Legal text to support REC Change R0180
Date of latest update
Type
Change
ID
R0336
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
REC Change R0180 “Clarity on use of on hold for switching issues, including the obligations of CSS Users” implements a technical solution for the closure of certain ticket raised to the Switching Operator when no response has been received. This Change Proposal contains the legal text to support R0180.
Change Plan
Change Report (Proposal Plan) approved by Change Panel ex-committee
Completed
Start:
Due:
Completion:
19 Aug 2026Solution presented at Technical Expert Panel
Completed
Start:
Due:
Completion:
26 Aug 2026Presented at Change Issues Group
Completed
Start:
Due:
Completion:
03 Sep 2026Impacted REC Documents
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
06 November 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0180 | Clarity on use of on hold for switching issues, including the obligations of CSS Users |
|
| R0207 | Import / Export MOA Charging Clarification |
|
| R0253 | Theft - DNO/Networks not providing photos |
|
| R0261 | Addition of Export flag in D0303 flows | |
| R0266 | REC Data Specification Clarifications |
|
| R0317 | Number of Displayed Register Digits Data Item linkage | |
| R0328 | Removal of D0383 & D0384 requirements from Sharing MTDs process |
|
| R0336 | Legal text to support REC Change R0180 |
|
| R0343 | MSC - Amending Statement Production Timescales | |
| R0345 | Housekeeping November 2026 |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 11 Nov 2026 | ||
| 1.0 | 11 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0336 Schedule 26 Switching Service Management - for consultation
Upload document
R0180 Schedule 26 Switching Service Management - for consultation.docx
Archive
Off
Document title
R0336 Switching Operator (SO) Service Definition - for consultation
Upload document
R0180 Switching Operator (SO) Service Definition - for consultation.docx
Archive
Off
Problem Statement
R0180 Clarity on use of on hold for switching issues, including the obligations of CSS Usersintroduces a technical solution for the closure of certain tickets raised to the Switching Operator when no response has been received. Without supporting legal text, these obligations and expectations are not documented within the REC.
Stages Selection
SME
SME Role
Lead Technical Analyst
R0336 submission form
R0336 Change Report (Proposal Plan and Consultation) V1.0
R0336 Consolidated Consultation Responses v1.0
R0336 Change Report (Final Recommendation) v1.0 Approved 30.09.2026
Company Name
REC Code Manager
Review status
Review required
Use of REL Data to Support Key Regulations
Date of latest update
Type
Change
ID
R0324
Change Category
Change Path
Priority
Urgent
No
Latest Update
29/10/2026 - The Change Report (Final Recommendation) in line with the Code Manager recommendation, the REC Technical Expert Panel approved this Change Proposal for implementation on 26 February 2027. The appeal window is open until 12 November 2026.
Summary
The REC Electricity Enquiry Service (EES) Service Definition and Electricity Data Access Matrix (DAM) limits access of REL data to the Authority. This Issues seeks to extend access to the Code Manager and government departments in Great Britain to facilitate key government reporting and REC processes.
Change Plan
Proposal Plan approved at Change Panel
Completed
Start:
Due:
Completion:
15 Sep 2026Final Recommendation approved at TEP
Completed
Start:
Due:
Completion:
28 Oct 2026Impacted REC Documents
Impacted REC Services
Status
Implementation Date
26 February 2027
| Included changes | Affected REC Items | |
|---|---|---|
| R0292 | Obligate Energy Suppliers to provide photo evidence of Theft in Conveyance to Network Parties | |
| R0322 | Erroneous Switch Review: I0237 Clarifications | |
| R0324 | Use of REL Data to Support Key Regulations |
|
| R0339 | REC Change to align with BSC CP Clarify Supplier obligations for IF-002 messages where a Switch is cancelled |
|
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0324 Draft Legal Text
Upload document
I0324 Draft Legal Text (1).zip
Archive
Off
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0324 submission form
I0324 Change Report (Proposal Plan and Consultation) v1.1 Pre-Approval
R0324 Change Report (Consultation) Approved 15.09.26
R0324 - Consolidated Consultation Responses v1.0
R0324 Change Report (Final Recommendation) v1.0 Pre Approval
R0324 Change Report (Final Recommendation) v2.0 Approved 28.10.26
Company Name
REC Code Manager
Review status
Review required
Number of Displayed Register Digits Data Item linkage
Date of latest update
Type
Change
ID
R0317
Change Category
Change Path
Priority
Urgent
No
Latest Update
06/11/26 - This Change Proposal has been implemented as part of the 6 November 2026 REC Release.
Summary
A Data Integration Platform (DIP) Data Item, DI-091 ‘Number of Displayed Register Digits’ that was implemented as part of MHHS has been incorrectly linked to the existing J0478 ‘Number of Register Digits’ in the Energy Market Data Specification, instead of the existing J2313 ‘Number of Displayed Register Digits’.
Status
Implementation Date
06 November 2026
| Included changes | Affected REC Items | |
|---|---|---|
| R0180 | Clarity on use of on hold for switching issues, including the obligations of CSS Users |
|
| R0207 | Import / Export MOA Charging Clarification |
|
| R0253 | Theft - DNO/Networks not providing photos |
|
| R0261 | Addition of Export flag in D0303 flows | |
| R0266 | REC Data Specification Clarifications |
|
| R0317 | Number of Displayed Register Digits Data Item linkage | |
| R0328 | Removal of D0383 & D0384 requirements from Sharing MTDs process |
|
| R0336 | Legal text to support REC Change R0180 |
|
| R0343 | MSC - Amending Statement Production Timescales | |
| R0345 | Housekeeping November 2026 |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 11 Nov 2026 | ||
| 1.0 | 11 Nov 2026 |
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed solution summary
- The proposed solution is to conduct a correction exercise to unlink the DIP Data Item DI-091 ‘Number of Displayed Register Digits’ from the Data Item J0478 and it should then instead be linked to the Data Item J2313.
Proposed Solution Document
Document title
R0317 Draft Legal Text 23.02.2026.zip
Upload document
R0317 Draft Legal Text 23.02.2026.zip
Archive
Off
Document title
R0317_Draft Legal Text (For Consultation)_v0.2
Upload document
R0317_Draft Legal Text (for Consultation)_v0.2.zip
Archive
Off
Document title
R0317_Draft Legal Text (For Final Recommendation)_v1.0
Upload document
R0317_Draft Legal Text (for Final Recommendation)_v1.0.zip
Archive
Off
Problem Statement
A linkage error has been identified as part of BSC CP1622 and REC Change Proposal R0300 where the DIP Data Item DI-091 has been incorrectly linked to the existing J0478 ‘Number of Register Digits’ in the EMDS at MHHS Go-Live, instead of the existing J2313 ‘Number of Displayed Register Digits’. As a result, contrary to the MHHS design and intended linkage, the EMDS incorrectly details the DI-091 in DIP interfaces, including the IF-005 and IF-006 (both REC-owned) and several other DIP Interfaces, even though the DIP reference appears correct (DI-091). It is important that EMDS is an accurate reflection of Market Messages and Data Items. Without correction this Issue may cause issues to future market entrants.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
R0317 submission form
R0317_Consolidated Consultation Responses_PUBLIC
R0317_Change Report (Final Recommendation) v1.0 Approved 27.05.26
Company Name
REC Code Managber
Review status
Review required
Addition of value 11 to data item J0418
Date of latest update
Type
Change
ID
R0310
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
To add value 11 to the valid set value for data item J0418 – Meter COP. Unable to update Meter technical details (MTD's), the D0268 flow, as specified under BSCP603/7 via the DTN as the AMVLP. The appointed agent will not be able to automatically process or upload the flows received to their systems due to validation errors.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0310 submission form
R0310 Proposed changes to REC Data Specification
R0310 Change Report (Proposal Plan and Consultation) Approved 17.03.26
R0310 Consolidated Consultation Responses
R0310 Change Report (Final Recommendation) Post-vote
Company Name
EDF Energy
Review status
Review required
Provision of data to the GES Provider
Date of latest update
Type
Issue
ID
I0302
Change Category
Change Path
Priority
Urgent
No
Latest Update
26/08/2026 On 26 August 2026, in line with the Code Manager's recommendation, TEP approved the extension to plan for I0302.
Summary
RECCo has commenced work on developing a dual-fuel Enquiry Service which will involve the migration of data from its legacy services.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Ahead of the introduction of a dual-fuel Enquiry Service and in the case that the GES Provider is not the same entity as the CDSP and GRDA, this Issue seeks to enable the migration of gas data from legacy services into a new physical interface.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
Workgroup
Workgroup(s)
I0302 submission form
I0302 Change Report (Proposal Plan) v1.0
I0302 Change Report (Update to Plan) v1.0 Approved 15.04.26
I0302 Change Report (Extension to Plan) v1.0 Approved 26.08.2026
Company Name
REC Code Manager
Review status
Review required
Amendments to D0312 to align with BSC CP1622
Date of latest update
Type
Change
ID
R0300
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
Elexon have raised CP1622 to amend the Validation rules within the Supplier Meter Registration Service (SMRS) for the Number of Register Digits Data Item within the IF-005 Market Message, to allow digit values from 1–9, ensuring accurate data and reducing exceptions. There are no Validation rules related to the D0312 Market Message which need to be amended under the Balancing and Settlement Code (BSC), but the D0312 itself contains a Data Item Rule regarding the Number of Displayed Register Digits which needs to be amended in line with CP1622.
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Amendments to D0312 red-lined data spec V0.1
Upload document
Amendments to D0312 red-lined data spec.docx
Archive
Off
Document title
Amendments to D0312 red-lined data spec V0.2
Upload document
Amendments to D0312 red-lined data spec V0.2.docx
Archive
Off
Document title
20260205 CP1622 R0300 industry workshop slides
Upload document
20260205 CP1622 R0300 industry workshop slides (1).pdf
Archive
Off
Problem Statement
BSC CP1622 is looking to address that SMRS cannot accurately update the Number of Displayed Register Digits for a SMETS2 Smart Electricity Meter due to Validation rules currently in place. The Validation rules proposed to be amended are those on the IF-005, which has direct impacts to the D0312.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0300 submission form
R0300 Change Report (Proposal Plan) V1.0
R0300 Consolidated Impact Assessment Responses PUBLIC v1.0
R0300 Update to Plan V1.0 approved 19.03.26
R0300 Change Report (For Consultation) V1.1
R0300 Consolidated Consultation Responses V1.0
R0300 Change Report (Final Recommendation) V1.0 approved 29.04.26
Company Name
Code Manager/CCSG
Review status
Review required
Data Latency Targets for the GES Service Definition
Date of latest update
Type
Change
ID
R0299
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal has been implemented as part of the June 2026 REC Release.
Summary
R0277 – Data Latency SLA alignment for Gas Enquiry Service amended two performance levels within the Gas Enquiry Service (GES) Service Definition. However, these changes only addressed ambiguity on when the performance level applied from and to and increased the number of hours in which data will be available to Authorised Persons within the Supply Point Switching API. This change will seek to support the changes made under R0277 whilst also providing a suitable percentage SLA target for the Gas Enquiry Service Provider to meet these measures.
Change Plan
Proposal Plan approved
Completed
Start:
Due:
17 Feb 2026Completion:
17 Feb 2026Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Date
26 June 2026
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0299 Legal Text for Consultation
Upload document
R0299 Legal Text for Consultation.zip
Archive
Off
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0299 submission form
R0299 Change Report v1.0 (Consultation) APPROVED
R0299 Change Report (Final Recommendation) v1.0 APPROVED
Company Name
REC Code Manager
Review status
Review required
Meter Manufacturers Make and Type not Populated in SMRS
Date of latest update
Type
Issue
ID
I0297
Change Path
Priority
Urgent
No
Latest Update
On 30 September 2026, the REC Technical Expert Panel voted to approve the Update to Plan for I0297, and to place this REC Issue on hold.
Summary
The Meter Manufacturers Make and Type (J0410 / DI-048) was not populated as part of the MHHS Programme's data cleanse. However it is part of the SMRS maintained Meter Technical Details (MTDs) for Smart Meters which replace the DTC MTD Market Messages for Smart Meters in the MHHS environment. It is not currently possible to populate this item in the legacy arrangements.
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
Following MHHS Migration, the MTDs provided by SMRS do not include the Meter Manufacturers Make and Type, as this replaces the existing D0149/D0150 Market Messages it could lead to the information being lost. This will mean Energy Suppliers and MOAs will not know the make and type of meter installed at a particular Site.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
I0297 submission form
I0297 Change Report (Proposal Plan) V1.0
I0297 Update to plan
I0297 Legal Drafting
I0297 Update to plan v1.0 Approved 30.09.26
Company Name
RECCo
Review status
Review required
Implementation of IF-051 Data Refresh in EES for BSC CP1607
Date of latest update
Type
Change
ID
R0294
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
28/10/2026 On 28 October 2026, the Technical Expert Panel voted, in line with the Code Manager’s recommendation, to approve the extension to plan for R0294. The Code Manager is working with the BSC on stakeholder workshops on a complete end-to-end solution, including the required market message specification, governance arrangements and operational processes. Stakeholder workshops will be held to run through the new ‘Data Refresh’ message, discuss the proposed change and gather stakeholder views on the full solution. The Code Manager will be attending these workshops to provide input on the new BSC CP, as well as impacts on the REC and REC services (primarily the Electricity Enquiry Services).
Summary
The IF-051 provides a refresh of data from Supplier Meter Registration Service (SMRS) to the Electricity Enquiry Service (EES) (REC) and Market Data Service (BSC). Currently the REC does not hold any detail regarding the DIP Market Messages that the EES is required to receive and process. Due to the nature of the IF-051, the EES Provider obligations need to be clear to ensure the interface can be received and processed appropriately.
Change Plan
Proposal Plan approved at REC Change Panel
Completed
Start:
Due:
16 Dec 2025Completion:
16 Dec 2025Consultation published
Completed
Start:
Due:
12 Feb 2026Completion:
12 Feb 2026Consultation closed
Completed
Start:
Due:
27 Feb 2026Completion:
27 Feb 2026Proposal Plan update approved by Technical Expert Panel
Completed
Start:
Due:
25 Mar 2026Completion:
25 Mar 2026Proposal Plan update approved by Technical Expert Panel
Completed
Start:
Due:
Completion:
28 Oct 2026Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
EES Service Definition v4.1 - redlined for IF-051
Upload document
EES Service Definition v4.1 - redlined for IF-051.pdf
Archive
Off
Document title
366_05B CP1607 IF-0XX_Proposed Data Refresh Flow v0.1
Upload document
366_05B CP1607 IF-0XX_Proposed Data Refresh Flow v0.1.pdf
Archive
Off
Document title
R0294 EES Service Definition REDLINED for Consultation
Upload document
R0294 EES Service Definition REDLINED for Consultation.pdf
Archive
Off
Document title
CP1629 Attachment C IF-051 Refresh Flow v2.0 REDLINED
Upload document
Attachment C IF-051 Refresh Flow v2.0 REDLINED.pdf
Archive
Off
Document title
R0294 Solution Development Report v1.0
Upload document
R0294 Solution Development Report v1.0.pdf
Archive
Off
Problem Statement
BSC CP 1607 will implement a new DIP Market Message, the IF-051 ‘Data Refresh’ on 26 March 2026. EES will be a recipient of that change. If EES is not able to receive and process instances of the IF-051, data in EES will be misaligned with other industry systems (SMRS, DIP and MDS) meaning that it will not maintain its role as the accurate reference point for industry participants. This could lead to potential disruption of industry processes.
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
R0294 Submission Form
R0294 Change Report (Proposal Plan) Approved v1.1 16.12.2025
R0294 Change Report (Consultation) Approved v1.0 04.02.2026
R0294 Consolidated Consultation Responses v1.0
R0294 - Change Proposal Re-Plan v1.0 (Approved) 25.03.2026
R0294 Change Report (Update to Plan) v1.0 Approved 07.07.26
R0294 Change Report (Update to Plan) v2.0 Approved 28.10.26
Company Name
REC Code Manager
Review status
Review required
Organisations with multiple role types EES and SDEP access
Date of latest update
Type
Issue
ID
I0285
Change Category
Change Path
Priority
Urgent
No
Latest Update
On 22 October 2026, the Code Manager published the I0285 Closure Report. Following a review of the responses to the Party impact assessment, the Code Manager has determined that this REC Issu can be moved to Resolved as there has been a lack of Parties indicating they would use the proposed solution under I0285. The enduring solution of one individual assigned to two company groups to use two separate email addresses for each company group will be sustained. RECCo will consider the requirement for a single login across multiple roles as part of the Enquiry Services Evolution project development.
Summary
It is currently not possible for organisations with multiple role types to have the same person be able to access all assigned role types within the Secure Data Exchange Portal (SDEP) without having a unique email address for each role type.
Change Plan
Change Report (Proposal Plan) approved by Change Panel
Completed
Start:
Due:
Completion:
04 Nov 2025Discussed at Technical Expert Panel
Completed
Start:
Due:
Completion:
17 Dec 2025Discussed at Technical Expert Panel
Completed
Start:
Due:
Completion:
28 Jan 2026Extension to Plan approved by Technical Expert Panel
Completed
Start:
Due:
Completion:
25 Feb 2026Discussed at Change Issues Group
Completed
Start:
Due:
Completion:
06 Aug 2026Impacted Consumers
Impacted REC Services
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
Zip file with I0285 legal text
Upload document
Legal text for Party IA (2).zip
Archive
Off
Document title
I0285 Solution Development Report V1.0
Upload document
I0285 Solution Development Report V1.0.pdf
Archive
Off
Problem Statement
Organisations with more than one role type are required to have unique email addresses for staff who require access to multiple role types, leading to inefficiencies, unnecessary administrative burdens and a poor user experience.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
I0285 submission form
I0285 Change Report (Proposal Plan) V1.0 approved 04.11.25
I0285 Extension to Plan V1.0 approved 25.02.26
I0285 Extension to Plan V2.0 approved 24.06.26
I0285 Consolidated Impact Assessment Responses v1.0
I0285_Closure Report
Company Name
REC Code Manager
Review status
Review required