Domestic Elective HH Switching
Date of latest update
Type
Change
ID
R0227
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
This change aims to remove unnecessary blocks to Consumer Switching, where a Domestic Consumer is registered as elective Half Hourly (HH) with the Losing Supplier, but the Gaining Supplier does not offer this.
Change Plan
Proposal plan approved at Change Panel
Completed
Start:
Due:
Completion:
04 Feb 2025Extension to Plan approved by Change Panel
Completed
Start:
Due:
Completion:
15 Apr 2025Change Report (Final Recommendation) approved by Change Panel
Completed
Start:
Due:
Completion:
17 Jun 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
07 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0152 | Revision to the Consolidated Metering Code of Practice (CoMCoP) |
|
| R0157 | Removal of Facsimile as a Method of Code Communication |
|
| R0191 | Introduction of SLA for Supplier De-Registration on Disconnected Meters |
|
| R0205 | Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches | |
| R0212 | Protecting Crimestoppers and their Contacts | |
| R0215 | Schedule 30 Switch Meter Reading Problems - Rejections and Timings |
|
| R0060 | ERDS Service Definition timezone correction |
|
| R0232 | Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) | |
| R0243 | Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership |
|
| R0248 | REC Changes to tie in with DCP451 - Suspending Registrations |
|
| R0254 | Non-Domestic Change of Occupier Reporting (R0155 Solution) | |
| R0255 | Terms of Reference Updates | |
| R0257 | Change to REC for Data processing outside of EEA | |
| R0263 | Sharing Confirmed Energy Theft Data with the BSCCo |
|
| R0269 | Schedule 5 – Change Management: Clarity and Typographical Review |
|
| R0279 | Housekeeping November 2025 |
|
| R0227 | Domestic Elective HH Switching |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0227 - Proposed Legal Text (IA) - Schedule 23 - Registration Services.doc
Upload document
I0227 - Schedule 23 Registration Services - Paragraph 11 Mark up - 28 February 2025(114145004).docx
Archive
Off
Document title
I0227 Schedule 23 pre MHHS version
Upload document
I0227 Schedule 23 pre MHHS version.pdf
Archive
Off
Document title
I0227 Schedule 23 post MHHS version
Upload document
I0227 Schedule 23 post MHHS version.pdf
Archive
Off
Problem Statement
There are issues when a Domestic Consumer intends to Switch Suppliers, but their MPAN is registered as elective HH with their current Supplier, and this is not offered by the Gaining Supplier. This can cause delays with Switching for Consumers.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Issues Proposal Form - Attachment 1. Electralink Post.docx
Issue Proposal form
I0227 - Change Report (Proposal Plan - Approved) v1.0 04.02.2025
I0227 - Consolidated Party Impact Assessment Responses (Non-Confidential) 11.04.2025
I0227 Extension to Plan V1.0 Approved 15.04.2025
R0227 Change Report (For Consultation) V1.0
R0227 Consolidated Consultation Responses v1.0
R0227 Change Report (Final Recommendation) V1.0 Approved 17.06.25
Company Name
octopus energy
Review status
Review required
In-year CRS budget amendment
Date of latest update
Type
Change
ID
R0226
Urgent
No
Latest Update
21/01/25 - Change Panel approved final recommendation for immediate implementation.
Summary
DCC has identified that the CRS budget for the current Financial Year (2024-2025) can be reduced, and as per the Code, a REC Change Proposal must be raised for the agreed budget to be amended.
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
Change Proposal Form
R0226 Change Report - Final Recommendation approved.
Company Name
DCC
Review status
Review required
Clarification on TDIS portfolio transfers on sale
Date of latest update
Type
Change
ID
R0225
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the REC Release on 27 June 2025.
Summary
The current wording of the Energy Theft Reduction Schedule has wording on the transfer of theft targets on portfolio sale, however which sales would qualify is ambiguous.
Change Plan
Change Plan at Change Panel
Clarification on TDIS portfolio transfers on sale > Change Plan
Start:
27 Nov 2024Due:
21 Jan 2025Completion:
21 Jan 2025Change Report (Consultation) to Change Panel
In Progress
Start:
21 Jan 2025Due:
04 Feb 2025Completion:
Impacted REC Documents
Status
Implementation Date
28 June 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0155 | Change of Occupier: Evidentiary Standards and Timescales |
|
| R0193 | Add Enumeration Values to the DI51035 - Communications Provider Data Item |
|
| R0202 | Performance Assurance Report Catalogue Updates (MHHS) | |
| R0225 | Clarification on TDIS portfolio transfers on sale |
|
| R0233 | Introduction of an Energy Theft Unit (ETU) under the REC | |
| R0234 | Introduction of an energy theft Referral Assessment Service under the REC | |
| R0236 | REC Party Auto de-accession proposal |
|
| R0238 | Performance Assurance Reporting Catalogue - Annual Review | |
| R0249 | Correction to Change Management Schedule regarding sub-committee voting |
|
| R0258 | Housekeeping June 2025 | |
| R0080 | Improvements to ‘Failed to Deliver’ CSS Messages |
|
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0225 - Legal Drafting
Upload document
I0225 - Legal Drafting (3).docx
Archive
Off
Document title
Schedule 7 Energy Theft Reduction (based on v3.0) Legal Drafting
Upload document
Schedule 7 Energy Theft Reduction (based on v3.0) Legal Drafting.doc
Archive
Off
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Change/ Issue form
I0225 - Change Report - Proposal Plan (Approved 21/01/2025)
R0225 Change Report (Consultation)
R0225 Consolidated Consultation Responses
R0225 Change Report (Final) Post-vote
Company Name
REC Code Manager
Review status
Review required
Reconciliation of Unallocatable Transactions Review
Date of latest update
Type
Change
ID
R0223
Change Category
Change Path
Priority
Urgent
No
Latest Update
22/09/25 - This Change Proposal has been implemented as part of the MHHS M8 22 September 2025 REC Release.
Summary
The process for Reconciliation of Unallocatable Transactions is set out in Section 10 of Schedule 11. During the most recent reconciliation delivery (the gas process from July 2024) several areas of improvement were identified, critically a lack of clarity regarding historic Supplier Licences and how to include or exclude them from the calculations. The Code Manager believes that this lack of clarity and past precedent would lead to material impact on one or more Party.
Change Plan
Findings from Information Request were presented at Change Issues Group
Completed
Start:
Due:
Completion:
06 Feb 2025Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
MHHS Programme Milestone M8 (Code changes delivered)
| Included changes | Affected REC Items | |
|---|---|---|
| R0044 | MHHS Programme Changes required to Central Switching Service |
|
| R0173 | Improvements to the Theft Detection Incentive Scheme (TDIS) |
|
| R0209 | Implementation of Market-wide Half Hourly Settlement (MHHS) Arrangements |
|
| R0222 | ESME ID Update Rejections | |
| R0223 | Reconciliation of Unallocatable Transactions Review |
|
| R0241 | MHHS Incremental Changes for go live |
|
| R0259 | Update to R0173 Implementation Date | |
| R0264 | Data Specification Housekeeping | |
| R0083 | Changes to Supply Number Format for MHHS | |
| R0097 | Consequential Change for CSS Smart Meter Data Retriever Appointments |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- A review of the process with specific regard to: - Clarity within the process regarding historic Supplier Licences - Alignment between fuels - Re-introducing an independent audit.
Proposed Solution Document
Document title
Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.2025
Upload document
Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.docx
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (I0223 - Party Impact Assessment) 05.06.docx
Archive
Off
Document title
Schedule 11 - Prepayment Arrangements (R0223 - Consultation) 24.07.2025
Upload document
Schedule 11 - Prepayment Arrangements (R0223 - Consultation).docx
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Consultation) 24.07.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Consultation).docx
Archive
Off
Document title
Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025
Upload document
Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025.pdf
Archive
Off
Document title
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025
Upload document
Extract - Schedule 11 - Prepayment Arrangements (R0223 - Final Recommendation) 18.08.2025.pdf
Archive
Off
Problem Statement
During the most recent reconciliation delivery (the gas process from July 2024) several areas of improvement were identified, critically a lack of clarity regarding historic Supplier Licences and how to include or exclude them from the calculations.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
I0223 - Submission Form
I0223 - Information Request Responses
I0223 - Change Report (Proposal Plan) V2.0 (Approved) 20.05.2025
I0223 - Proposal Plan Update V1.0 (Approved) 20.05.2025
I0223 - Change Report (Impact Assessment) V1.0 (06.06.2025)
I0223 - Party Impact Assessment Consolidated Responses V1.0 (11.07.2025)
R0223 - Change Report (For Consultation) V1.0 (24.07.2025)
R0223 - Change Report (Final Recommendation) V2.0 (Approved) 02.09.2025
Company Name
Code Manager
Review status
Review required
Housekeeping Change for R0206
Date of latest update
Type
Change
ID
R0220
Change Path
Urgent
No
Latest Update
08/11/2024 - This Change Proposal has been implemented as part of the November 2024 REC Release.
Summary
This is a Housekeeping Change Proposal subject to the Housekeeping Change Proposal process, rather than the standard Change Process. The nature of the change is that it makes non-material changes to the REC Products to correct typographical, grammatical or consistency errors, and provides an opportunity to introduce necessary clarifications. This change proposal is looking to fix an error identified with R0206 Cross code change to align with BSC CP1598. BSC CP1598 was raised to add six scenario variants to four Market Messages that have been identified as missing. The REC Energy Market Data Specification contains a number of Market Message scenario variants used in BSC processes. This REC Change Proposal has been raised to align with CP1598 and ensure these scenario variants are added to the REC Data Specification. The legal text for R0206 approved at Change Panel on 15 October 2024, had a change to one of the scenario variants (SV00474) that was not clear as it was not red lined. The change was to the owner of the scenario variant from the Retail Energy Code Company (RECCo) to the Balancing and Settlement Code Company (BSCCo). The red lining for SVcccc was also incorrect as it deleted RECCo as the owner when in fact it is a new scenario variant so no previous owner. The owner as BSCCo that was approved, is correct.
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R220_R0206 HK Solution Document v1.0.pdf
Upload document
R220_R0206 HK Solution Document v1.0.pdf
Archive
Off
Stages Selection
R0220 - Housekeeping Change Report
Company Name
-
Review status
Review required
Proposal to Enable Broader Use of Retail Energy Location (REL) Data for Non-Switching Applications
Date of latest update
Type
Issue
ID
I0218
Change Category
Change Path
Priority
Urgent
No
Latest Update
05/11/2026 - Service Provider Impact Assessments are in progress and will close on 06 November 2026. A refreshed Code Manager Initial Assessment will be carried out given the change of scope since the original assessment.
Summary
The problem being addressed is the current restriction within the Retail Energy Code (REC) that limits the use of Retail Energy Location (REL) data solely to switching purposes. This restriction prevents the full utilisation of REL data, which could be valuable for a broader range of operational, regulatory, and industry applications. Key Issues: - Currently, REL data, enriched with Unique Property Reference Numbers (UPRNs), is available via the Electricity and Gas Enquiry Services. However, Schedule 29 (Address Management) of the REC restricts its use to switching purposes only, preventing its use in other important industry initiatives. - Various industry stakeholders, including REC and non-REC data requestors as well as Ofgem (the regulator), have expressed a strong interest in utilising REL data for non-switching purposes. The restriction is seen as a limitation, especially for initiatives that require accurate property data to support wider operational and regulatory functions. - By restricting the use of REL data to switching, stakeholders are unable to fully leverage it for improving operational efficiency, regulatory compliance, and overall service delivery. Lifting this restriction would enable the wider use of REL data, allowing stakeholders to benefit from its full potential across various non-switching applications.
Change Plan
Proposal plan approved at Change Panel
Completed
Start:
Due:
Completion:
21 Jan 2025Extension to Proposal Plan approved by REC Change Panel
Completed
Start:
Due:
Completion:
06 May 2025Update to Plan approved at Change Panel
Completed
Start:
Due:
Completion:
18 Nov 2025Extension to Plan approved at Change Panel
Completed
Start:
Due:
Completion:
04 Aug 2026Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- RECCo would acquire a AddressBase Core license from Ordinance Survey and the REC would be updated to allow parties to take full advantage of this data. In order for parties to use the REL data, they would need to acquire an AddressBase Premium license from Ordinance Survey or other relevant license.
Problem Statement
Retail Energy Location (REL) data currently is not permitted for uses such as improving customer service and streamlining internal processes. This means that stakeholders, such as Ofgem and data requestors, have been unable to benefit from this data and Consumers are therefore unable to benefit from the full potential use of their data.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
rosalind.timperley
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
Issue proposal form
I0218 - Change Report (Proposal Plan) V2.0 (07.05.2025)
I0218 - Extension to Plan V1.0 (06.05.2025) (Approved)
I0218 - Update to Plan V2.0 (09.09.2025) (Approved)
I0218 - Update to Plan V3.0 (18.11.2025) Approved
I0218 Extension to Plan V1.0 Pre-Approval
I0218 - Extension to Plan V2.0 (04.08.2026) Approved
Company Name
RECCo
Review status
Review required
Schedule 30 Switch Meter Reading Problems - Rejections and Timings
Date of latest update
Type
Change
ID
R0215
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
The Switch Meter Reading Problems processes do not appropriately describe the use of rejections. This inhibits Parties from operating the process as intended and may cause unnecessary delay to the production of an accurate and agreed Switching Meter Reading. Additionally, the Performance Assurance Reporting Catalogue (PARC) is missing key data items to allow Performance Assurance to more accurately assure Party performance against Risk Drivers 5.6 and 5.8. Rejection reasons do not appear to be being reviewed, nor are they understood to be end statuses for the process.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
07 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0152 | Revision to the Consolidated Metering Code of Practice (CoMCoP) |
|
| R0157 | Removal of Facsimile as a Method of Code Communication |
|
| R0191 | Introduction of SLA for Supplier De-Registration on Disconnected Meters |
|
| R0205 | Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches | |
| R0212 | Protecting Crimestoppers and their Contacts | |
| R0215 | Schedule 30 Switch Meter Reading Problems - Rejections and Timings |
|
| R0060 | ERDS Service Definition timezone correction |
|
| R0232 | Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) | |
| R0243 | Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership |
|
| R0248 | REC Changes to tie in with DCP451 - Suspending Registrations |
|
| R0254 | Non-Domestic Change of Occupier Reporting (R0155 Solution) | |
| R0255 | Terms of Reference Updates | |
| R0257 | Change to REC for Data processing outside of EEA | |
| R0263 | Sharing Confirmed Energy Theft Data with the BSCCo |
|
| R0269 | Schedule 5 – Change Management: Clarity and Typographical Review |
|
| R0279 | Housekeeping November 2025 |
|
| R0227 | Domestic Elective HH Switching |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0215 Schedule 30 v0.1
Upload document
I0215 Schedule 30 v0.1 for portal.pdf
Archive
Off
Document title
I0215 Schedule 30 v0.1 - pre MHHS version
Upload document
I0215 Schedule 30 v0.1 for portal (1).pdf
Archive
Off
Document title
I0215 Schedule 30 v0.1 - post MHHS version
Upload document
I0215 Schedule 30 v0.1 MHHS drafting.pdf
Archive
Off
Problem Statement
Suppliers may interact with the Missing Switch Read process in a way that is operationally standard for them, but not reflected in the Code. This means that the D0300 or SAR may either be escalated unnecessarily (including Performance Assurance checks), or may not be responded to, whilst still resolving the overall issue.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
beth.brown@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
RECRIG_24_0308 - Meeting Notes.pdf
Change Issue Proposal Form
RECRIG_24_0614 - Meeting Notes.pdf
I0215 Change Report (Plan) (Approved) V1.0 17.12.24
I0215 Rebaselined Plan v1.0 Approved 25.03.25
I0215 Consolidated Impact Assessment Responses v1.0
R0215 Change Report (For Consultation) V1.0
R0215 Consolidated Consultation Responses v1.0
R0215 Change Report (Final Recommendation) V1.0 Approved 17.06.25
Company Name
Code Manager
Review status
Review required
Multiple Switch Requests Increasing Objection Rate
Date of latest update
Type
Issue
ID
I0214
Change Category
Change Path
Priority
Urgent
No
Latest Update
20/05/2025 - the Code Manager has withdrawn this Issue, as there are no adequate solution options and minimal Consumer detriment. The adoption window has closed.
Summary
REC Parties have told the Code Manager that they are seeing multiple registrations attempts (10 plus attempts on consecutive days in some instances) on individual MPxNs. They are concerned about Consumer detriment as those trying to switch are not getting time to review objection related communications from their current Supplier to allow them to act and resolve the issue. This was initially presented as a non-domestic issue, but initial Code Manager investigations have also highlighted potential concern around proposed domestic transfers as well. There is also a risk of Party Performance impacts with initial analysis flagging potential impacts on Performance Assurance Risk Drivers, 8.9, 8.10 & 8.11.
Change Plan
Presented at Change Issues Group
Completed
Start:
Due:
Completion:
06 Mar 2025Impacted Consumers
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Non-Domestic Consumers are having their Switch experience affected by multiple Objection attempts following a single initial attempt to register for their supply by a prospective gaining Supplier. This results in Consumer detriment, as multiple Objections result in repeated rounds of communications to the Supplier. This results from automated Registration systems employed by Non-Domestic Suppliers.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME User
maxime.van-eyseren@capgemini.com
SME Role
Lead Assurance Analyst
SME User
vaishnsharma@deloitte.co.uk
Change Issue Proposal Form
I0214 Change Report (Plan) (Approved) V1.0 17.12.24
I0214 Rebaselined Plan v1.0 Approved 28.03.25
Company Name
Code Manager
Review status
Review required
Introducing Third Party Intermediary (energy broker) assurance and accreditation (Alternate)
Date of latest update
Type
Change
ID
R0137A
Change Category
Urgent
No
Latest Update
16/05/2025 - the Authority have published their decision to reject R0137 and R0137A.
Summary
This change seeks to expand the obligation for Energy Suppliers to only work with TPIs who are adhering to principles as set out in the REC TPI Code of Practice to all Non-Domestic Consumers. It also looks to reduce the burden on Energy Suppliers having to perform their own audits by introducing a REC Services Accreditation Scheme and allowing companies to qualify as an Industry-Recognised Accreditation Body.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Legal Text R0137A Consultation
Upload document
Legal Text R0137A Consultation.zip
Archive
Off
Document title
Legal Text for R0137A - Final
Upload document
R0137A Final Legal Text.zip
Archive
Off
Problem Statement
Non-Domestic Consumers have more limited protections than Domestic and Microbusiness Consumers in the energy market, and so may not always experience best practice from all parties they interact with. The aim is to expand these protections while limiting the audit burdens on Suppliers and TPIs.
Stages Selection
SME
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
R0137A Change Proposal Form
Authority decision on REC modification proposal R0137 and R0137A
Company Name
REC Code Manager
Review status
Review required
Creation of a Mechanism to Allow Third Parties to Report Objection Activity
Date of latest update
Type
Issue
ID
I0213
Change Category
Change Path
Priority
Urgent
No
Latest Update
15/07/2025 - The Code Manager has rejected Issue I0213. This Issue has been deemed out of scope of the REC and has been rejected following a legal review. This decision was ratified by the REC Change Panel at their meeting on 15 July 2025.
Summary
Presently only industry parties can raise the matter of non-compliant or unwarranted objections activity that a supplier may be participating in. This Issues has been raised to request RECCo to consider accepting notice and evidence (that can be acted upon) from qualifying 'non industry' parties, from third party consultants and brokers.
Change Plan
Proposal Plan Approved at REC Change Panel
Completed
Start:
Due:
Completion:
06 May 2025Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- I0213 has been raised with a suggestion that the Code Manager should consider accepting notice and evidence from qualifying non-industry Parties, including Third Party consultants and brokers (Third Party Intermediaries (TPIs)). A possible solution for this may include a new submission page, or form, on the REC Portal, that would allow Third Parties to submit evidence of non-compliant Objection activity.
Problem Statement
There is currently not a method for Third Parties, who may be involved in the Switching process, to report non-compliant Objection activity. Non-Compliant Objection activity can result in time consuming procedures for Consumers, creating unnecessary engagement with Energy Suppliers, and may result in a financial burden.
Stages Selection
Stages Selection
I0213 - Change Proposal Form
I0213 - Change Report (Proposal Plan) 25.04.2025 (Approved)
I0213 - Solution Development Report (for Party impact assessment) V1.0 (16.05.2025)
I0213 Consolidated Impact Assessment Responses V1.0 (Non-Confidential) 07.07.2025
Company Name
Energy Consultants Association
Review status
Review required