Clarifications to the Theft Detection Incentive Scheme
Initial Assessment Report Issued
Start:
23 Jan 2023Due:
27 Jan 2023Completion:
27 Jan 2023Change Proposal Plan Issued
Start:
27 Jan 2023Due:
27 Jan 2023Completion:
27 Jan 2023Preliminary Change Report Issued
Start:
07 Feb 2023Due:
17 Feb 2023Completion:
17 Feb 2023Consultation Issued
Start:
17 Feb 2023Due:
17 Feb 2023Completion:
17 Feb 2023Responsible Committee Decision
Start:
17 Feb 2023Due:
24 Mar 2023Completion:
24 Mar 2023IAR and CPP Approval
Start:
27 Jan 2023Due:
07 Feb 2023Completion:
07 Feb 202301 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0047 | Metering Code of Practice Consolidation Review |
|
| R0025 | Service Provider Performance Charges (DCC) |
|
| R0073 | Introduction of a Housekeeping Change Proposal Process |
|
| R0084 | Housekeeping changes to the approved legal text for R0047 |
|
| R0091 | Clarifications to the Theft Detection Incentive Scheme |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an Energy Supplier, I need my TDIS obligations to be clear to ensure I can meet the requirements appropriately.
- As the Code Manager, I want all Suppliers to be clear on the required Energy Theft reporting so that the scheme can be effectively administered.
- As RECCo, I want to ensure that all Suppliers have clear obligations to ensure the effective administration of TDIS to support the Theft Reduction Strategy.
Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text
Solution Development
Start:
23 Jan 2023Due:
23 Feb 2023Completion:
23 Feb 2023Party Impact Assessment Issued
Start:
23 Feb 2023Due:
24 Feb 2023Completion:
24 Feb 2023Preliminary Change Report Issued
Start:
24 Feb 2023Due:
27 Mar 2023Completion:
24 Mar 2023Consultation Issued
Start:
27 Mar 2023Due:
27 Mar 2023Completion:
24 Mar 2023Final Change Report Issued
Start:
27 Mar 2023Due:
19 Apr 2023Completion:
19 Apr 2023Responsible Committee Decision
Start:
19 Apr 2023Due:
26 Apr 2023Completion:
30 June 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0101 | Revision of the Implementation Date and approved solution for R0021 |
|
| R0102 | Revision of the approved solution for R0032 |
|
| R0114 | Housekeeping amendments |
|
| R0015 | Remote communication obligations for electricity Advanced Meters |
|
| R0010 | New Meter Types for Auxiliary Proportional Controllers (APCs) |
|
| R0011 | Reporting of Additional EMR Backing Data to Suppliers |
|
| R0021 | Allowing REC accredited MEMs to de-energise and re-energise supply points independent of the Supplier |
|
| R0030 | Erroneous Transfer Cancellations |
|
| R0066 | Inclusion of SMRS Data Items in EES (BSC CP1568 Consequential Change) | |
| R0032 | New Registration data items and processes to support the transition to Market-wide Half-Hourly Settlement (MHHS) |
|
| R0090 | Alignment of Data Specification with Pre-REC Rules and Consequential Impacts on R0011 Legal Text |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Market Participant I want to have clarity on the format of Data Items within the Data Specification, so that my internal systems can be correctly configured to send and receive Data Items within Market Messages.
Make Shipper NExA values available on the GES portal
Initial Assessment and Change Proposal Plan issued
Start:
16 Jan 2023Due:
24 Mar 2023Completion:
24 Mar 2023Initial Assessment Report and Change Plan approved
Start:
24 Mar 2023Due:
04 Apr 2023Completion:
04 Apr 2023Service Provider Impact Assessment
Start:
04 Apr 2023Due:
25 Apr 2023Completion:
24 Apr 2023Party Impact Assessment
Start:
25 Apr 2023Due:
31 May 2023Completion:
31 May 2023Preliminary Change Report published
Start:
31 May 2023Due:
16 Jun 2023Completion:
16 Jun 2023Consultation
Start:
16 Jun 2023Due:
21 Jul 2023Completion:
21 Jul 2023Final Change Report published
Start:
21 Jul 2023Due:
18 Aug 2023Completion:
18 Aug 2023Responsible Committee decision
Start:
18 Aug 2023Due:
30 Aug 2023Completion:
30 Aug 202303 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0110 | A review of Supplier access to data on GES | |
| R0138 | Combined progression of Change Proposals R0058, R0104 and R0129 | |
| R0140 | Housekeeping amendments | |
| R0059 | Maintenance of Qualification Schedule Change |
|
| R0088 | Make Shipper NExA values available on the GES portal | |
| R0017 | Invalid Requests for Site Technical Details |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a Consumer, where I have entered a bi-lateral NExA with the relevant Transporter, I want my Shipper and Transporter to have access to all the data they need when capacity referrals to the Gas Transporters are required.
- As a Gas Transporter, I want the details of the NExA to be held in GES, to increase visibility of the existence of the NExA and to provide details of the offtake parameters.
- As a Gas Shipper, I need to understand both that a NExA exists, and that I have visibility of the offtake parameters relative to the site, so that I can ensure that I take the necessary actions to ensure the Consumer has the appropriate booked Supply Point Capacity.
MAP GES data access
Housekeeping changes to the approved legal text for R0047
Preliminary Change Report published and issued for Consultation
Start:
16 Dec 2022Due:
24 Feb 2023Completion:
24 Feb 2023Consultation ends
Start:
24 Feb 2023Due:
10 Mar 2023Completion:
10 Mar 2023Final Change Report published
Start:
10 Mar 2023Due:
21 Mar 2023Completion:
21 Mar 2023Responsible Committee decision (Ex-Committee)
Start:
21 Mar 2023Due:
24 Mar 2023Completion:
24 Mar 2023Appeal window closure
Start:
24 Mar 2023Due:
07 Apr 2023Completion:
01 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0047 | Metering Code of Practice Consolidation Review |
|
| R0025 | Service Provider Performance Charges (DCC) |
|
| R0073 | Introduction of a Housekeeping Change Proposal Process |
|
| R0084 | Housekeeping changes to the approved legal text for R0047 |
|
| R0091 | Clarifications to the Theft Detection Incentive Scheme |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a DNO, MEM, AMI, ASP or MI, I want all Code of Practice obligations to be clear and transparent, to ensure all obligations placed upon my organisation and operatives are understood and can be met in the most efficient way.
- As an Energy Supplier, I want to be confident that my Appointed agents are compliant with all relevant CoP obligations to ensure the safety of my Consumers.
- As RECCo, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
- As the Metering Scheme Auditor, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
Formalising the Submission of PPMIP Unallocated Transaction Report (UTR) Files
Solution analysis and development
Start:
28 Nov 2022Due:
12 Jan 2024Completion:
11 Jan 2024Service Provider Impact Assessment start date
Start:
12 Jan 2024Due:
15 Jan 2024Completion:
15 Jan 2024Service Provider Impact Assessment close
Start:
15 Jan 2024Due:
11 Mar 2024Completion:
11 Mar 2024- As a PPMIP, I want to have clear guidance on how and when I should submit my Unallocated Transaction Report files.
- As a Supplier, I want to receive accurate Unallocated Transactions in relation to prepayment meters that are not smart meters.
- As the Code Manager, I want visibility of the Unallocated Transaction Report.
- As the EES Provider, I want to be able to efficiently upload the Unallocated Transaction Reports.
Improvements to ‘Failed to Deliver’ CSS Messages
Service Provider Impact Assessment close
Start:
09 Nov 2022Due:
25 Jan 2024Completion:
25 Jan 2024Party Impact Assessment trigger
Start:
25 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Party Impact Assessment close
Start:
02 Feb 2024Due:
23 Feb 2024Completion:
23 Feb 2024Preliminary Change Report and Consultation issued
Start:
23 Feb 2024Due:
10 May 2024Completion:
10 May 2024Consultation close
Start:
10 May 2024Due:
03 Jun 2024Completion:
03 Jun 2024Responsible Committee Decision
Start:
24 Jul 2024Due:
31 Jul 2024Completion:
31 Jul 2024Final Change Report Issued
Start:
03 Jun 2024Due:
24 Jul 2024Completion:
19 Jul 202428 June 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0155 | Change of Occupier: Evidentiary Standards and Timescales |
|
| R0193 | Add Enumeration Values to the DI51035 - Communications Provider Data Item |
|
| R0202 | Performance Assurance Report Catalogue Updates (MHHS) | |
| R0225 | Clarification on TDIS portfolio transfers on sale |
|
| R0233 | Introduction of an Energy Theft Unit (ETU) under the REC | |
| R0234 | Introduction of an energy theft Referral Assessment Service under the REC | |
| R0236 | REC Party Auto de-accession proposal |
|
| R0238 | Performance Assurance Reporting Catalogue - Annual Review | |
| R0249 | Correction to Change Management Schedule regarding sub-committee voting |
|
| R0258 | Housekeeping June 2025 | |
| R0080 | Improvements to ‘Failed to Deliver’ CSS Messages |
|
- As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
- As the CSS Provider I want the messages I send to CSS Users to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
- As the CSS User I want to receive CSS messages in a timely manner following any outage of my own gateway or systems, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
Addition of Previous MEM to the EES API
EMR Settlement Limited - additional access to EES
SERVICE PROVIDER IMPACT ASSESSMENT ISSUED
Start:
26 Oct 2022Due:
07 Jul 2023Completion:
11 Aug 2023PRELIMINARY CHANGE REPORT AND CONSULTATION ISSUED
Start:
07 Jul 2023Due:
18 Aug 2023Completion:
18 Aug 2023FINAL CHANGE REPORT ISSUED
Start:
18 Aug 2023Due:
08 Sep 2023Completion:
08 Sep 2023RESPONSIBLE COMMITTEE DECISION
Start:
08 Sep 2023Due:
15 Sep 2023Completion:
15 Sep 202329 September 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0078 | EMR Settlement Limited - additional access to EES |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
- As EMRS I want to have an appropriate understanding of the portfolio so that I am able to complete metering assessments and checks on Switches so that I can fulfil my role.
- As the EES Provider I want to be able to provide access to EMR Settlement Limited as set out in the Data Access Matrix.
Release of Community View Data Items to MEMs in GES
Service Provider Impact Assessment
Start:
05 Oct 2022Due:
21 Nov 2022Completion:
16 Dec 2022Party Impact Assessment
Start:
21 Nov 2022Due:
21 Nov 2022Completion:
18 Dec 2022Preliminary Change Report Issued
Start:
21 Nov 2022Due:
13 Jan 2023Completion:
13 Jan 2023Consultation closure
Start:
13 Jan 2023Due:
27 Jan 2023Completion:
27 Jan 2023Responsible Committee Decision
Start:
27 Jan 2023Due:
22 Feb 2023Completion:
22 Feb 202324 February 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0052 | GES Service Definition Document | |
| R0055 | Switching Operator Outage Notification Lead time |
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 |
- As a Consumer, I want a Metering Equipment Manager to be able to access and validate my site details, ahead of their arrival on site for planned or emergency metering work, so that I do not experience any delays in work being completed and can have continuity of supply.
- As a MEM, I want access to sufficient data for sites where I am not the Appointed MEM, to enable me to complete pre-metering works validations of the site details, so I can undertake these works correctly and safely.
- As a MEM, I want access to data for sites where I am not the Appointed MEM, so I can confirm de-appointments and answer invoice validation queries.