started

Start:

05 May 2022

Due:

26 May 2022

Completion:

Final Change Report issued

Not Started

Start:

26 May 2022

Due:

21 Jun 2022

Completion:

Technical Expert Panel decision

Not Started

Start:

21 Jun 2022

Due:

29 Jun 2022

Completion:

Impacted Consumers
Impacted REC Services
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed solution summary
  1. As an EES User (organisation), I want a method of integrating the service status of the EES API with my systems, so that in the event of EES API outage or disruption I do not trigger unnecessary internal diagnostic activity of my IT systems and processes, and I can initiate appropriate mitigation activity to reduce impacts to my systems and/or the services I provide.
Problem Statement
EES Users do not have a method of integrating the service status of the EES API with their systems. EES Users could experience disruption in their systems/services, caused by EES API disruption or outage. EES Users are not able to automatically identify the root cause of API outages/disruption and may initiate unnecessary internal diagnostic activity after seeing disruption in their systems/services
Stages Selection
SME
SME Role
Lead Technical Analyst
R0013 - Initial Assessment Report v1.0 (Approved)
R0013 - Change Proposal Plan v1.0 (Approved)
Company Name
Switchcraft
Review status
Review required