REC Main Body 3.14
– Implemented on
Loading...
REC Main Body 3.13
– Implemented on
Loading...
REC Main Body 3.12
– Implemented on
Loading...
Smart Meter Communication Licence Code Changes
Date of latest update
Type
Change
ID
R0333
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented on 01 October 2026.
Summary
Ofgem has awarded the Smart Meter Communications Licence 2 (SMCL2) to DCC2 Limited, a subsidiary of Smart Energy Code Company Limited (SECCo). To enable a smooth transition and ensure continuity of service, changes to both the Smart Energy Code (SEC) and the Retail Energy Code (REC) will be required.
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
R0333 - Legal Text V1.1 28.08.26
Upload document
R0333 - Legal Text V1.1 28.08.26.pdf
Archive
Off
Document title
R0333 - Legal Text V1.0 28.07.26
Upload document
I0333 - Legal Text V1.0 28.07.26 (1).pdf
Archive
Off
Stages Selection
SME
SME Role
Lead Assurance Analyst
I0333 Submission Form (PDF)
R0333 Change Report (Consultation) (Approved) 04.08.26
R0333 Consolidated Consultation Responses V1.0 08.09.26
R0333 Change Report (Final Recommendation) (Post-Vote) 15.09.26
Company Name
Code Manager RPS
Review status
Review required
In-year CRS budget amendment
Date of latest update
Type
Change
ID
R0309
Change Path
Urgent
No
Latest Update
17/02/2026 - Change Panel approved this Change Proposal for implementation with immediate effect.
Summary
DCC has identified that the CRS budget for the current Financial Year (2025-2026) can be reduced, and as per the Code, a REC Change Proposal must be raised for the agreed budget to be amended.
Status
Implementation Status
Date Raised
REC Decision Maker
Solution Development
Stages Selection
R0309 submission form
R0309 Change Report (Final Recommendation) approved 17.02.26
Company Name
Smart DCC
Review status
Review required
REC Main Body 3.11
– Implemented on
Loading...
Establishing the Safe Isolation Provider (SIP) as a Standalone REC Party
Date of latest update
Type
Issue
ID
I0278
Change Category
Other Industry Codes impacted
Change Path
Priority
Urgent
No
Latest Update
21/07/2026 - An Update to Plan has been approved by the Change Panel on 21 July 2026.
Summary
This proposal recommends the formal recognition of the Safe Isolation Provider (SIP) as a standalone Party under the Retail Energy Code (REC). This aligns with the direction set out in Ofgem’s recently published Strategic Direction Statement (SDS), which explicitly calls for the establishment of SIPs as a standalone Party role. The aim is to address the growing scale of unregulated SIP activity, mitigate associated consumer safety risks, and ensure the metering industry is equipped to support the UK’s Net Zero ambitions. By enabling easier access to certified SIPs, this change will enhance consumer protection, accelerate low-carbon technology deployment, and improve operational efficiency across the energy sector.
Impacted Consumers
Impacted REC Documents
Impacted REC Parties and Market Participants
Status
Status
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Problem Statement
The current SIP framework poses several risks: - Consumers, MEMs and unaccredited practitioners’ safety. Unaccredited and unregulated isolation work increases the risk of unsafe installations and potential harm to Consumers. NAPIT highlighted to RECCo and DESNZ that 17 and 13 unregulated practitioners respectively died in 2023 and in 2024 due to unsafe isolation. With the right Party undertaking this work, there would also be less safety issues for the Consumer at their premises; - Inequity. Independent Installers face longer wait times compared to supplier-led installations, creating a two-tier system; - Low competitive market. Currently prospective Parties can be put off from applying to be a SIP as it appears they would need full MEM Accreditation which is often too far outside their current business operating model. Providing SIPs with their own pathway and requirements could result in more Parties becoming SIPs and therefore giving Consumers more choice in their provider; and - Decarbonisation delays. The inability to scale SIP capacity undermines the timely deployment of LZCTs, threatening Net Zero targets.
Stages Selection
Stages Selection
SME
SME Role
Lead Technical Analyst
SME Role
Lead Assurance Analyst
SME User
amoden@deloitte.co.uk
I0278 submission form
I0278 Change Report (Proposal Plan) V1.0 (Pre-Approval) 09.10.2025
I0278_Change Report (Extension to Plan) v1.0 (Pre-Approval) 12.01.2026
I0278_Change Report (Extension to Plan) v2.0 (Pre-Approval) 13.07.2026
I0278_Change Report (Extension to Plan) v2.1 (Approved) 21.07.26
I0278_Consolidated Information Request DNO Responses
I0278_Consolidated Information Request MEM-SIP Responses PUBLIC
I0278_Consolidated Information Request RPA Responses
Company Name
RECCo
Review status
Review required
REC Main Body 3.10
– Implemented on
Loading...
Change to REC for Data processing outside of EEA
Date of latest update
Type
Change
ID
R0257
Change Category
Change Path
Priority
Urgent
No
Latest Update
This Change Proposal was implemented as part of the 7 November 2025 REC Release.
Summary
There is an added layer of authorisation to the processing of data outside of the European Economic Area (EEA) which provides no value to the process. The issue is specifically around 20.8) point a) which requires REC Board Approval prior to any processing.
Status
Implementation Date
07 November 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0152 | Revision to the Consolidated Metering Code of Practice (CoMCoP) |
|
| R0157 | Removal of Facsimile as a Method of Code Communication |
|
| R0191 | Introduction of SLA for Supplier De-Registration on Disconnected Meters |
|
| R0205 | Provision of Half-Hourly Consumption Data for Advanced Meter Erroneous Switches | |
| R0212 | Protecting Crimestoppers and their Contacts | |
| R0215 | Schedule 30 Switch Meter Reading Problems - Rejections and Timings |
|
| R0060 | ERDS Service Definition timezone correction |
|
| R0232 | Non-Domestic Change of Occupier SDEP Screens (R0155 Solution) | |
| R0243 | Transfer of Standard Settlement Configuration and Time Pattern Regime Data Item Ownership |
|
| R0248 | REC Changes to tie in with DCP451 - Suspending Registrations |
|
| R0254 | Non-Domestic Change of Occupier Reporting (R0155 Solution) | |
| R0255 | Terms of Reference Updates | |
| R0257 | Change to REC for Data processing outside of EEA | |
| R0263 | Sharing Confirmed Energy Theft Data with the BSCCo |
|
| R0269 | Schedule 5 – Change Management: Clarity and Typographical Review |
|
| R0279 | Housekeeping November 2025 |
|
| R0227 | Domestic Elective HH Switching |
|
Implementation Status
Date Raised
Fuel
REC Decision Maker
Solution Development
Proposed Solution Document
Document title
I0257 Legal drafting (27/05/2025)
Upload document
I0257 Legal drafting (1).doc
Archive
Off
Document title
R0257 Legal drafting
Upload document
R0257 Legal drafting.docx
Archive
Off
Problem Statement
This Issue was raised by RECCo’s Data Protection Officer who noted that the addition of the extra layer of approval delays the process for Parties in processing this data, and it does not align with similar changes for the Balancing and Settlement Code (BSC), where board approval is not required.
Stages Selection
Proposal Form
I0257 Change Report (Proposal Plan) Approved 03/06/2025
R0257 Change Report (For Consultation)
R0257 Consolidated Consultation Responses
R0257 Change Report (Final Recommendation) (Approved) 05.08.2025
Company Name
RECCo
Review status
Review required
REC Main Body 3.9
– Implemented on
Loading...