ERDS Upload File in the Data Specification and clarification of cancellation code
Housekeeping changes to the approved legal text for R0047
Preliminary Change Report published and issued for Consultation
Start:
16 Dec 2022Due:
24 Feb 2023Completion:
24 Feb 2023Consultation ends
Start:
24 Feb 2023Due:
10 Mar 2023Completion:
10 Mar 2023Final Change Report published
Start:
10 Mar 2023Due:
21 Mar 2023Completion:
21 Mar 2023Responsible Committee decision (Ex-Committee)
Start:
21 Mar 2023Due:
24 Mar 2023Completion:
24 Mar 2023Appeal window closure
Start:
24 Mar 2023Due:
07 Apr 2023Completion:
01 April 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0047 | Metering Code of Practice Consolidation Review |
|
| R0025 | Service Provider Performance Charges (DCC) |
|
| R0073 | Introduction of a Housekeeping Change Proposal Process |
|
| R0084 | Housekeeping changes to the approved legal text for R0047 |
|
| R0091 | Clarifications to the Theft Detection Incentive Scheme |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a DNO, MEM, AMI, ASP or MI, I want all Code of Practice obligations to be clear and transparent, to ensure all obligations placed upon my organisation and operatives are understood and can be met in the most efficient way.
- As an Energy Supplier, I want to be confident that my Appointed agents are compliant with all relevant CoP obligations to ensure the safety of my Consumers.
- As RECCo, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
- As the Metering Scheme Auditor, I want the Metering Scheme obligations to be clear and transparent, to ensure the arrangements deliver against the RECCo strategic aims.
Formalising the Submission of PPMIP Unallocated Transaction Report (UTR) Files
Solution analysis and development
Start:
28 Nov 2022Due:
12 Jan 2024Completion:
11 Jan 2024Service Provider Impact Assessment start date
Start:
12 Jan 2024Due:
15 Jan 2024Completion:
15 Jan 2024Service Provider Impact Assessment close
Start:
15 Jan 2024Due:
11 Mar 2024Completion:
11 Mar 2024- As a PPMIP, I want to have clear guidance on how and when I should submit my Unallocated Transaction Report files.
- As a Supplier, I want to receive accurate Unallocated Transactions in relation to prepayment meters that are not smart meters.
- As the Code Manager, I want visibility of the Unallocated Transaction Report.
- As the EES Provider, I want to be able to efficiently upload the Unallocated Transaction Reports.
CSS Market Message Retry Strategy
Improvements to ‘Failed to Deliver’ CSS Messages
Service Provider Impact Assessment close
Start:
09 Nov 2022Due:
25 Jan 2024Completion:
25 Jan 2024Party Impact Assessment trigger
Start:
25 Jan 2024Due:
02 Feb 2024Completion:
02 Feb 2024Party Impact Assessment close
Start:
02 Feb 2024Due:
23 Feb 2024Completion:
23 Feb 2024Preliminary Change Report and Consultation issued
Start:
23 Feb 2024Due:
10 May 2024Completion:
10 May 2024Consultation close
Start:
10 May 2024Due:
03 Jun 2024Completion:
03 Jun 2024Responsible Committee Decision
Start:
24 Jul 2024Due:
31 Jul 2024Completion:
31 Jul 2024Final Change Report Issued
Start:
03 Jun 2024Due:
24 Jul 2024Completion:
19 Jul 202428 June 2025
| Included changes | Affected REC Items | |
|---|---|---|
| R0155 | Change of Occupier: Evidentiary Standards and Timescales |
|
| R0193 | Add Enumeration Values to the DI51035 - Communications Provider Data Item |
|
| R0202 | Performance Assurance Report Catalogue Updates (MHHS) | |
| R0225 | Clarification on TDIS portfolio transfers on sale |
|
| R0233 | Introduction of an Energy Theft Unit (ETU) under the REC | |
| R0234 | Introduction of an energy theft Referral Assessment Service under the REC | |
| R0236 | REC Party Auto de-accession proposal |
|
| R0238 | Performance Assurance Reporting Catalogue - Annual Review | |
| R0249 | Correction to Change Management Schedule regarding sub-committee voting |
|
| R0258 | Housekeeping June 2025 | |
| R0080 | Improvements to ‘Failed to Deliver’ CSS Messages |
|
- As a Consumer, I want the Switching process to work successfully, so that I can switch Energy Supplier without delays or issues.
- As the CSS Provider I want the messages I send to CSS Users to be received and processed successfully, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
- As the CSS User I want to receive CSS messages in a timely manner following any outage of my own gateway or systems, so that there is no interruption to the Switching process or the Consumers’ Switching experience.
DNOs notifying Suppliers about Crossed Meters
Introduction of a new Meter Asset Condition Code
Provision of Enduring Test Environments
Solution Analysis and Development
Start:
09 Sep 2022Due:
06 Jun 2023Completion:
06 Jun 2023Service Provider Impact Assessment Period
Start:
06 Jun 2023Due:
06 Oct 2023Completion:
06 Oct 2023Service Provider Impact Assessment
Start:
24 Nov 2023Due:
03 Jan 2024Completion:
03 Jan 2024Party Impact Assessment Issued
Start:
06 Oct 2023Due:
24 Nov 2023Completion:
24 Nov 2023Preliminary Change Report Issued
Start:
03 Jan 2024Due:
16 Jan 2024Completion:
16 Jan 2024Responsible Committee Review
Start:
16 Jan 2024Due:
23 Jan 2024Completion:
23 Jan 2024Consultation Issued
Start:
23 Jan 2024Due:
26 Jan 2024Completion:
26 Jan 2024Final Change Report Issued
Start:
26 Jan 2024Due:
23 Feb 2024Completion:
23 Feb 2024Responsible Committee Decision
Start:
23 Feb 2024Due:
05 Mar 2024Completion:
05 Mar 202428 June 2024
| Included changes | Affected REC Items | |
|---|---|---|
| R0043 | Commissioning of Works by the Crowded Meter Room Coordinator (CMRC) to Resolve Issues In Crowded Meter Rooms |
|
| R0158 | Amendment to the ‘Supplier Registration Report (MAP)’ report methodology | |
| R0160 | Electricity Supply to Hydrogen Electrolysers |
|
| R0064 | Creating a Meter Operator Agent and MOCoP Installer |
|
| R0070 | Provision of Enduring Test Environments |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 16 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As a CSS User I want access to a CSS Test Environment, to enable me to test my systems and processes ahead of the implementation of complex or significant changes, so that I can identify any issues prior to go-live.
- As the SO, I want clarity on the obligations placed on me regarding the provision and maintenance of CSS Test Environments and data, so that I can meet my obligations and provide CSS Users and Service Providers with access to appropriate Test Environments.
- As a Switching Data Service Provider (SDSP), I want clarity on the obligations placed on me regarding the provision and maintenance of Test Environments and data, so that I can meet my obligations to test CSS changes. As a Switching Data Service Provider (SDSP), I want access to a CSS Test Environment, to enable me to test my systems and processes ahead of the implementation of complex or significant changes, so that I can identify any issues and address prior to go-live.
Resolution of invalid CSS data by Data Owners
Solution Analysis and Development
Start:
22 Aug 2022Due:
15 Aug 2023Completion:
15 Aug 2023Service Provider Impact Assessment Due
Start:
15 Aug 2023Due:
19 Oct 2023Completion:
19 Oct 2023- As a Consumer, I want data relating to my energy supply to be accurate, so that I can have a consistent and faultless switching experience. As a Consumer, I want any data issues related to my switch to be resolved quickly and by the party responsible, to ensure a fast and efficient switching experience.
- As a DNO, I want my service level requirements to be reflective of my data ownership responsibilities, so that data queries can be resolved more efficiently. As the CSS Service Desk provider, I want my tickets to be allocated to the most appropriate party able to resolve them.
Maintenance of Qualification Schedule Change
Solution Development
Start:
05 Aug 2022Due:
01 Mar 2023Completion:
01 Mar 2023Impact Assessment Start
Start:
01 Mar 2023Due:
10 Mar 2023Completion:
10 Mar 2023Impact Assessment End
Start:
10 Mar 2023Due:
24 Mar 2023Completion:
24 Mar 2023Preliminary Change Report Issued
Start:
24 Mar 2023Due:
14 Apr 2023Completion:
14 Apr 2023Responsible Committee Review
Start:
14 Apr 2023Due:
25 Apr 2023Completion:
25 Apr 2023Consultation Start
Start:
25 Apr 2023Due:
28 Apr 2023Completion:
28 Apr 2023Consultation End
Start:
28 Apr 2023Due:
22 May 2023Completion:
22 May 2023Final Change Report Issued
Start:
22 May 2023Due:
16 Jun 2023Completion:
15 Jun 2023Responsible Committee Decision
Start:
16 Jun 2023Due:
27 Jun 2023Completion:
27 Jun 2023Appeal Window Closure
Start:
27 Jun 2023Due:
11 Jul 2023Completion:
03 November 2023
| Included changes | Affected REC Items | |
|---|---|---|
| R0110 | A review of Supplier access to data on GES | |
| R0138 | Combined progression of Change Proposals R0058, R0104 and R0129 | |
| R0140 | Housekeeping amendments | |
| R0059 | Maintenance of Qualification Schedule Change |
|
| R0088 | Make Shipper NExA values available on the GES portal | |
| R0017 | Invalid Requests for Site Technical Details |
|
Documents
| Name | Version | Last updated | Actions |
|---|---|---|---|
| 1.0 | 02 Nov 2026 | ||
| 1.0 | 02 Nov 2026 |
- As an Energy Supplier, DNO, GT, MEM and REC Service User, I want to understand precisely what obligations apply to me under the Schedule 9 – Qualification and Maintenance, so that I can provide the required information to the Code Manager in a timely manner and be compliant.
- As the REC Code Manager, I want REC Parties and REC Service Users to have a clear understanding of the information they need to submit relating to the maintenance of their qualification, so that necessary information can be submitted for review and consideration in the most efficient way.